        <article-title>Operations architecture modeling for IT-driven organizational development of a construction company</article-title>
      </title-group>
      <contrib-group>
        <contrib contrib-type="author">
          <string-name>Dmitry Kudryavtsev1,2</string-name>
          <email>d.v.kudryavtsev@gsom.pu.ru</email>
          <xref ref-type="aff" rid="aff1">1</xref>
        </contrib>
        <contrib contrib-type="author">
          <string-name>Maxim Arzumanyan1</string-name>
          <email>maxim.arzumanyan@gmail.com</email>
          <xref ref-type="aff" rid="aff0">0</xref>
        </contrib>
        <aff id="aff0">
          <label>0</label>
          <institution>1 EA Lab, Interuniversity Academic Center of Excellence</institution>
          ,
          <addr-line>on Enterprise Architecture</addr-line>
          ,
          <country country="RU">Russia</country>
        </aff>
        <aff id="aff1">
          <label>1</label>
          <institution>1 EA Lab, Interuniversity Academic Center of Excellence, on Enterprise Architecture, Russia, 2 Graduate School of Management, Saint-Petersburg State University</institution>
          ,
          <country country="RU">Russia</country>
        </aff>
      </contrib-group>
      <pub-date>
        <year>2016</year>
      </pub-date>
      <fpage>23</fpage>
      <lpage>32</lpage>
      <abstract>
        <p>The case report describes a business architecture-driven project of IT implementation planning for a medium-sized Russian construction company. The fictitious name “BuildIt” will be used for the company for confidentiality purposes. Although the project took place in 2012, many raised issues are still relevant for companies in the region. The report will describe the company at the moment when the project took place. BuildIt company deals with design and construction of non-residential buildings (industrial facilities, schools, theaters, museums, libraries, etc.). The company's portfolio involves many unique facilities. At the beginning of the project its portfolio included five large-scale projects whose total cost amounted to $200 million. There are about 1000 employees in the company, and the payroll budget amounts to $1.5 million per month. One should consider that this amount excludes workers (constructors) since the company acts as a general contractor meaning the very works are carried out by subcontractors, some of them dealing with windows, others doing concrete works, etc. The company's projects are comprehensive and complicated: they involve different works related to a facility's lifetime, as well as different subsystems of a facility under construction (heat supply, electric power supply, water supply, IT infrastructure, etc.). Such projects require interaction and joint work of different divisions. Sometimes their interaction is hindered by political, administrative, and cultural factors.</p>
      </abstract>
    </article-meta>
  </front>
  <body>
    <sec id="sec-1">
      <title>Context</title>
      <p>any sense in the Company's strategy development. However, the company has managed to develop a really unique value
proposition. The closest competitor who also builds complicated facilities in the region is far behind BuildIt.
2</p>
    </sec>
    <sec id="sec-2">
      <title>Problem description</title>
      <p>Project schedules are often violated due to ill planning and weak control over the situation. The Company’s Director is
incapable of controlling everything and struggles for automation viewing it as a way out. Keywords: “Task management”,
"Task, responsible person, deadline". Management cycle is linked to weekly management meetings on various issues; tasks are
set within such meetings and controlled within later meetings. Formalized processes are almost absent. Task and document
management automation is the first intuitive request of the BuildIt management.</p>
      <p>Until recently IT didn't develop in the company. There is only a department of system administrators, which provides
maintenance and support for equipment and several systems (CAD systems and some 1C modules). The company is ready to
invest in IT, but is not always ready for organizational changes. Recently, BuildIt started to pay increased attention to IT as a
means of performance improvement.</p>
      <p>The company invited consultants on ERP systems implementation, but they did not manage to persuade the managers.
Their proposal was limited to ERP and included a sequential deployment of ERP modules. BuildIt managers anticipated many
risks and knew about many failures in complex ERP implementation, so they doubted the feasibility of standardized
step-bystep deployment of a rigid integrated system at their company. Additionally, BuildIt managers heard about other types of
information systems (e.g. Workflow management system) and were thinking about their usage. The implementation approach
was also unclear – what modules of ERP would be based on best practices and what modules would keep and automate the
existing BuildIt practices. Finally, BuildIt director invited new consultants – the authors of the paper with the team. He
expected to receive a less ERP-biased approach with more solid foundations.</p>
      <p>The final goal of the project was to implement IT in order to make the management and control system in the organization
more effective.</p>
      <p>In order to achieve this goal, it was necessary to answer the following questions:
• What should be the directions for IT development in the company?
• What should be the target state of IT support?
• How to attain the target state?</p>
      <p>In addition to these conceptual questions, which are associated with IT strategy, it was necessary to specify requirements
for the most urgent information system (IS).
3
3.1</p>
    </sec>
    <sec id="sec-3">
      <title>Solution</title>
    </sec>
    <sec id="sec-4">
      <title>Approach</title>
      <p>We suggested an approach which had several important features:
1. Componentized architecture of business operations was used for comprehensive analysis of the current state and for
planning the target state of the company. The analysis and planning employed an effective visual technique – heat
maps;
2. A specialized modeling tool was used in order to systematize and integrate the results of the analysis and planning of
enterprise architecture;
3. Special attention in the project was paid to “soft” issues: organizational culture and management style were analyzed
in order to set priorities in IS implementation.</p>
      <p>1. Componentized architecture of business operations, or simply operations architecture, as it was named in the project, was
based on the paper [Sanz et al, 2011]. During the development of this architecture we also reused ideas from [Kudryavtsev,
Grigoriev, 2011]. Operations architecture is a part of business architecture and was used for structuring problematic areas,
identifying strategically important areas, mapping of existing IT support, setting the priorities for IT implementation, etc.</p>
      <p>Operations component was considered as a group of interrelated activities, which are supported by the corresponding IS,
resources, organizational roles, etc. Such discrete modules can be shared across the firm. The componentized architecture of
business operations realizes the principle of resource aggregation and complexity reduction, thus yielding a componentized or
modularized approach to business operations.</p>
      <p>The first aspect of modularization is based on the notion of competence. For example, Upstream is a competence of a
typical oil and gas industry; Water Procurement is a competence in the water segment of the utilities industry; Health Care and
Environment are competences in the city government segment of the public industry; Customer Service is a typical
competence where services matter, which, thus, takes place in a variety of industry segments such as banking and
telecommunications; and so on. The other aspect of modularization is based on a typology of the enterprise activities. This
dimension leads to a partition into four levels. These levels correspond to four broad categories of activities involved in
creating the following outcomes: vision and strategy, learning and innovation, oversight and management, and production and</p>
      <p>Having identified and organized the business operations into a componentized architecture, we started to apply this model
for business analysis and planning.</p>
      <p>
        There are two techniques to consider [Pohle et al, 2005; Business Architecture Guild, 201
        <xref ref-type="bibr" rid="ref5">5; The Open Group, 2016</xref>
        ]:
1. Heat mapping the componentized architecture of business operations itself;
2. Mapping the relationships between the operations components and other business and IT architecture domains.
      </p>
      <p>Heat mapping helps identify opportunities for business improvement or investment. It visually highlights components that
are performing at a sub-optimal level, or that might not exist in a form that is required to meet some future strategic need.</p>
      <p>The second approach helps to strengthen alignment across different parts of the business, ensuring that what the business
wishes to do is: reflected in the company’s strategic and operational objectives (the why); supported by the appropriate
systems, processes, information, and organizational structure (the how and where).</p>
      <p>These techniques were used in BuildIt for identifying priority areas for IT implementation, planning target IT support, and
structuring the expected impact of development projects.</p>
      <p>2. Specialized modeling tool ORG-Master was used in order to systematize the results of diagnostics and planning of the
enterprise architecture [Grigoriev, Kudryavtsev, 2013].</p>
      <p>Fig. 3 demonstrates the main objects of the enterprise model we used. It includes business operations components, goals &amp;
objectives, information systems (IS) and their functions, etc. These objects are represented using classifications (hierarchical
lists). Relationships between the objects of different types are represented using matrices (linking two or more hierarchical
lists) – for example, operation components help achieve some objectives.</p>
      <p>The developed model provided multifaceted representations of BuildIt enterprise architecture and enabled the generation of
different reports, which became the foundation for heat maps and final recommendations. The usage of a specialized modeling
tool significantly improved the speed and quality of diagnostics and design of the target enterprise architecture.</p>
      <p>3. In addition to enterprise architecture modeling and analysis, we decided to pay attention to “softer” issues. Initial
meetings with BuildIt representatives demonstrated that it was necessary to take into account the organizational culture,
management style, and level of capability maturity when selecting the IT implementation policy/conception. Rigid
formalization and control (which is necessary for an integrated ERP system) is not suitable for all companies or may be
limited. In order to mitigate these risks, we evaluated the corporate culture of BuildIt using Cameron &amp; Quinn [2006] method
(see Fig. 4) and analyzed the current and the desired style of work organization.
With respect to all the aforementioned features of the approach, we suggested the following way of working– see Fig. 5.</p>
      <p>IT-driven transformation program and requirement specifications for pilot projects were the most interesting deliverables
for managers since the goal of the project was to implement IT in order to make the management and control system in the
organization more effective. In order to receive these deliverables, it was necessary to analyse/diagnose the current state of
BuildIt business and IT architecture, organizational culture, and management style, identify problems and their causes. Best
practices and IT trends were also analysed in order to reflect world knowledge and experience in BuildIt plans. Planning
included both conceptual decisions (e.g. about the priorities in the categories of IS) and more specific issues – what operations
components should be supported by IT first of all, what IS categories and specific vendors can provide such a support, what
development projects must be initiated, and how to implement them.</p>
      <p>We used the following data collection methods at BuildIt:
• Interviews with top managers and relevant specialists of the company;
• Surveys – several online questionnaires were rolled out (about BuildIt problems, their causes and possible solutions;
organizational culture; work organization and management style);
• Observation and ethnography (e.g. participation in weekly management meetings, meetings at different construction
objects, etc.);
• Analysis of documents (regulatory documents, etc.) and BuildIt website.</p>
      <p>Multiple sources of evidence and data gathering in “triangulating fashion” helped to take into account the interests and
interpretations of different stakeholders – this enabled us to develop a balanced transformation program and minimize risks.
3.2</p>
    </sec>
    <sec id="sec-5">
      <title>Application of the suggested approach</title>
      <p>According to the suggested approach we developed the componentized architecture of business operations for BuildIt (Fig. 6)
and used it for the following analysis and planning.</p>
      <p>This analysis and planning applied heat map and relationship mapping techniques and included several interrelated steps
(Fig. 7). In the beginning heat maps for problematic and strategically important areas (components) were developed. They
helped to define critical areas (problematic and strategically important ones). Then the potential for IT support was evaluated
for critical areas. On the other hand, the analysis of the existing IT architecture resulted in a map which demonstrates
relationship between operations components and IS – existing IT support. Priority areas (components) for IT implementation
were defined by taking into account criticality, existing IT support, and potential for IT support. Prerequisites and dependencies
were also considered. Finally, IS (mostly categories, but also modules of 1C:Enterprise1), which can support priority areas,
were mapped to the componentized architecture of business operations. This mapping became the basis for creating the project
portfolio, identifying quick wins, and planning transformation.
1 1C:Enterprise 8 is a popular Russian system, which includes ERP modules and can be used for overall enterprise automation,
http://1c.ru/eng/.</p>
      <p>The evaluation of components for heat maps was done through the analysis of enterprise data (see data collection methods)
and more detailed study of relationships between objects using the enterprise architecture management tool ORG-Master. For
example, we identified strategically important areas (components) through the analysis of relationships between the operations
architecture and objectives (see Fig. 8).</p>
      <p>One of the questionable things was ERP implementation. Since BuildIt organizational culture appeared distinct from the
hierarchical control-oriented type (see Fig. 4) and the level of capabilities maturity was low, the project team saw high risks in
overall ERP implementation. In order to mitigate these risks, it was decided to use workflow management system (WFMS) for
automating some areas, especially at the beginning of active IT implementation. WFMS can support the same business
processes as ERP and provide more flexibility – processes can be changed by business users and implemented in the system.
In spite of this flexibility, WFMS is not a complete substitute for ERP since the latter works with structured information, can
do calculations, supports data integration, and provides functionality for analytics and decision support system. So in some
areas of BuildIt operations WFMS was considered as an intermediate step (e.g. making an order of construction materials),
which would establish organizational readiness for more mature IT support.
1С
1С
1С
1С
SAP
SAP</p>
      <sec id="sec-5-1">
        <title>Ensure timely delivery, storage, and retrieval of documents</title>
      </sec>
      <sec id="sec-5-2">
        <title>Provide performance discipline</title>
      </sec>
      <sec id="sec-5-3">
        <title>Provide performance discipline</title>
      </sec>
      <sec id="sec-5-4">
        <title>Provide relevant information for applicants about the status of their material request</title>
      </sec>
      <sec id="sec-5-5">
        <title>Raise awareness of managers</title>
        <p>and employees at facilities
Raise
managers
awareness
of
top</p>
        <p>The suggested IT implementation projects were evaluated based on three main criteria – potential impact, implementation
complexity (with respect to other organizational factors), and costs. The final project portfolio included 25 projects. Projects
from “quick wins” category can be found in Table 1.</p>
        <p>Finally, a transformation program was suggested – see Fig. 9. The horizontal axis represents time, and all the projects are
distributed between three stages: quick wins (immediate implementation), tactical, and strategic perspective. The vertical axis
corresponds to the areas of business operations.
As far as there are no regularly measured performance indicators for internal processes at BuildIt, the effects of the described
project can be assessed only qualitatively. The suggested transformation program (for IT implementation) was positively
evaluated by BuildIt management. Projects from “quick wins” category were successfully implemented.</p>
        <p>
          Lessons learned are the following:
1. Componentized architecture of business operations (Fig. 6) together with heat maps (Fig. 7) are good tools for
communication and decision making process, which provide a common language within a project. Componentized
architecture provides one-page overview of business operations and shared context for any suggested solution.
Componentized operations architecture and heat map analysis provided sound arguments for the final deliverables
(project portfolio, roadmap) and supported differentiated IT strategy by highlighting core and non-core competencies
          <xref ref-type="bibr" rid="ref7">(Rosenberg et al., 2011)</xref>
          . Core competencies enable an organization to outperform its rivals. These competencies,
when automated and supported with an IT system, should be treated as the company’s own practice (how they are
organized is a competitive advantage of the company). Far too often such competencies are automated with the IT
system’s best practices, and therefore their uniqueness and differentiation can potentially be destroyed. In their turn, the
IT system best practices are vital for cutting costs, for example, fast implementation, fewer mistakes, standardization,
and less risk, because they are proven to work. To keep the cost low, a company should standardize its non-core
competencies and thereby apply IT system best practices to all non-core competencies and the attached main and
supporting processes. We also provided an overview of possible IS types and ERP modules for BuildIt managers, their
advantages and disadvantages – componentized operations architecture became a supporting tool for their positioning
and comparing.
2. The developed models are a significant investment in the management infrastructure of BuildIt. This investment must
create value beyond the described IT planning project in order to receive good return on modeling. For example,
BuildIt managers saw a potential of using operations architecture for efficient responsibility assignment in
RACImatrix format. The suggested approach also identified many critical areas (components) and initiatives beyond the
scope of IT implementation (process redesign, change in incentive system, etc.). So it makes sense to establish
business-oriented enterprise architecture management practice within BuildIt and go over to capability-based planning;
3. It is crucial to take into consideration "soft" aspects of an enterprise (like Business Transformation Readiness
Assessment in TOGAF). What is important, “Soft” aspects should not only be related with HR practices (trainings,
incentives, etc.) and communication, but also should be reflected in IT support. So we decided to automate some areas
        </p>
        <p>using WFMS instead of ERP modules (e.g. order of construction materials). This approach provides more flexibility,
enforces discipline, and establishes organizational readiness for more mature IT support;
We used a simplified approach for modeling and analysis of business architecture – only operations architecture
instead of a combination of functions, business processes, and capabilities. It seems to be correct in the context of
BuildIt – the company which hasn’t got used to working with models.</p>
        <p>Whereas the project was realized in not an agile way and had a big modeling part, the customer could feel unhappy
seeing no practical results within several months. It is better to move from pure “waterfall” model to more iterative and
incremental ones. “Quick wins” projects could be launched earlier; they help to engage BuildIt employees in further IT
implementation and inspire them.</p>
        <p>Acknowledgements
Preparation of the report has been conducted with financial support from Russian Science Foundation grant (project No.
1518-30048).</p>
      </sec>
    </sec>
  </body>
  <back>
    <ref-list>
      <ref id="ref1">
        <mixed-citation>
          1.
          <string-name>
            <given-names>Business</given-names>
            <surname>Architecture</surname>
          </string-name>
          <string-name>
            <surname>Guild.</surname>
          </string-name>
          (
          <year>2015</year>
          )
          <article-title>A Guide to the Business Architecture Body of Knowledge (BIZBOK Guide)</article-title>
        </mixed-citation>
      </ref>
      <ref id="ref2">
        <mixed-citation>
          2.
          <string-name>
            <surname>Cameron</surname>
            ,
            <given-names>K. S.</given-names>
          </string-name>
          , &amp;
          <string-name>
            <surname>Quinn</surname>
            ,
            <given-names>R. E.</given-names>
          </string-name>
          (
          <year>2006</year>
          ).
          <article-title>Diagnosing and changing organizational culture. Revised edition</article-title>
          . SF:
          <string-name>
            <surname>Jossey-Bass</surname>
          </string-name>
          .
        </mixed-citation>
      </ref>
      <ref id="ref3">
        <mixed-citation>
          3.
          <string-name>
            <surname>Grigoriev</surname>
            <given-names>L.</given-names>
          </string-name>
          ,
          <string-name>
            <surname>Kudryavtsev</surname>
            <given-names>D.</given-names>
          </string-name>
          (
          <year>2013</year>
          )
          <article-title>Non-diagrammatic method and multi-representation tool for integrated enterprise architecture and business process engineering //</article-title>
          <source>Proceedings of 15th IEEE Conference on Business Informatics (CBI</source>
          <year>2013</year>
          ),
          <fpage>15</fpage>
          -
          <issue>18</issue>
          <year>July</year>
          ,
          <year>2013</year>
          , Vienna, Austria.
          <fpage>258</fpage>
          -
          <lpage>263</lpage>
          (
          <year>2013</year>
          )
        </mixed-citation>
      </ref>
      <ref id="ref4">
        <mixed-citation>
          4.
          <string-name>
            <surname>Kudryavtsev</surname>
            ,
            <given-names>D.</given-names>
          </string-name>
          ,
          <string-name>
            <surname>Grigoriev</surname>
            ,
            <given-names>L.</given-names>
          </string-name>
          (
          <year>2011</year>
          )
          <article-title>Systemic approach towards enterprise</article-title>
          functional decomposition // The workshop “Convergence of Business Architecture,
          <source>Business Process Architecture, Enterprise Architecture and Service Oriented Architecture” within the 13th IEEE Conference on Commerce and Enterprise Computing, September 5-7</source>
          ,
          <year>2011</year>
          .
          <fpage>310</fpage>
          -
          <lpage>317</lpage>
          .
        </mixed-citation>
      </ref>
      <ref id="ref5">
        <mixed-citation>
          5. The Open Group (
          <year>2016</year>
          )
          <article-title>Business Capabilities</article-title>
          . Open Group Guide.
        </mixed-citation>
      </ref>
      <ref id="ref6">
        <mixed-citation>
          6.
          <string-name>
            <surname>Pohle</surname>
            <given-names>G.</given-names>
          </string-name>
          ,
          <string-name>
            <surname>Korsten</surname>
            <given-names>P.</given-names>
          </string-name>
          ,
          <string-name>
            <surname>Ramamurthy</surname>
            <given-names>S.</given-names>
          </string-name>
          (
          <year>2005</year>
          )
          <article-title>Component Business Models - Making Specialization Real, IBM Institute for Business Value</article-title>
          .
        </mixed-citation>
      </ref>
      <ref id="ref7">
        <mixed-citation>
          7.
          <string-name>
            <surname>Rosenberg</surname>
            <given-names>A.</given-names>
          </string-name>
          ,
          <string-name>
            <surname>Chase</surname>
            <given-names>G.</given-names>
          </string-name>
          ,
          <string-name>
            <surname>Omar</surname>
            <given-names>R.</given-names>
          </string-name>
          , Taylor J., &amp;
          <string-name>
            <surname>von Rosing</surname>
            <given-names>M.</given-names>
          </string-name>
          (
          <year>2011</year>
          ).
          <article-title>Applying real-world BPM in an SAP environment</article-title>
          . Galileo Press.
        </mixed-citation>
      </ref>
      <ref id="ref8">
        <mixed-citation>
          8.
          <string-name>
            <surname>Sanz</surname>
            ,
            <given-names>J. L.</given-names>
          </string-name>
          ,
          <string-name>
            <surname>Leung</surname>
            ,
            <given-names>Y.</given-names>
          </string-name>
          ,
          <string-name>
            <surname>Terrizzano</surname>
            ,
            <given-names>I.</given-names>
          </string-name>
          ,
          <string-name>
            <surname>Becker</surname>
            ,
            <given-names>V.</given-names>
          </string-name>
          ,
          <string-name>
            <surname>Glissmann</surname>
            ,
            <given-names>S.</given-names>
          </string-name>
          ,
          <string-name>
            <surname>Kramer</surname>
            ,
            <given-names>J.</given-names>
          </string-name>
          , &amp;
          <string-name>
            <surname>Ren</surname>
            ,
            <given-names>G. J.</given-names>
          </string-name>
          (
          <year>2011</year>
          )
          <article-title>Industry Operations Architecture for Business Process Model Collections</article-title>
          .
          <source>In Business Process Management Workshops</source>
          , pp.
          <fpage>62</fpage>
          -
          <lpage>74</lpage>
          . Springer Berlin Heidelberg.
        </mixed-citation>
      </ref>
    </ref-list>
  </back>
</article>