      <title-group>
        <article-title>Minimized communication protocol based on a multi-LOD meta-model for adaptive detailing of BIM models</article-title>
      </title-group>
      <contrib-group>
        <aff id="aff0">
          <label>0</label>
          <institution>Chair of Architectural Informatics, Technical University of Munich</institution>
          ,
          <country country="DE">Germany</country>
        </aff>
        <aff id="aff1">
          <label>1</label>
          <institution>Chair of Computational Modeling and Simulation, Technical University of Munich</institution>
          ,
          <country country="DE">Germany</country>
        </aff>
      </contrib-group>
      <abstract>
        <p>A continuous generation and evaluation of design variants characterize the conceptual architectural design stages. Variants comparison is a crucial process for making design-detailing decisions. Objectifiable criteria, including results of simulations and analysis, used for evaluation and comparison of design variants can legitimize decisions as the design process proceeds. A major challenge today is the management of design information and collaboration among several actors in a building project. Yet, a large portion of the Architecture, Engineering and Construction (AEC) industry deals with conventional methods to exchange design information. The growing use of building information models is promising but even the most recent developments and practices still rely heavily on human-readable protocols and issue management systems. Considering the potential of schematized computer-readable communications to be analyzed and used for future references and case-based reasoning systems. This paper proposes a novel minimized communication protocol that aims to introduce a computer-readable, yet adaptive universal method which works on schematized information exchange requirements (templates) for different use cases. The concept is demonstrated using an example scenario.</p>
      </abstract>
    </article-meta>
  </front>
  <body>
    <sec id="sec-1">
      <title>1. Introduction</title>
      <p>While the building sector alone consumes around 50% of all the materials obtained from the
earth, the architecture, construction, and engineering (AEC) industry still fall greatly behind
other advanced industries, such as automotive industry in terms of efficiency and productivity
(Hegger et al., 2012). The early conceptual architectural design stages comprise a highly
creative process that is characterized by a continues endeavor for the creation of variants,
evaluating their performance, and a progressive detailing of their components. Decisions taken
in the early stages have a significant influence on the performance and costs of the developed
solution. Typically, decisions about the building’s envelope, shape and façade are made in a
short period of time mostly based on the architect’s empirical knowledge, generic values, or
rules of thumb (Attia et al., 2012). Since the use of analytical tools requires a mostly completed
and very detailed model, the application of simulation tools in the early stages, including the
assessment of different design options, is not fully attainable.</p>
      <p>Today, the use of digital building models for the design, construction, and operation of
buildings is already a hot trend in the building industry. Building Information Modelling (BIM)
plays an important role in the construction industry resulting in a significant modernization of
the working procedures (Borrmann et al., 2018). However, the use of BIM in the early design
stages is difficult to master since this method requires more planning effort and leads to highly
detailed designs, which are not necessarily apt for these early stages (Azhar, 2011).
Nevertheless, certain potential lies in the direct reuse of data held by digital models for diverse
analysis and simulation tasks, e.g. the structural analysis or the energy performance simulation
(Borrmann et al., 2018). To address this gap, the research project EarlyBIM (FOR2363) 1,
funded by the ‘Deutsche Forschungsgemeinschaft’ (DFG), is dedicated to the development of
strategies and methods for adaptively detailing the partially incomplete and vague design
models in order to assess and compare different design options. This paper proposes an upgrade
for our adaptive minimized BIM-based protocol for communication between architects and
various specialist planners (domain experts) in the design stages (Zahedi and Petzold, 2018b).</p>
    </sec>
    <sec id="sec-2">
      <title>2. State of the Art</title>
    </sec>
    <sec id="sec-3">
      <title>2.1 The Design Process in the Early Design Stages</title>
      <p>
        As the building design evolves, many aspects of the design desire different domain-experts to
evaluate and comment on them. Among the challenges during the early design phases are the
incompleteness of input information and immensity of design decisions regarding numerous
variations of design parameters. Moreover, since one way to overcome the gap between data
requirements of simulation tools and model quality (degree of detailing and abstraction) in
conceptual design is to simplify simulation engines and make assumptions, hence the leading
results may appear to be exact but then again are uncertain. Studies show that the AEC
professionals become so occupied with managing design information, including manually
integrating and coordinating domain-specific design information and representations that, in
the end, they manage to create only few design alternatives
        <xref ref-type="bibr" rid="ref1">(Flager et al., 2009)</xref>
        .
Another way to close the gap is to decide on and fill in the missing data. This pretty much
means passing through the conceptual design and reaching into more detailed design.
Moreover, the architect (other than having a knowhow) is not and should not be an expert in all
aspects of design. The alternative according to the adaptive detailing concept is to suggest and
provide proper detailing, corrections and modifications from domain-expert to the architect.
Nonetheless, without the architect’s approval, no change will be recognized. These suggestions
and modifications received from the domain-experts are referred to as Feedback (Zahedi and
Petzold, 2018a).
      </p>
      <p>Exploring different paths and developing several design variants is a fundamental recurrent
feature in the creative activity of building design. Every building design task/activity starts with
some requirements demanded by the client, followed by some city restrictions and regulations.
As the planning activity moves forwards, more suitable and preferred variants are explained in
more detail while other drafts are rejected or discarded. Proper management of design variants
and avoiding data redundancies has been a topic of many researches. Mattern &amp; König (2018)
introduced so called option categories to organize the possibilities that evolve in design process.
Furthermore, the authors suggested graph models to manage interdependencies within different
design variants. Nevertheless, due to complex situations and restrictions, the authors suggest
that the creation of invalid combinations are to be avoided (Mattern and König, 2018). This
paper aims to utilize the concept as mentioned above later on in its backend system during the
temporal development between options and design variants.</p>
    </sec>
    <sec id="sec-4">
      <title>2.2 BIM Collaboration Format (BCF)</title>
      <p>
        There exists strong evidence in the literature that knowledge, especially in complex projects, is
a socially attained phenomena. In other words, obtaining appropriate information for better
decision-making in early design stages could be achieved by integrating as many
domainexperts as early as possible in the design process
        <xref ref-type="bibr" rid="ref2">(Kvan, 2000)</xref>
        . Turk (Turk, 2000) argued that
based on speech act theory (Searle et al., 1980) the primary goal of communication is requesting
and fulfilling commitments (between participants) rather than just exchanging information. In
other words, when the structural engineer advises to the architect that the supporting columns
are too far apart, besides the information exchange he is trying to commit the architect to fix it.
Taking into account the significance of internal communications in building design, the
buildingSMART organization (formerly known as International Alliance for Interoperability
IAI) introduced an open standard called BIM Collaboration Format (BCF) to enable BIM-based
workflow and communication between different software tools. Through BCF, actors create
topics (e.g. issues, proposals, change requests) that comprise various types of communication
information (e.g. type, description, comments, screenshots and viewpoints inside model)
addressed in BIM data models. This way only topics and not the entire bulky BIM models will
be exchanged between different BIM authoring tools. In 2014, BCF-V2 was equipped with a
RESTful API and the possibility to exchange machine-readable topics, using so called
BIMSnippets. Example of a BIM-Snippet could be a partial IFC file (buildingsmart-tech.org, 2019)
There's no doubt that BCF is a well-established and -supported communication protocol that is
vendor-neutral and opensource. Almost all commercial BIM software have implemented BCF
in their systems too. However, BCF XML is dominantly used for grasping human-readable data
regarding issue management. Even though BCF v2.1 is capable of encompassing so-called
BIM-Snippets to encapsulate schematized arbitrary data, BCF is still mostly used to address
human-readable issue management in AEC and examples of implementing BIM-Snippets are
not yet commonly introduced. The authors of this paper, while not arguing the reputation and
usefulness of BCF, merely intend to present another approach for BIM-based communication
workflow and structured dialogue in early stages of design. A machine-readable structured
dialogue between project participant could help the AEC industry with its fragmented nature to
learn from various projects and communications. Nevertheless, aiming for computer-readable
communications does not necessarily eliminates the need for social interactions. Still, in our
protocol, there is room for comments and freestyle text and explanations. However, since the
AEC industry is fragmented with many small and medium-size companies, and in most cases,
collaborations between companies are limited to the duration of one project, we believe that
being able to learn from the partnerships and communications of various building projects
might be of great help to improve this less advanced industry.
      </p>
    </sec>
    <sec id="sec-5">
      <title>3. Multi-LOD Meta-Model and Adaptive Requirements Template</title>
      <p>A major challenge for using BIM-authoring tools in the early design stages is that despite the
insufficient information available in these stages, a BIM model appears precise and certain,
which can lead to false assumptions and model evaluation. Additionally, although the Level of
Development (LOD) (BIMForum, 2019), is a well-known concept that describes the quality
and quantity of the information contained within a BIM model, the currently available
specifications are informal, textual descriptions and graphical illustrations.</p>
      <p>To define the different component types’ LOD requirements in a formal manner, Abualdenien
&amp; Borrmann (Abualdenien and Borrmann, 2019) have introduced a multi-LOD meta-model.
As illustrated in Figure 1, the meta-model consists of two layers: (1) the data-model level to
define the component types’ LOD requirements, and (2) and the instance level to represent the
actual building components as well as their relationships. The data-model level facilitates the
definition of various component types, such as wall, window, and slab. Each component type
is associated with multiple LOD definitions and linked to an Industry Foundation Classes (IFC)
(buildingSMART, 2019) class, which makes it possible to use the rich geometry representations
and test with real-world building models. An LOD definition includes a geometry
representation, BoundingBox as an example, as well as geometric and semantic properties,
which are assigned to a vagueness type and maximum percentage. The explicit specification of
vagueness to the LOD requirements facilitates a model’s analysis and supports informed
decision-making in the early design stages. The instance level, on the other hand, represents the
building components and maps their properties as well as geometry representation to the
requirements defined at the data-model level.
Besides communicating the information vagueness to the project’s participants, a major benefit
of defining the requirements at the multi-LOD meta-model is to formalize the vague input used
by the different analysis tools. Accordingly, the domain experts collaborate to alleviate the
impact of the information vagueness. As demonstrated in Figure 2 and 3, the concept is
implemented as a web-server with a user interface (UI) providing the possibility for managing
and checking exchange requirements between different domains (Abualdenien and Borrmann,
2019). These exchange requirements defined on the multi-LOD meta-model are used as the
basis for the aLODx templates that are used in communication protocol proposed in this paper
(please refer to Section 4). Accordingly, depending on the analysis type and the design stage,
which contains diverse levels of development for the different component types, every
domainexpert specifies a list of building components in addition to a set of properties.</p>
    </sec>
    <sec id="sec-6">
      <title>4. Adaptive Minimized Communication Protocol Based on BIM</title>
      <p>In a general sense, any request for analysis during early design stages could yield to three
possible outcomes as following:
1. The design model is extremely immature and therefore not capable of analysis.
2. Some geometrical details or semantical information which are expected to be present
in the model are missing. In this case, the analysis might be performed with
simplification of simulation tools (or making assumptions regarding the missing input
data) or the domain-expert reports the missing information to the architect as this
information is required to carry on with the analysis.</p>
      <p>3. The analysis could be performed, and the results will be presented to the architect.
Making design decisions requires knowledge and experience in various domains; hence, the
architect confronts multiple challenges while overcoming the lack of information by making
estimations. Therefore, the early domain-experts involvement facilitates evaluating the
consequences of the design decisions as well as provides the required assistance by providing
design suggestions/options.</p>
      <p>This paper differentiates design variants and options. The term variants are given to the design
models developed by the architect, whereas options represent the feedback and suggestions
provided by the different experts. The options are to be used (accepted or rejected) by the
architect as a source of inspiration, suggestion, or a possible solution provided by a
domainexpert. It is important to note that throughout the design process, the architect is the team leader
and the only responsible for creating and modifying the design model/variants. At the same
time, the architect is the team member who is liable for updating the design state and approving
the final decisions.</p>
      <p>To support communication among the project participants in a means of structured dialogue,
the authors propose establishing a Common Data Environment (CDE). Besides formalizing the
communication, the proposed approach makes it possible to share bulk product and model data,
as well as facilitating proposing design options to the architect for further detailing the available
design variants. The proposed design options, so-called “feedback”, which are provided by the
domain-expert, consist of the following responses:
• report on the missing details in the design model
• possible options that could serve to fulfill the shortcomings in the design model
• the results of analysis or simulations when each of those options is selected
The proposed communication protocol focuses on staying as minimized and lite as possible,
which means avoiding to send back and forth any actual digital BIM files. Even partial models
(as options) will rest on the CDE, and the protocol will only inhale their links and globally
unified IDs (GUID). In the case of updating/suggesting attributes and properties for already
existing building components in the digital design model, these alphanumerical values will be
included in the messages. But in the case of creating/suggesting new building
components/objects, they will be only referred/linked to inside the messages.
The proposed communication system is consisting of two parts. One part would be an issue
tracking system or so-called ticketing system. Via this part, just like any other ticketing system,
requests and responses will be managed, and their progress will be controlled. Priorities can be
set for each ticket, and their responsive person can also be traced back. Various tags can be
assigned to tickets which makes the coordination and communication more seamless and
transparently traceable. The other part would serve and inhale the essence of the feedback
provided by various consultants and domain experts. In the next section, the method/function
called "feedback" will be defined.</p>
    </sec>
    <sec id="sec-7">
      <title>4.1 Feedback Function</title>
      <p>This universal method based on its use case will receive different arguments. This adaptive
feedback function along with its’ arguments are explained one by one as follows:
Feedback (actionType, optionGroupID, GUID, aLODx, objectID, propertyID, value, rating)
actionType: The first argument is called actionType. It represents the use case of the feedback
function. Possible actionTypes are missingObject, missingObjectProperty, createNewObject,
deleteObject, updateObjectProperty. missingObject is to report for some building components
that are missing overall (e.g., all the openings are missing). missingObjectProperty refers to an
attribute required for a building component that is unfilled. createNewObject refers to a newly
created building component (probably as part of an option) by the domain-expert which will
have a GUID that is unique and will be used to refer later on in the protocol. deleteObject refers
to an unnecessary building component to be deleted by the architect. updateObjectProperty is
used to suggest a value to fill in missing property.
optionGroupID: This argument is used to group multiple suggestions. The proposed details
could either be individually suggested, or they could be part of a package all sharing the same
optionGroupID. To preserve the consistency and effectiveness of the suggested option,
packaged suggestions should be treated (accepted or rejected) as a whole and not individually.
GUID: This argument refers to the Globally Unique ID of a particular building component
inside a given BIM model on the CDE. In case the actionType in the feedback function is
missingObject, then this argument (GUID) would be the unique id of the building component
that contains the missing objects. Like with the example of all the openings being absent, then
this GUID could be the Building's GUID. But when the actionType is createNewObject then
this argument will be the GUID of the temporarily newly created object that is suggested to the
architect by the domain-expert. With the missingObjectProperty and updateObjectProperty as
actionType, then this argument is the GUID of the building component that accordingly has a
missing property, or a new value is suggested for its absent property. Finally, when the
actionType is deleteObject then this argument is the GUID of the building component, which
is recommended for deletion by domain-expert.
aLODx, objectID, propertyID: In each design stage, the individual demand detailed
requirements when exchanging building models. The presence of these requirements is crucial
to perform model analysis, such as Life Cycle Assessment (LCA) and Structural Analysis. To
support this kind of information exchange, the defined components and their LOD requirement
at the multi-LOD meta-model (explained in Section 3), which are intended for a particular
analysis, are called aLODx. This way, the requirements for a specific analysis are formulized.
Inside the proposed concept, an aLODx serves as an adaptive lookup table (using ObejctID &amp;
PropertyID) that both the architect and the domain expert will refer to when they are
communicating with each other. Accordingly, they can both be sure about what type of building
a component (object) and what sort of attribute (property) they are talking about.
The requirements demonstrated in Figure 2 represent an example of the scheme (aLODx) of
the properties required from the structural analysis specialists in the authors' research group.
Using this screen, the domain-experts are capable of defining the property sets that are expected
to be present in the exchanged model to perform their analysis. For each of the defined the
properties, it is possible to specify the property’s details as well as assigning a corresponding
set of disciplines, including structural analysis (SA), operational energy (OE), and embodied
energy (EE).
After defining the exchange requirements, the corresponding component types are defined and
mapped to their properties. Figure 3 illustrates the FloorSlab component type’s details screen.
The General tab defines the component name, IfcType, and description. Whereas the second
tab Requirements facilitates the association of properties at every LOD, including a
specification of the vagueness type and percentage.
value: This argument, if present depending on the actionType, will inhale the suggested values
in the form of different options for the architect. Through the demonstrative example in the next
section, the use of this argument will be more clarified.
rating: This new argument represents the normalized evaluation or rating/grade of the
suggested option according to its performance with respect to the (based on the result of the)
requested analysis. For example, this rating could be a number between 1 to 5, while 5 being
the best.</p>
    </sec>
    <sec id="sec-8">
      <title>5. Case Study: Structural Analysis in the Early Design Stages</title>
      <p>Figure 4 demonstrates an example of the communication in case of structural analysis. Upon
requesting for analysis, a ticket will be issued which clarifies the scope of analysis. The
domainexpert, as the recipient of this ticket (following the link to the CDE) checks the model against
the requirements and sends the architect a feedback regarding the missing details. In this
simplified example slab type, main material group and structural elements are missing. The
architect decides for flat slab and concrete but asks the structural engineer in return to give him
options regarding the formation and possible types of structural elements. The structural
engineer will provide three option, one with the mainly interior walls, one with exterior walls
as load-bearing with columns and bars (joists), and the other with mainly columns and bars.
Furthermore, the structural engineer also provides the options with ratings according to their
structural performance. At the same time, the architect may have also other criteria in mind for
making design decisions, such as spatial layout flexibility or preferred window-to-wall ratio &amp;
etc. This makes the point again clear that he is the only responsible team leader to make design
decisions.</p>
      <p>With regard to our minimized communication protocol, the feedback function will be used in
two stages and in multiple forms. At first it is used to report the missing details, namely in this
example missingObjectProperty and missingObject as actionType are used in multiple
instances. In the next round as the structural expert proposes options, createNewObject is used
and various components (objects) are being created (temporarily) as part of a packaged option.
All new objects within an option will share the same optionGroupID, but each will be referred
to by their unique ID (GUID). Figure 5 shows the demonstration of the feedback function in
the case of creating new columns.</p>
    </sec>
    <sec id="sec-9">
      <title>6. Conclusions</title>
      <p>This paper introduced a BIM-based minimized communication protocol that is based on a
metamodel approach for defining exchange requirements for the different component types at
multiple LODs. The protocol enhances the collaboration and transparency of communication
during the important early phases of design. This BIM-based communication protocol is built
on schematized information requirements that are adaptively defined by domain-experts for the
different analysis types and building project types using the multi-LOD meta-model. The
protocol’s aim is to store the history of these communications and use this accumulated data
for supporting decision making in future use cases. By means of this minimized protocol,
computer-readable communications take place, which can be filtered and analyzed for future
use cases. Using this protocol, all communications, variant evaluations, and decision-making
will be documented and traceable afterward for further use cases.</p>
    </sec>
    <sec id="sec-10">
      <title>7. Acknowledgments</title>
      <p>We gratefully acknowledge the support of German Research Foundation (DFG) for funding the
project under grant FOR 2363.
Abualdenien, J. and Borrmann, A. (2019) ‘A meta-model approach for formal specification
and consistent management of multi-LOD building models’, Advanced Engineering
Informatics, pp. 20–42.</p>
      <p>Attia, S. et al. (2012) ‘Simulation-based decision support tool for early stages of zero-energy
building design’, Energy and Buildings, 49, pp. 2–15.</p>
      <p>Azhar, S. (2011) ‘Building information modeling (BIM): Trends, benefits, risks, and
challenges for the AEC industry’, Leadership and management in engineering, 11(3),
pp. 241–252.</p>
      <p>BIMForum (2019) LOD | BIMForum: Level of Development Specification. Available at:
https://bimforum.org/lod/ (Accessed: 3 April 2019).</p>
      <p>Borrmann, A. et al. (2018) ‘Building Information Modeling: Why? What? How?’ in Building
Information Modeling: Springer, pp. 1–24.
buildingSMART (2019) IFC Introduction - buildingSMART, 3 April. Available at: https://
www.buildingsmart.org/about/what-is-openbim/ifc-introduction/ (Accessed: 3 April 2019).
buildingSMART (2019) Open BIM Collaboration Format (BCF) intro. Available at: http://
www.buildingsmart-tech.org/specifications/bcf-releases (Accessed: 3 April 2019).</p>
      <p>Hegger, M. et al. (2012) Energy manual: sustainable architecture: Walter de Gruyter.</p>
      <p>Mattern, H. and König, M. (2018) ‘BIM-based modeling and management of design options
at early planning phases’, Advanced Engineering Informatics, 38, pp. 316–329.
Searle, J.R. et al. (1980) Speech act theory and pragmatics. (10): Springer.</p>
      <p>Turk, Z. (2000) ‘Communication workflow approach to CIC’, in Computing in Civil and
Building Engineering (2000), pp. 1094–1101.</p>
      <p>Zahedi, A. and Petzold, F. (2018a) ‘Seamless integration of simulation and analysis in early
design phases’, in Proceedings of the 6th IALCCE Conference, pp. 2007–2015.
Zahedi, A. and Petzold, F. (2018b) ‘Utilization of Simulation Tools in Early Design Phases
Through Adaptive Detailing Strategies’, in Proceedings of the 23rd CAADRIA, Beijing,
China, 17-19 May 2018, pp. 11–20.</p>
    </sec>
  </body>
  <back>
    <ref-list>
      <ref id="ref1">
        <mixed-citation>
          <string-name>
            <surname>Flager</surname>
            ,
            <given-names>F.</given-names>
          </string-name>
          et al. (
          <year>2009</year>
          ) '
          <article-title>Multidisciplinary process integration and design optimization of a classroom building'</article-title>
          ,
          <source>Journal of Information Technology in Construction</source>
          ,
          <volume>14</volume>
          (
          <issue>14</issue>
          ), pp.
          <fpage>595</fpage>
          -
          <lpage>612</lpage>
          .
        </mixed-citation>
      </ref>
      <ref id="ref2">
        <mixed-citation>
          <string-name>
            <surname>Kvan</surname>
            ,
            <given-names>T.</given-names>
          </string-name>
          (
          <year>2000</year>
          ) '
          <article-title>Collaborative design: what is it?' Automation in Construction, 9(4</article-title>
          ), pp.
          <fpage>409</fpage>
          -
          <lpage>415</lpage>
          .
        </mixed-citation>
      </ref>
    </ref-list>
  </back>
</article>