=Paper= {{Paper |id=Vol-2574/short20 |storemode=property |title=Augmenting Value Stream Mapping by Possession, Ownership and Availability (short paper) |pdfUrl=https://ceur-ws.org/Vol-2574/short20.pdf |volume=Vol-2574 |authors=Pavel Hruby,Christian Scheller |dblpUrl=https://dblp.org/rec/conf/vmbo/HrubyS20 }} ==Augmenting Value Stream Mapping by Possession, Ownership and Availability (short paper)== https://ceur-ws.org/Vol-2574/short20.pdf
     Augmenting Value Stream Mapping1 by Possession,
               Ownership and Availability

                         Pavel Hruby and Christian Vibe Scheller
                          phruby@acm.org, scheller2@msn.com



        Abstract. Value stream map (VSM) is a special type of flow chart used in lean
        manufacturing to depict and improve the flow of material and flow of
        information. Possession, ownership and availability (POA) is a modeling
        framework for design of enterprise information systems using flows of
        economic resources in enterprises or business ecosystems. This paper compares
        these two modeling techniques and identifies the benefits of using value stream
        mapping augmented by the POA semantics.



1       Introduction

Value stream map (VSM) is a special type of flow chart used in lean manufacturing to
depict and improve the flow of inventory and flow of information (Storch 2010). The
purpose of lean manufacturing is to make the flow more efficient by minimizing
waste, such as wasted time, unnecessary motion, or excess inventory. A value stream
map is a graphical representation of the value stream, including material and
information flows. It shows the flow of steps in product management and information
systems that support value-adding activities.
   The Possession, Ownership and Availability (POA) modeling framework (Scheller
and Hruby 2016) represents the creation, flow, and consumption of economic
resources, expressed as flow of possession, flow of ownership and flow of
availability.
   The POA model also shows the flow of steps in product management and
information systems the support value-adding activities, but from a different
perspective than value stream mapping.
   In this short paper we provide an example of a simple manufacturing process
represented both in the value stream map and in the POA model. We will compare
differences between them and illustrate areas where the value stream map would
benefit from considering adding the POA semantics to the value stream map.


2       Concepts

Concepts such as flows, value and information have different semantics in the value
stream map and in the POA model.




1 Acknowledgement: The authors would like to thank to Paula Lipnick of DXC Technology

    for valuable feedback on the draft version of the paper, and for very useful suggestions for
    further research.



                                              216

Copyright © 2020 for this paper by its authors. Use permitted under Creative Commons License
Attribution 4.0 International (CC BY 4.0).
Augmenting Value Stream Mapping by Possession, Ownership and Availability


Value
In the value stream map (VSM), the value is a capability provided to a customer,
defined by the customer (Storch 2010, Martin and Osterling 2013). Examples are
quality, right time of delivery and appropriate price, and can be measured absolutely
using the quantities of contributing features. The VSM value definition carries a
certain aspect of contract negotiation – if we deliver you the quality, at the right time
and at appropriate price, would you buy? It might indicate that VSM is primarily
targeted to business-to-business scenarios rather than to business-to-consumer, where
it is often difficult to find how the consumer determines the value.
    The value of an economic resource in the POA model is determined by observing
the exchange processes, and cannot be measured absolutely, only relatively, by
comparing the value of the resource to the values of other resources at the time of
exchange. For example, when Elwood of Blues Brothers traded Cadillac for a
microphone, under the given circumstances the microphone had higher value for
Elwood than the Cadillac, which Jake of Blues Brothers acknowledged: “OK, I can
see that” (Dendis, 2011, Wilson 2018). From the POA model we cannot determine
whether Elwood wanted microphone because of quality, time of delivery and
appropriate price; the only fact the POA model tells us, is that the microphone had
higher value than the Cadillac at the time of exchange.
    Both approaches are useful. Using the VSM definition, knowing what features of a
product are valuable for the customer, helps to design the product the customer might
eventually buy. However, using the POA definition, we cannot be sure that the
product has any value for the customer, until the customer actually buys it.

Flow
A flow in the value stream map is an “item” that flows through a value stream (Storch
2010). Examples are materials in manufacturing processes, designs in design and
development processes, external customer needs in service industry, and internal
customer needs in administrative processes.
   In the POA model, a flow represents the transfer of possession, ownership, or
availability of an economic resource from one role to another, or the creation or
consumption of an economic resource (Scheller, Hruby, 2016). A flow can also be a
flow of information from one role to another, see below.

Information
In the value stream map, the information flow is not precisely defined and is specified
only intuitively, and focuses on the actual mechanism of delivering information,
rather than what the information actually means in the context of the analyzed
process.
   In the POA model, information is an economic resource. Consequently, a flow of
information is a flow of possession, ownership and availability of information from
one role to another. Information is special, compared to other economic resources,
because a provider can send information to a recipient without losing it. In other
words, a flow of information does not change the possession, ownership, or
availability of that information for the provider, but does make the information
available (and optionally owned and possessed) to the recipient.

Other concepts
The value stream map can contain several other concepts such as timeline, showing
value-adding times (cycle times) and non-value adding (waiting) times; inventory,
shipment, material push flow, material pull flow, kaizen burst, highlighting the need
for improvement, glasses icon, indicating visual gathering of information, sticky man
for verbal communication, wiggle arrow indicating electronic communication, solid


                                          217
         Augmenting Value Stream Mapping by Possession, Ownership and Availability


         line for manual flow of information such as memos, and reports, and a number of
         icons related to Kanban, such as Kanban signal, Kanban post, Kanban stockpoint.
         Some of these concepts are illustrated in Fig. 1
            Main POA concepts are economic agents, roles, economic resources, repositories
         and flows of possession, ownership and availability of the resources. The full list of
         concepts is included in the POA metamodel in (Scheller, Hruby, 2016).
            To summarize, the value stream map focuses mainly on the actual mechanisms
         supporting and enabling the material and information flows, while the POA model
         focuses on their economic semantics.


         3          Example of a Manufacturing Process in VSM and POA

         Example of a manufacturing process in the value stream map is illustrated in Fig. 1. A
         manufacturer delivers metal foils on Tuesdays and Thursdays. The metal foil is
         stamped, assembled, packed and dispatched the Customer/Recipient. Manufacturer
         deployed an MRP system for production control, that receives 90/60/30 day forecast
         and a daily order from the Customer/Recipient, sends 6-week forecast and weekly
         order to the Supplier, and produces weekly schedule for the stamping and assembly
         stations, and a daily ship schedule to the pack-and-shipping station.

                                                                                               90/60/30/day
                                          6 week                                                 Forecast
                                         Forecast
                                                              Production control          electronic
                                electronic                                                                                 Recipient /
                                                                                                                           Customer
             Supplier
                                                                                                electronic
                                              o               MRP                                                           Product
         Raw material                                                                                                   12.000 pcs/week
                                     Weekly                                                        Daily order
                                     order


                                                     Weekly schedule

                        Tuesdays &
                                                                                                       Daily ship                          1 daily
                        Thursdays
                                                                                                       schedule




                          Stamping                                         Assembling                                        Pack and dipatch



                                                                                                       Inventory
Inventory                                         Inventory
                                                                                                           6
  5 days                                             70
                  Cycle time = 1 s                                      Cycle time = 62 s
              Changeover time = 1 hour                              Changeover time = 10 min
                     Staff = 2                                              Staff = 4


5 days                                              2 days                                          4,5 days        Production lead time 11,5 days

                          1 second                                           62 seconds                             Value added time 63 seconds




                               Fig. 1. Example of a manufacturing process in value stream map

         Example of the same process represented using Possession, Ownership and
         Availability concepts is illustrated in Fig. 2. Information from the value stream map,
         which cannot be represented using core POA concepts, is depicted by the UML Note



                                                                          218
                             Augmenting Value Stream Mapping by Possession, Ownership and Availability


                             symbol; an example is the information that Supplier delivers on Tuesdays and
                             Thursdays.
                                Activities in the POA model are instantaneous (have zero duration), therefore, in
                             the POA model, start and end of each manufacturing operation must be represented
                             explicitly. It is also necessary to explicitly represent the resources consumed and
                             created by each activity, for example, the Start Stamping activity consumes the metal
                             foil and creates the temporary “in-stamping” resource. The Finish Stamping activity
                             consumes the “in-stamping” resource and produces the stamped widget.
                                While the operation symbol in the value stream map indicates how many workers
                             (staff) are required for the operation, the well-formed POA model must be more
                             precise. Labor in the POA model is an economic resource created by Worker agents
                             and is related by the “usage” relationship to the start and to the end of each
                             manufacturing operation. The repository Labor (work day) represents the total
                             available time of the Workers, while the start and end of each manufacturing
                             operation represent the actual value-adding time of the used Labor. The value stream
                             map in Fig. 1 does not illustrate utilization of labor, in contrast to the POA model.

                                                           «availability»                                                                    «availability»
                                                                                                                                                                                                                         1 daily
                                                    Metal foil (6 week forecast)                                                    Product (90/60/30 day forecast)

                                                             «availability»
                                                       Metal foil (Weekly order)                                                                                                                      «possession»
                                                                                                                                             «availability»                                             product
                                                                                                                                                                                                                                   Unload
                                                                                                                                          Product (daily order)

                                                                                                                                                                                      Recipient/
            Supplier                                                                                                                                                                                        «ownership»                «possession»
                                          Tuesdays &                                                                                       12000 pcs / week                           Customer
          «possession»                    Thursdays                                                                                                                                                           product                    Product
          «ownership»                                                                                      Manufacturer
           Metal Foil                                                                                                                                                                              «availability»
                                                                                                                                                                                                     Product                       Carrier
                                                                                                                                                                 «availability»
                                                    «availability»
                                                                                                                                                              Assembled Product
           Metal Foil                       Metal foil (Weekly schedule)
                                                                                                                                                              (Daily ship schedule)                                            «possession»
            Receipt                                                                                                                                                                                                              Product
                                                                                                                               «availability»
                                                                        «availability»              «availability»          Assembled product
          «possession»                                                Stamped widget              Stamped widget                                                                                                                   Load
                                                                                                  (Weekly schedule)                                                      6 pieces
          «ownership»
            Metal foil       Consume
                             Metal foil                                                                                                                                                                                            «ownership, possession»
                                                                                       70 pieces                                                                                                      In packning                          Product
                                                                                                                                                                                                          and
                                                                                                                                                                                                                  In Packing and
           Waiting for                     In Stamping                                                                        In Assembly                                                             Dispatching
                                                                 Consume            Waiting for                                                       Consume¨             Waiting for                              Dispatching
           Stamping                          Process                                                      Stamped               Process
                                                                In stamping         Assembly                                                             In                 Packing                                   Process In packning
                                                                                                           widget
                                                                                                                                                      assembly                       Assembled                                      and
                                In stamping            In stamping                                                    In assembly       In assembly                                    product                                  Dispatching

                                                                                     Stamped                                                                                                 Start Packing                                      Finish Packing
                                                                                                                                                                      Assembled
                          Start stamping                     Finish stamping          widget         Start assembly                          Finish assembly                                and Dispatching                                    and Dispatching
                                                                                             Consume                                                                   product
                                                                                             Stamped
                                                                                              Widget                             Use                                           Consume                                Use
              Use                                                                                                             Assembly                  Create                Assembled                             Packing
Worker       Labor                           Use     Use                                                                       machine                Assembled                 Product                             machine                            Create
                            Create                                Create                                       Create
                                          StampingStamping                                                                Use                          product                                                                  Use                    Product
                         In stamping                             Stamped                                    In assembly Assembly
                                          machine machine                                                                                                                                               Create                Packing
          Use                                                     widget
                                                                                                                          machine                                                                  In packing and             machine
         Labor                                                                                                                                                                                                                                  Consume
Create                                                                                                                                                                                               dispatching                               In packing
                                                                               Cycle time = 1s
Labor            Consume                      Stamping                         Changeover time = 1 hour                                                                                                                                      and dispatching
                  Labor                       machine                                                                         Assembly                        Cycle time = 62 s
                                                                                                                               Machine                        Changeover time = 10 min                                 Packing
                                                                                                                                                                                                                       machine
                                                                              Use Labor
             Labor
                                                                                                    Use Labor
           (work day)
                                                                                                                            Use Labor


                                                                                                                                              Use Labor




                                   Fig. 2. Example of a manufacturing process using possession, ownership and availability

                             Another interesting observation is that the information flows (forecasts, weekly and
                             daily orders), as well as the weekly and daily schedules in the value stream map in
                             Fig. 1, are actually flows of availability of material, in the POA terms.
                                It illustrates the importance of determining the economic semantics of the
                             information flows. The POA model has a consistency rule that when a resource is
                             created, the possession, ownership and availability of this resource are created with it,
                             likewise, possession, ownership and availability no longer exist after the resource is
                             consumed. Therefore, an activity consuming a resource must have incoming flows of



                                                                                                                          219
Augmenting Value Stream Mapping by Possession, Ownership and Availability


possession, ownership and availability of this resource, otherwise the resource cannot
be consumed.
   Applying this rule leads to a discovery of flows not present in the VSM model in
Fig. 1, but which are necessary for the completeness of the model from the economic
perspective. For example, there must be a flow of availability of Stamped Widget
resource to the Manufacturer, otherwise the Manufacturer would not be able to
transfer this availability to Start Assembly activity, which needs it in order to
consume Stamped Widget. The flows of resources discovered in this way are
indicated in red color in Fig. 2.
   During process improvement we can then start thinking whether this flow of
availability must go through a central planning system or can be transferred directly to
the next manufacturing operation, which could then start immediately after the
previous operation finishes, which could in some cases lead to shorter waiting time
and leaner process.


4       Information Model

The main purpose of the POA model is to create an enterprise information system,
from the model of the flows of economic resources in the business ecosystem. Hruby
and Scheller (2019) illustrated that occurrence of each flow at runtime represents an
information that is useful to potentially all stakeholders in the ecosystem and can be
forwarded to them. For example, the information about arrival of metal foil to the
inventory can be also made available to the stamping, assembly, packing stations and
perhaps even a Recipient/Consumer, which might get valuable signals about changes
in the manufacturing processes. For example, when Samsung in 2016 stopped placing
orders for components of 3D glasses, it was a useful signal for the consumers that
Samsung is stopping producing 3D TV sets, although Samsung has not announced it
publicly.
   The number of information flows generated this way is proportional to the number
of flows multiplied by the number of stakeholders; this amount of information in any
larger system can no longer be handled manually and requires a digital solution.


5      Conclusions

Although the value stream map is an informal diagram, understanding the economic
semantics of the material and information flows helps to make the process leaner and
eliminate waste by discovering and enabling additional information flows between
processes and trading partners, allowing them to adapt at runtime to the deviations
from the schedules. Making the information instantly available where needed and
when needed, requires a digital information technology solution.
   Therefore, value stream mapping, in its traditional form, is a valuable tool in
situations when digital information processing is not possible or desirable and when
information must be fully or partially processed and transferred manually. If it is
feasible to fully or partially automate the value stream and implement a digital
information system, augmenting the value stream by possession, ownership and
availability allows to design an information system better supporting the lean business
processes.




                                          220
Augmenting Value Stream Mapping by Possession, Ownership and Availability


6      References
Martin K, Osterling M (2014) Value Stream Mapping: How to Visualize Work and Align
        Leadership for Organizational Transformation. McGraw Hill
Dendis, W (2011) The Blues Brothers - You traded the Cadillac for a microphone
        https://www.youtube.com/watch?v=nrKmNkDcDuk
Hruby P, Scheller C.V (2019) Device as a Service – an Economic Model, Value Modeling and
        Business Ontology (VMBO) workshop, Stockholm, Sweden, March 4-5, 2019
Lipnick, P (2019) Value Stream Mapping Next Practices, ADaPT 2019 – Agile DevOps and
        Product Thinking, FCA, December 2019
Rother M., Shook J (1999) Learning to See: value-stream mapping to create value and
        eliminate muda. Brookline, Massachusetts: Lean Enterprise Institute
Scheller C.V, Hruby, P (2016) Business Process and Value Delivery Modeling Using
        Possession, Ownership, and Availability (POA) in Enterprises and Business Networks.
        Journal of Information Systems: Summer 2016, Vol. 30, No. 2, pp. 5-47.
Storch, R.L (2010) Value Stream Mapping, University of Washington,
        https://courses.washington.edu/ie337/Value_Stream_Mapping.pdf
Skillsoft (2019 Applying Value Stream Mapping in Lean Business,
        https://cdnlibrary.skillport.com/courseware/Content/ria/RIA_V3_1_2237/
Wilson, N. (2018) Why did Elwood trade a Cadillac for a microphone?
        https://movies.stackexchange.com/questions/47210/why-did-elwood-trade-a-cadillac-
        for-a-microphone, https://www.youtube.com/watch?v=nrKmNkDcDuk