=Paper= {{Paper |id=Vol-2581/aesp2020paper5 |storemode=property |title=Procedural Model for Selecting Enterprise Systems Based on Project Management Software |pdfUrl=https://ceur-ws.org/Vol-2581/aesp2020paper5.pdf |volume=Vol-2581 |authors=Christoph Weiss,Johannes Keckeis |dblpUrl=https://dblp.org/rec/conf/se/WeissK20b }} ==Procedural Model for Selecting Enterprise Systems Based on Project Management Software== https://ceur-ws.org/Vol-2581/aesp2020paper5.pdf
  Procedural Model for Selecting Enterprise Systems
       Based on Project Management Software
                     Christoph Weiss                                                                       Johannes Keckeis
  AUB's German-language interdisciplinary Ph.D. programme                            Department of Strategic Management, Marketing and Tourism,
                       (Economics)                                                                      University of Innsbruck
                    Budapest, Hungary                                                                     Innsbruck, Austria
             christoph.weiss@andrassyuni.hu                                                          johannes.keckeis@uibk.ac.at


     Abstract - Project management software helps companies                        Many authors offer selecting consulting services, tools or
plan, execute and control projects. The simpler and more                       platforms (see table 6 in annex). The consultancy service often
efficient the processes for projects are executed, the more                    consists of requirement assessment and requirement definition
profitable and more successful the projects are for companies.                 for the selection of project management software.
Therefore, the process of defining and selecting requirements for
a project management software is an important success factor for                  The aim is to develop a procedural model for selecting
any company in any industry and company size. Based on a                       project management software from existing process models
qualitative analysis of existing procedural models for the                     and to validate it with two user cases. The introduction or
selection of project management software, a procedural model
                                                                               implementation of the project management software is
for the selection of project management software is developed
and validated with two user cases. So companies can execute and                excluded (Implementation phase included in five analyzed
support projects for the selection, implementation and                         procedural models (see Table 6 in annex).
continuous development of project management software even
more efficiently.                                                                                II. METHODOLOGY
    Keywords – activities, analysis, enterprise systems                           The analysis of different process models for selecting
evaluation, model, provider, procedural model, requirements,                   project management software takes place in two successive
requirements management. project, project management                           phases:
software, selection, software, tasks
                                                                                     •    In the first phase, a literature analysis (see list of
                     I. INTRODUCTION                                                      literature) is carried out in order to find and identify
                                                                                          possible procedural models for the selection of project
    Project management software is a type of software in the                              management software.
family of enterprise systems. The term Enterprise Systems
subsumes for example Business Intelligence, Customer                                 •    In the second phase, a detailed word analysis [5] is
Relationship Management, Enterprise Resource Planning,                                    performed. Sources, phases, activities and tasks are
Product Lifecycle Management, Production Planning System                                  coded, analyzed and finally summarized. As an
and many more. Enterprise systems therefore subsumes all                                  example, the condensation of the term "define" is
software systems that are used to conduct and execute                                     mentioned here:
business processes in a company [1].
                                                                                          Define: appoint, define, establish, form, etc.
    Project management software is used for a wide variety of
projects in a company including enterprise systems projects to                     Based on the literature and word analysis, a sequence of
select, introduce and continuously develop them.                               identified and summarized phases for the new procedural
                                                                               model for the selection of project management software is
    Project management software is usually modular and                         determined. Three different calculation methods are used to
consists of various modules or components such as multi                        find a new procedural model for selecting project management
project management, project controlling, portfolio                             software [6]:
management, resource management, and so on. [2]. These
modules, with a variety of functions, are usually found in the                       •    Mean from the first and last identified phase digit (see
original project management software but also in other                                    column heading A in Table 1)
enterprise systems types such as Enterprise Resource                                 •    Average valuation with sum of the multiplication per
Planning. They are sold and implemented by different vendors                              phase location in the order and number of phase
(manufacturers and implementation partners) [3].                                          designations (see column heading B in Table 2)
    In contrast to Enterprise Resource Planning, there are less                      •    Normalize (scaling to “one”, see Table 7 in annex) of
scientific publications for the selection and evaluation of                               phases per procedural model and average valuation
project management software [4]. In recent years (publication                             (see column heading C in Table 2)
year: between 2009 and 2016) different consulting companies
and consultants have dealt with the domain of selection and
introduction of project management software and have                                                           Nomination
developed their own process models with different phases and                     #         Phase                               ∑         A         R1
                                                                                                               in phase
sequences as well as tasks and activities (see table 5 in annex).
These models can be found mainly on their websites or in                       Tab. 1: Grid to order the phases of the procedural model for selecting project
special journals.                                                              management software I




Copyright © 2020 for this paper by its authors. Use permitted under Creative Commons License Attribution 4.0 International (CC BY 4.0).

AESP20: 1st Workshop on Requirement Management in Enterprise Systems Projects @ SE20, Innsbruck, Austria                                                  24
   ∑: Number of entries in the eleven previous models                                Tab. 4: Phases of the new procedural model for selecting project
analyzed                                                                             management software II (in alphabetical order)

     R1: Order Column A                                                                  D: Mean A+B+C
 #              B            R2       C            R3        D             R4                                       P2
                                                                                          P1 Project                                P3                 P4
                                                                                                             Requirement
                                                                                     initialization phase                      Analyze phase    Presentation phase
Tab. 2: Grid to order the phases for procedural model for selecting project                                 definition phase
management software II
                                                                                           P5                      P6                P7
     R2: Order column B                                                                 Test phase          Selection phase    Decision phase
     R3: Order column C
                                                                                     Figure 1: Seven phase procedural model for selecting project management
     R4: Order column D                                                              software (R4)

                              III. ANALYSIS                                              The analysis of the results shows that the phase of the
                                                                                     requirement definition is the most important, since with ten
A. Selection phases of the procedural model for selecting
                                                                                     mentions in eleven models it is most common in all models. It
     project management software                                                     can be concluded that you cannot get passed the requirement
    The analysis and subsequent formation of an order of the                         management. The second most important phase besides the
eleven procedural models for selecting project management                            requirement definition is the selection phase with nine
software results in a new procedural model for selecting                             responses followed by the analysis phase with five responses
project management software with seven selection phases (see                         in the eleven models.
Figure 1, Table 3 and 4). Only phases are included, which are
used at least in four existing procedural models for the                             B. Selection activities of the procedural model for
selection of project management software.                                                 selecting project management software
    The present and analyzed procedural models for selecting                             Different tasks and activities are performed at each stage
                                                                                     of the calculated project management software selection
project management software have a minimum of two phases
                                                                                     process. The analysis of eleven procedural models for the
and a maximum of nine phases. Looking at all eleven
                                                                                     selection of project management software presents those tasks
procedural models (see Annex) for selecting project
management software, the average is 4.72 phases compared to                          and activities that are mentioned at least twice in the
the seven phases of the new project management software                              procedural models (each in alphabetical order).
selection process.                                                                       Project initialization phase
 #          Phase
                                  Nomination
                                                        ∑           A           R1                     •    Define goals
                                  in phase
                                                                                                       •    Describe degree of maturity of the project
 3          Analyze               1, 2, 4               5           2,50        2
                                                                                                       •    Nominate project team
 4          Decision              5, 6, 8               4           6,50        7
                                                                                                       •    Start project
 5          Presentation          4                     4           4,00        4
                                                                                         Requirement definition phase
            Project
 6                                1, 2                  4           1,50        1
            initialization                                                                             •    Analyze processes

 1
            Requirement
                                  1, 2, 3, 5            10          3,00        3                      •    Analyze requirements
            definition
                                                                                                       •    Capture processes
 2          Selection             2, 3, 4, 6            9           4,00        4
                                                                                                       •    Conduct interviews
 7          Test                  5, 7                  4           6,00        6
                                                                                                       •    Conduct workshops
Tab. 3: Phases of the new procedural model for selecting project
management software I (in alphabetical order)
                                                                                                       •    Create request catalog
                                                                                                       •    Document requirements
 #          B           R2        C            R3            D          R4
                                                                                                       •    Identify requirements
 3          2,40        3         0,19         3             2,67       3
                                                                                                       •    Prioritize requirements
 4          6,25        7         0,97         7             7,00       7
                                                                                                       •    Structure requirements
 5          4,00        5         0,64         4             4,33       4

 6          1,25        1         0,05         1             1,00       1

 1          2,10        2         0,18         2             2,33       2
                                                                                         Analyze phase
 2          3,33        4         0,85         6             4,67       6
                                                                                                       •    Analyze benefits
 7          5,50        6         0,79         5             5,67       5
                                                                                                       •    Analyze costs



AESP20: 1st Workshop on Requirement Management in Enterprise Systems Projects @ SE20, Innsbruck, Austria                                                        25
              •    Define demand                                                               IV. USE CASES
              •    Define stakeholders                                        The analyzed and calculated procedural model for
                                                                          selecting project management software has been validated in
              •    Define target                                          two user cases.
              •    Perform actual analysis                                   In the first company, a service company in Austria, the
                                                                          application of the procedural model for the selection of a new
    Presentation phase
                                                                          project management software was applied as part of a
              •    Assess evaluation                                      consulting project.
              •    Comment presentations                                      The second company, a large company in the industry of
                                                                          plant engineering and construction with its headquarters in
              •    Design evaluation                                      Germany and several subsidiaries all over Europe, the new
              •    Evaluate presentations                                 procedural model for selecting project management software
                                                                          was used in the evaluation of the existing project management
              •    Moderate presentations                                 software in the course of evaluating the entire enterprise
                                                                          systems landscape.
              •    Perform presentations
                                                                              In the planning phase of both projects for the selection of
    Test phase                                                            project management software, the companies identified two
              •    Document tests                                         gaps in the procedural model for selecting project
                                                                          management software in form of the evaluation phase and the
              •    Obtain test positions                                  contract phase, as these are two common phases in each
                                                                          selection project for both companies. Therefore, these two
              •    Perform tests
                                                                          phases for the implementation of the selection project were
              •    Schedule tests                                         additionally added in the procedural model for the selection of
                                                                          project management software.
    Selection phase
                                                                              In the course of the project initialization phase, it was
              •    Analyze software favorite                              apparent, that the analysis phase had to be carried out before
              •    Carry out test positions                               the requirement definition phase and not the other way around
                                                                          to the service company at the beginning and to the plant
              •    Decision                                               engineering company at the end of the project initiation phase.
                                                                          Therefore, this should be taken into account in the new
              •    Compare requirements                                   procedural model for selecting project management software.
              •    Conduct call for proposals                             In certain cases, from the point of view of both companies,
                                                                          these two phases could also be conducted in parallel.
              •    Create evaluation
                                                                              Furthermore, in the course of the two selection projects, it
              •    Create longlist                                        was apparent that a specific tendering phase is necessary and
                                                                          should not be included in the selection phase. Therefore, this
              •    Create shortlist
                                                                          further phase has been added in the procedural model for
              •    Finalize software favorite                             selecting project management software.
              •    Interview reference customers                              From the point of view of the two companies, possible
                                                                          reductions of different phases from the proposed procedural
              •    Make presentations                                     model for the selection of project management software were
              •    Make selection                                         not necessary, as all planned phases are considered
                                                                          indispensable.
              •    Negotiate contracts
                                                                          V. EXPERIENCED MODEL FOR THE SELECTION OF
              •    Obtain test positions                                           PROJECT MANAGEMENT SOFTWARE
              •    Perform feasibility analysis                               The ten phase process model for selecting project
                                                                          management software, derived from qualitative analysis and
              •    Perform fine selection                                 validation by two use cases, is shown in Figure 2. The
              •    Pre-selection                                          calculated procedural model with seven phases for selecting
                                                                          project management software was supplemented by three
              •    Visit reference customers                              phases (marked gray) and the order of two phases were
    Decision phase                                                        changed (analysis phase follows requirement definition
                                                                          phase).
              •    Decision                                                                                                 P3
                                                                                P1 Project             P2                                    P4                 P5
              •
                                                                                                                     Requirement
                   Document presentations                                  initialization phase   Analyze phase
                                                                                                                    definition phase
                                                                                                                                       Tendering phase   Presentation phase


              •    Evaluate presentations                                        P6                      P7                P8                P9                P10
                                                                              Test phase          Selection phase   Evaluation phase   Decision phase     Contract phase
              •    Perform presentations



AESP20: 1st Workshop on Requirement Management in Enterprise Systems Projects @ SE20, Innsbruck, Austria                                                                26
Figure 2: Ten phase procedural model for selecting project management                    selection
software

    From the two use cases, the tasks and activities for the                             Selection help
three complementary phases (contract, evaluation and                                                                                  Company
                                                                           [8]           for PPM             4           Steps
                                                                                                                                      folder
tendering) that were used in both user cases were determined.                            software
This also applies to the additions to the requirement phase
                                                                                         The six steps to
(each in alphabetical order).                                                            the right project
                                                                           [2]                               6           Steps        Journal
    Requirement definition phase (supplements)                                           management
                                                                                         software
              •    Analyze vulnerabilities
                                                                           [9]           Project process     4           Phases       Book
              •    Analyze potentials
                                                                                         Concept for
              •    Create specifications                                                 selecting a
                                                                           [10]          project             2           Steps        Slides
              •    Define technical requirements                                         management
                                                                                         software
              •    Define data management
                                                                                         Selection and                                Website
              •    Document procedural requirements                        [11]          introduction        6           Steps        consul-
                                                                                         process                                      tant
              •    Weight requirements
                                                                                         Selection
    Tendering phase                                                                      process for
                                                                           [12]          project             9           Process      Journal
              •    Get initial offers                                                    management
                                                                                         software
              •    Market research (providers)
                                                                                         Selection of
              •    Market research (systems)                                             project
                                                                                                                                      Website
                                                                           [13]                              5           Levels       consul-
                                                                                         management
    Evaluation phase                                                                     software
                                                                                                                                      tant

              •    Carry out evaluation                                                  Software
                                                                                                                                      Website
              •    Create evaluation criteria                              [14]
                                                                                         Launch
                                                                                                             2           Phases       consul-
                                                                                         Procedural
                                                                                                                                      tant
    Contract phase                                                                       Model

              •    Negotiate project management provider                                 Procedural
                                                                                         model pmcc
                   and/or implementation partner                                                                                      Presen-
                                                                           [15]          consulting PPM      6           Steps
                                                                                                                                      tation
              •    Negotiate project management software                                 software
                                                                                         selection
                   contracts
                                                                                         Expiration of a
              •    Obtain final offers                                     [16]          PM software         6           Phases
                                                                                                                                      Lecture
                                                                                                                                      document
              •    Review contracts                                                      selection

                  VI. FURTHER RESEARCH                                    Tab. 5: Investigated procedural models for selecting project management
                                                                          software I
    The two user cases have shown that the calculated order of
the determined phases for the new procedural model for                                                       Selection                Evalu-
                                                                                     Implementation                      Evaluation
selecting project management software is a basis for practical             Autor
                                                                                     phase
                                                                                                             consul-
                                                                                                                         platform
                                                                                                                                      ation
application in companies. It is worth mentioning whether so                                                  tation                   tools
many phases are really necessary for the selection of a project            [7]       X                       X                        X
management software. This depends on the size of the
company and the specific requirements or affinity of                       [8]
stakeholders in relation to project management software. The
new ten phase model for selecting project management                       [2]                               X
software should therefore be confirmed in a broad and deep                 [9]       X                       X
analysis. This can be qualitatively verified either by a
quantitative survey or by expert interviews. Further use cases             [10]      X                       X
can certainly support the results.
                                                                           [11]      X                       X                        X
                          VII. ANNEX
                                                                           [12]                              X           X
             Selection         Number                     Docume
 Author                                    Procedure
             model name        of phases                  nt type          [13]                              X           X            X

             Parameta                                                      [14]      X                       X           X            X
             procedural                                   White
 [7]                           2           Phases
             model for                                    paper
                                                                           [15]                              X
             software



AESP20: 1st Workshop on Requirement Management in Enterprise Systems Projects @ SE20, Innsbruck, Austria                                        27
    [16]     X                                                                   [5]  P. Mayring, Qualitative Inhaltsanalyse (Grundlagen und Techniken),
                                                                                      Beltz, 12., überarbeitete Auflage, Weinheim und Basel, 2015.
Tab. 6: Investigated procedural models for selecting project management          [6] C. Weiss, M. Kofler, R. Friedemann, Qualitative Analysis of different
software II                                                                           ERP Evaluation Models. In (Piazolo, F., et.al.): ERP Future 2016:
                                                                                      Innovations in Enterprise Information Systems Management and
                                                                                      Engineering (5th International Conference), Hagenberg, 17-25, 2016.
                                                                                 [7] M. Streng, Projektmanagement-Software herstellerneutral auswählen
# phase Division # phase Division # phase Division # phase Division                   (Whitepaper),                                  https://pm-blog.com/wp-
1          0,0000    1        0,0000    1        0,0000     1       0,0000            content/uploads/2013/06/whitepaper-selectppm.pdf,                  Stand:
2          1,0000    2        0,5000    2        0,3333     2       0,2500            08.06.2017.
                     3        1,0000    3        0,6667     3       0,5000       [8] A. Gaide, Auswahlhilfe für PPM-Software, https://pm-united.de/wp-
                                                                                      content/uploads/2013/06/Auswahlhilfe-PPM-Software.pdf,             Stand:
                                        4        1,0000     4       0,7500            08.06.2017.
                                                            5       1,0000       [9] W. Weber, Beratungsleistungen beim Einsatz von PM-Software. In:
                                                                                      (Wagner, R., Hrsg.): Beratung von Organisationen im
# phase Division # phase Division # phase Division # phase Division                   Projektmanagement, Symposion, 1. Auflage, S. 405-429, 2015.
1          0,0000    1        0,0000    1        0,0000     1       0,0000       [10] A.      Gobert,     Anforderungen       und    Auswahlkriterien       für
2          0,2000    2        0,1667    2        0,1429     2       0,1250            Projektmanagement-Software am Beispiel von Chipkartenprojekten,
3          0,4000    3        0,3333    3        0,2857     3       0,2500            https://www4.in.tum.de/~kuhrmann/gi2008/final-gobert.pdf, Stand:
                                                                                      08.06.2017.
4          0,6000    4        0,5000    4        0,4286     4       0,3750
                                                                                 [11] A.      Frick,     PPM-Software       Auswahl       und       Einführung;
5          0,8000    5        0,6667    5        0,5714     5       0,5000            https://projektforum.de/de/Beratung/PPM-Software-Auswahl-und-
6          1,0000    6        0,8333    6        0,7143     6       0,6250            Einfuhrung.htm, Stand: 28.05.2016.
                     7        1,0000    7        0,8571     7       0,7500       [12] P. Berleb, R. Wolf-Berleb, Projektmanagement-Software kompakt,
                                                                                      Projekt Magazin kompakt, Januar 2015.
                                        8        1,0000     8       0,8750
                                                                                 [13] M .Bunge, Auswahl von Projektmanagement Software,
                                                            9       1,0000
                                                                                      https://projectplant.de/ppmatch.html#info, Stand: 28.07.2017.
Tab. 7: Normalization table                                                      [14] M. Meyer, A. Voßmeyer, Erfolgreich Software einführen Schritt für
                                                                                      Schritt,       https://pm-software.de/tipps-und-tricks/so-gehen-sie-vor,
                         VIII. BIBLIOGRAPHY                                           Stand: 28.07.2017
[1]    B. Ramdani, P. Kawalek, Predicting SMEs’ adoption of enterprise           [15] P.         Borbely,         J.       Schauer,          http://www.pmcc-
       systems, Journal of Enterprise Information Management, Vol. 22 No.             consulting.com/de/_downloads/newsletter/1611/pmcc_NL1611_Soft
       1/2, 10-24, 2009.                                                              ware.pdf?utm_source=newsletter&utm_medium=email&utm_campai
                                                                                      gn=pmcc+Newsletter+1611, Stand: 08.06.2017.
[2]    M. Streng, PM-Software muss zum Anwender passen – nicht
       umgekehrt, manage it, 5-6, 2011.                                          [16] U. Aßmann, Einsatz von Projektmanagement-Software, Fakultät
                                                                                      Informatik, Technische Universität Dresden, https://st.inf.tu-
[3]    J. Verville, R. Palanisamy, C. Bernadas, Halingten, A., ERP                    dresden.de/fles/teaching/ss10/SWM/MMsoftware.pdf,                  Stand:
       Acquisition Planning: A Critical Dimension for Making the Right                08.06.2017.
       Choice, Long Range Planning 40, 45-63, 2005.
[4]    M. Pérez-Salazar, I. Rivera, Cristóbal-Vázquez, I. ERP selection: a
       literature review, Int. J. Industrial and Systems Engineering, Vol. 13,
       No. 3, 309-324, 2013.




AESP20: 1st Workshop on Requirement Management in Enterprise Systems Projects @ SE20, Innsbruck, Austria                                                    28