=Paper= {{Paper |id=Vol-2851/paper23 |storemode=property |title=Features of Forming a Successful IT Project Team and Method of Team Leader Choosing |pdfUrl=https://ceur-ws.org/Vol-2851/paper23.pdf |volume=Vol-2851 |authors=Maryna Kutsenko,Yevheniya Boiko |dblpUrl=https://dblp.org/rec/conf/itpm/KutsenkoB21 }} ==Features of Forming a Successful IT Project Team and Method of Team Leader Choosing== https://ceur-ws.org/Vol-2851/paper23.pdf
Features of Forming a Successful IT Project Team and Method
of Team Leader Choosing
Maryna Kutsenko, Yevheniya Boiko
Kyiv National University of Construction and Architecture, Povitroflotsky Avenue, 31, Kyiv, 03037, Ukraine


                 Abstract
                 Today, the IT sector remains one of the most developed and complex, competition is
                 constantly growing, projects are becoming more complex and organizations that implement
                 these projects are trying to succeed as much as possible. The project success depends on a
                 large number of components. In this article considered how the effectiveness of the IT project
                 team affects its success, studied where the impact on efficiency, which should pay special
                 attention when forming a team. The work of many scientists is devoted to the formation of an
                 effective project team. The issues of individual psychological participants qualities, their
                 influence on team interaction and obtaining a positive effect from further work remain open
                 for study. The main aspects of team work, signs of a successful team and key characteristics
                 are highlighted in the work, the research model of project success dependence on quality of
                 team work is presented. The process of team formation, which requires considerable attention
                 and responsibility, is considered. During this process, there are many influencing factors,
                 neglect of which will lead to a negative result. It is important to take into account the
                 personal characteristics of each participant, to study psych types and to form a common
                 psychological field. The choice of the project manager plays a significant role in the success
                 of forming a coordinated team. It must be the best of the best - a high-level specialist, a
                 leader who is able to work with a large number of people, feel the mood in the team, form
                 and maintain team spirit. The method of selection of the best candidate for IT project
                 managers is offered in the work. This methodology is based on the candidate’s assessment on
                 three components: the values it adheres to, the cost of its work and the risks associated with
                 possible failure to perform their functions. The calculations based on the selected criteria
                 allow you to accurately select the best candidate, the leader of an effective IT project team,
                 on the way to the success of the whole project.

                 Keywords 1
                 Project team, efficiency, project success, method, project manager, team leader

1. Introduction
   Today the IT industry market continues to develop rapidly. Requirements for the implementation
of IT projects are high and constantly growing. There is a need for an integrated approach to project
implementation and the creation of strong competitive advantages. The success of the project depends
on the coordinated and effective work of all its participants, their cooperation and mutual assistance.
The IT project team works with many project parameters - these are economic, social and
organizational parameters, and must take into account their features. Factors of the external
environment of the project - economic, political, cultural, legal, which operate in the area of the
project itself also have an impact. Considering the work of the team in such an environment, we can
say that still relevant is the development of approaches and methods of forming an effective project



Proceedings of the 2nd International Workshop IT Project Management (ITPM 2021), February 16-18, 2021, Slavsko, Lviv region, Ukraine
EMAIL: marynakutsenko@ukr.net (A. 1); boikoye@gmail.com (A. 2)
ORCID: 0000-0002-4499-0021 (A. 1); 0000-0002-2000-4258 (A. 2)
            ©️ 2021 Copyright for this paper by its authors.
            Use permitted under Creative Commons License Attribution 4.0 International (CC BY 4.0).
            CEUR Workshop Proceedings (CEUR-WS.org)
team, which would take into account environmental factors, individual characteristics of participants
and aspects of inter-action between them.

2. Setting objectives and theoretical studies
   The issue of research approaches to the formation of an effective project team and the impact of
the relationship between the participants has been of concern to scientists for decades. In domestic
science there are works devoted to the essence and role of factors of uniqueness of the project in team
management of projects, which is based on taking into account the features of the product and the
environment of the project; a special role is given to team development tools [1-8]. It is believed that
the foundation of a team's success is not only the association of high-quality professionals, but also
the development of team skills of image and communication, as well as team interactions.
      Team building processes are closely linked to effective communication skills. World scientists
pay attention to the study of the communication management process in the IT industry at the macro
and micro levels to improve their efficiency [9].
   It remains to open the question of the relationship between the team effectiveness and the
individual psychological properties and characteristics of the participants interaction (relationship).
Taking these factors into account will reduce some of the project risks and improve the benefits of the
project organization.
   The purpose of this work is to describe the peculiarity for forming the composition of the IT
project team, taking into account the individual psychological characteristics and peculiarities of the
participants interaction, which has made it possible to increase the efficiency of the team's work, as
well as to offer recommendations on the selection the leader of such team.
   For further research, considered the following aspects of the project team work:
         1. As a result of the increase in the size of the team, satisfaction with the overall work of the
             team often decreases.
         2. If the project manager is a strong leader, he can influence the cohesion of the team,
             increasing the number of interactions between participants. The leader controls these
             interactions, from himself available to interact. If such an atmosphere is formed in the
             team and the degree of recognition of the leader increases, then the overall satisfaction
             with the work of the team increases.
         3. If the variation in the amount of intellectual capital in the team and the team of leaders
             decreases, then the customer's satisfaction with the result of the team's work decreases.
         4. The increase in customer satisfaction with the team result is influenced by:
         • Growth in the value of intellectual capital;
         • Reduction of variation in the types and sizes of career and value orientation of the
             participants in the team.
         • Separation of action roles and analysis roles;
         • The predominance of the roles of analysis over social roles;
         • An increase in the number of participants fulfilling the role of an idea generator in
             comparison with those performing other roles in the team;
         • Growth in the size of the career and value orientation of the team members and the team of
             leaders.
   Forming a team of IT specialists for high-quality project implementation is one of the strategic
tasks on the way to ensuring maximum competitiveness of the domestic IT industry.
   The very concept of a project team has changed and expanded today. The complexity and
complexity of projects in modern organizations dictates the need to unite people with knowledge and
skills, and experience in different fields, into a project team [10].
   Let's consider the definition of a project team. The project team consists of people with defined
roles and responsibilities for the implementation of the project, and who act together to achieve the
goal of the project [11, 12]. Solving a problem within a team is called teamwork or teamwork [11].
   The structure and characteristics of the project team may differ; however, the role of the project
leader remains unchanged - the team leader responsible for managing the project, and the rest of the
team members who carry out the work of the project, but do not necessarily participate in the
management. Project management team - members of the project team directly involved in managing
its operations.
    As the project progresses, the professional and size of its team may change [12].
    If we are talking about an IT project team, then this is a team involved in the development of new
software products and information systems of the organization. A software product development team
is a team of people with technical knowledge and skills who actively interact and exchange
information to ensure high-quality and fast delivery of the product being developed [13, 14].
    IT project teams have the following attributes:
        • The heterogeneity of the composition, including the diversity of roles, technical
            knowledge, skills and personal characteristics of the participants [14, 15];
        • Coordination and synchronization, including awareness of the division of tasks within the
            team and the possibility of redistributing the load [16],
        • The intensity of information exchange associated with the high rate of changes in the
            information environment [16];
        • Integration and interaction, including the exchange of knowledge through the use of a
            single pool of data and information systems [14, 15];
        • The important role of informal communication, which allows you to form a common circle
            of interests and develop a common style of communication [15, 16, 17].
    The research was based on the hypothesis that the characteristics of the team shape the quality of
the project product and project processes and affect the efficiency of the team and the success of the
project. Below the Figure 1 shows the model for studying the dependence of project success on team
performance, introductory factors, dependencies and results.




Figure 1: Research model of project success dependence on team work efficiency

3. Formation of an effective IT project team
    In software development projects (IT teams), people (teams) are considered as a key factor in the
success of the project [19, 20], which allows us to consider the success of the project and the success
of the team as synonyms. In addition, the goal of a software development project is a product that
coincides with the output of agile IT project teams. In this regard, for such projects, the parameters of
the project results can be equated to the parameters of the command result [19, 20].
    In this regard, the parameters of the team's result can be conditionally equated with the parameters
of the project's result, especially for flexible teams of IT projects, in which the result of the team's
activity is a product that determines the goal of the project.
    The factors related to the team activities, which directly or indirectly affect the parameters of the
results of the team's work and the success of the project, will be called the factors of the effectiveness
of the team. The process of creating an effective team is complex, as it depends on many factors that
have a complex structure and change over time. The factors can be divided into two groups according
to the principle of localization: organizational (factors located in the zone of influence of the team)
and environmental factors (factors outside the zone of influence of the team) [12].
    Organizational factors include:
        • Factors of group interaction (behavior) - communication, coordination), cooperation,
            relations between participants, previous experience of interaction of participants;
        • Social and psychological properties of a small group or properties of group processes
            (group dynamics) - cohesion, leadership, focus on mutual support, social identification and
            commitment;
        • Factors of composition and structure - team abilities, team intellectual capital, team size,
            compatibility of individual characteristics of the participants.
    Environmental factors include:
        • Type of project environment
        • Parameters of the organization's environment,
        • Top management support.
    The properties of group processes and factors of group interaction relate to the relationship of the
team, and the factors of composition and structure mainly depend on the individual characteristics of
the team members.
    For new teams that are formed at the start of the project, there may not be enough information
about the direct relationships between the participants, so it makes sense to consider primarily the
compatibility of the team [13]. Compatibility is a factor of conformity, compatibility of one team
member with others in terms of a number of parameters, under the influence of which the team is
either strengthened or weakened.
    The best use of individual and professional qualities of team members can be ensured through
various mechanisms of psychological compatibility. The most important ones are the following:
        1. The similarity and complementarity, the similarity of the characteristics of the team
            members, is used for teams that solve formalized repeatable tasks, for example, in
            operational activities (crews of ships, aircraft, conveyors);
        2. Complementarity, diversity - complementarity, applicable for teams solving non-
            formalized atypical tasks, for example, in project activities (a team of designers and
            software developers);
        3. The contrast of properties and qualities, complete diversity, leads to effective activity only
            when all team members have a pronounced striving for a common collective goal; rarely
            used.

3.1.    Development process of the IT project team
   Team building - actions for the selection of participants, optimization of the team structure and
functional-role distribution [11]. The formation of a team is consonant with one of the stages of the
formation of a team, and is an organized accompaniment of this stage [18]. The goal of the team
building process is to build an effective team.
   In general, team building is a complex process influenced by many factors. The success of team
building depends on the parameters of the team, the behavior of the participants, as well as the
effective work of the project manager in building the team in traditional IT projects.
Figure 2. Project team development process

   The successful work of the project team is influenced by both group interaction factors and
individual influence factors. It is important to evaluate the possibility of building a team taking into
account both sides of the impact. Individual factors are individual social experience and direction of
personal development (career growth and values).
   The properties of group processes include the most significant factors: team size (structure
parameter), cohesion, leadership.
   Can be argued that an IT Project Team is effective if:
       1. The size of the team is the smallest possible with a full set of skills and available time for
            the required speed of work (from 3 to 10 people);
       2. There is a high level of cohesion in the core of the team (leaders in terms of the number of
            connections), there may be a lack of connections with individual team members
            (outsourcing of insignificant work);
       3. There is a high degree of recognition of the leader (more than half of the team members),
            the leader by recognition is a participant with the greatest intellectual capital in terms of
            contribution to the project;
       4. The team of leaders all have a predominant focus on "themselves", team members - on
            "business", the minimum number of people with an orientation toward "communication":
       5. The team leader has a high service orientation; the leadership team has a high skill
            orientation;
       6. The team has a full set of roles (GI - generator of ideas, NA - analyst, CR - critic), there is
            a predominance of action roles over mental, and mental over social roles, a small number
            of GI and NA in comparison with other roles;
       7. The intellectual capital of the team of leaders should be multi-level: a combination of one
            intellectual leader and several social leaders with less intellectual capital is preferable.

4. Method of selecting a candidate to IT project team leader
   The project manager plays an important role in forming an effective IT project team. He must have
a wide range of knowledge in the field of IT project management, know all stages of the project life
cycle. However, the most important area of his activity is effective cooperation with a large number of
people: team members and project stakeholders.
   The project manager must understand people, evaluate and anticipate what can be expected of
them in a given situation. Such knowledge helps him to find contact with team members and other
project participants. Understanding people's psychology will allow the project manager to take the
right position in negotiations, meetings, conflicts, as well as to take people in favor of the project with
maximum effect.
   The choice of a candidate for the project manager role is great importance and influence on the
further success of the team and the project as a whole. You need to use effective tools for this.
   The hierarchy analysis method will help to choose the candidate for the role of IT project team
leader [23-38].
   The first stage is a developing a hierarchical structure of the problem of choosing a candidate for
the role of IT project team leader (Figure 3).




Figure 3. Hierarchical structure of the candidate's choice for the role of IT project team leader

   The second stage is forming a matrix of pairwise comparisons for the elements of the first level of
the hierarchy (criteria). Using a scale of relative weight of the criteria (Table 1) after interviewing a
expert group to form a team of IT project, next step is to build a matrix of pairwise comparisons of the
weight of the criteria (Table 2). The following characteristics are taken into account when selecting
experts: competence in the field of IT project management, high level of communication, collective
perception. Most of these characteristics are evaluated qualitatively, not quantitatively.

Table 1.
Scale of relative criteria weight
   Intensity of relative weight                             Definition
                               Unambiguous (accurate) assessment
              1                                         Equivalent weight
              3                                       Moderate advantage
              5                                        Average advantage
              7                                  The advantage is above average
              9                                      A significant advantage
           Compromise cases (intermediate decisions between two adjacent assessments)
              2                       Between equivalent weight and moderate advantage
              4                            Between moderate and medium advantage
              6                   Between the average advantage and the advantage above the
                                                              average
              8                     Between the above-average advantage and the significant
                                                            advantage
                                         Inverse values
                 1/k                             Used to evaluate non-predominant elements

Table 2.
Scale of relative criteria weight
         Criteria                   Value (С1)             Cost (С2)                   Risks (С3)
       Value (С1)                       1                      2                           6
        Cost (С2)                      1/2                     1                           4
        Risks (С3)                     1/6                    1/4                          1

   Next, calculate the basic parameters of the matrix by formulas. Calculation of the main eigenvector
of the vector                       positive square matrix            implemented on the basis of the
definition of equality:           , were      - the maximum eigenvalue of the matrix A.
   The components of the eigenvector of local priorities are calculated by the formulas:

                                        =            ,                                                  (1)

Where       – i element of the j-column of pairwise comparisons matrix of criteria;
n – is the number of criteria,

                                                 ,                                                      (2)

   The calculation of the main eigenvector of the criterion local priorities is presented in Table 3.

Table 3.
The calculation of the main eigenvector of the criteria local priorities
                                     Eigenvector components of local
Сriterion С1           С2    С3                                      Local priorities
                                     priorities

С1
             1         2     6

С2
             1/2       1     4

С3
             1/6       1/4   1




   Next, determine the consistency of local priorities:
   a) the maximum eigenvalue of the matrix        :

                                                                                                (3)




   b) estimates of the relative importance of the elements being compared must be consistent, so
determine the index (CI) and the ratio (CR) of consistency:
                                                                            ,
                                                                                                   (4)
were N – the number of random agreements.
   At the third stage forms matrices of pairwise comparisons of alternatives on each criterion (Tables
4-6).

Table 4
Matrix of pairwise comparisons for alternatives by the criterion "Value"
                                              Team leader
Value                                                                      Vector of priorities
                    CC1              CC2              CC3       CC4
CC1                 1               2                 5         6          0,673
CC2                 1/2             1                 4         5          0,43
CC3                 1/5             1/4               1         2          0,136
CC4                 1/6             1/5               1/2       1          0,087

   In accordance                ,                ,

Table 5
Matrix of pairwise comparisons for alternatives by the criterion "Cost"
                                              Team leader
Cost                                                                        Vector of priorities
                     CC1             CC1              CC1       CC1
CC1                  1               1/6              1/8       1/9         0,0352
CC2                  6               1                1/4       1/5         0,1265
CC3                  8               4                1         2           0,4835
CC4                  9               5                1/2       1           0,363

   In accordance                 ,                ,

Table 6
Matrix of pairwise comparisons for alternatives by the criterion "Risks"
                                               Team leader
Risks                                                                        Vector of priorities
                        CC1             CC1               CC1       CC1
CC1                     1               1/3               1/7       1/8      0,048
CC2                     3               1                 1/2       1/5      0,1276
CC3                     7               2                 1         1/3      0,2535
CC4                     8               5                 3         1        0,571

   In accordance                    ,             ,
   The vector of global priorities of alternatives was calculated. For this purpose, from vectors of
local priorities of alternatives on each criterion will be made a matrix.
                                                                       ,

   Next, calculate using the formula:
                                                                                                     (5)
   Therefore, the vector of global priorities is equal to:




   Based on the obtained priority values, choosing the alternative CC1, because the maximum
component of the vector of global priorities corresponds to the first alternative.
   And although the criteria for selecting a candidate for the role of team leader of the IT project are
demanding, using MAH (this technique), it is possible to choose the leader who will succeed in the
project.

5. Conclusions
    The article considers the current problem of decision-making on the selection of a candidate for
the role of IT project team leader in the conditions of multi-purpose and multi-criteria uncertainties.
With the help of MAH (Saati method) the optimal candidate was selected from the proposed ones,
criteria were determined that are important for the investor (customer). This technique can be used in
the educational process in the form of laboratory and term papers, in theses and directly in production
in IT project management, when it is necessary to choose the optimal candidate for the role of IT
project team leader, guided by specific requirements of the investor (customer).
    Thus, working on existing knowledge and practices for the formation of an effective IT project
management team, it can be concluded that the success of the entire project directly depends on the
effectiveness of the team.
    When choosing a new team member, it is necessary not only to evaluate his experience,
knowledge, practical skills, but also to take into account how he fits the existing team, how it
complements the individual characteristics of the whole team. If it is considered the process of team
building from the point of view of individual psychological and personal characteristics, it is
necessary to set up remote team work, which in modern conditions will be effective and safe. The
team leader must select new members so that they complement the roles of the team, correspond to
the psychological types of other members, have common values. It is equally important to choose the
right leader for the team.
    The article proposes a method of selecting candidates for the role of project manager, based on the
method of hierarchy analysis. This method allows to determine the satisfaction of the candidate
requirements for the position and choose the best manager and leader for the project team.

6. Acknowledgements
   This work is a combination of scientific topics of doctoral students. The issue of creating a
successful project team today is relevant and important, given the circumstances in which companies
have to work. We thank the work of domestic and foreign scientists, such as Bushuyev S, Verenych
O, Bushuyeva N, Wagner, R, Yilmaz M., Yngve Lindsjorn and others, whose scientific work became
the basis and inspired further research.
7. References
[1] О. Danchenko, D. Bedrii, I. Semko, Conceptual model for the formation of a highly effective
     scientific project team, Bulletin of the National Technical University "KhPI", Strategic
     Management, Portfolio, Program and Project Management, vol. 1 (1277), (2018) 51-56. DOI:
     10.20998/2413-3000.2018.1277.8
[2] A. Voitushenko, S. Bushuyev, Reative potential as a factor of influence on the effective work of
     collective, Management of Development of Complex Systems, vol. 29, (2017) 34 –39.
[3] Ye. Kolesnikova, D. Lukyanov, O. Sherstyuk, Evaluation of the effectiveness of teamwork at the
     stage of project initiation, Project management and production development, vol. 21, (2015), 37–
     42.
[4] S. Kramskoy, Method of assessment of professional competence of role for IT-company using
     fuzzy logic, Management of Development of Complex System, vol.28, (2016), 81–89.
[5] I. Kononenko, G. Sushko, Formation of a project team for the developing of information and
     communication technologies, Information Technologies and Learning Tools, vol. 73 (5), (2019),
     307-322.
[6] V. Moskalenko, Modern approaches to project team formation, Business and Intellectual Capital,
     vol. 5, (2014), 78–86.
[7] S. Bushuyev, V. Molokanova, Formalization of the method of taking into account value memes
     in the portfolios of organizations development and ICT tools for its implementation, Information
     Technology and Learning Tools, vol. 62 (6), (2017) 1-15.
[8] S. Bushuyev, D. Bushuyev, N. Bushuyeva, B. Kozyr, Information technologies for the
     development of project management managers competencies based on global trends, Information
     Technologies and Learning Tools, vol. 68 (6), (2018), 218 – 234.
[9] V. Semenyshyn, I. Oleksiv, Theoretical approaches to communications management in IT
     industry of Ukraine. Econtechmod. An International Quarterly Journal on Economics in
     Technology, New Technologies and Modelling Processes 2(4) (2013) 67–72.
[10] V. S. Kumar, Essential leadership skills for project managers, Proceedings of the PMI Global
     Congress ’09, Project Management Institute, Newtown Square, Orlando, FL North America,
     2009. URL: https://www.pmi.org/learning/library/essential-leadership-skills-project-managers-
     6699
[11] G. Caupin, ICB IPMA Competence Baseline, Version 3.0., International Project Management
     Association, USA, 2006.
[12] Project Management Knowledge Base Guide (PMBOK Guide). 5th ed., Project Management
     Institute, USA, 2013.
[13] Software Extension to the PMBOK Guide. 5th ed., Project Management Institute, USA, 2013.
[14] Ali E. Akgün, Antecedents and consequences of collective empathy in software development
     project     teams,      Information     &    Management,     vol.     52,   (2015)      247–259.
     doi:10.1016/j.im.2014.11.004
[15] S. Hansen, Getting on the same page: Collective hermeneutics in a systems development team,
     Information and Organization, vol.20, (2010) 44–63. doi:10.1016/j.infoandorg.2010.01.001
[16] Yngve Lindsjorn, Dag I.K. Sjoberg, Torgeir Dingsoyr, Teamwork quality and project success in
     software development: A survey of agile development teams, The Journal of Systems and
     Software, vol. 122, (2016) 274–286. doi: 10.1016/j.jss.2016.09.028
[17] S. A. Licorish, Communication and personality profiles of global software developers,
     Information       and        Software     Technology,     vol.      64,    (2015)       113–131.
     doi: 10.1016/j.infsof.2015.02.004
[18] S.A. Shapiro, Organizational behavior, KNORUS, Moscow, Russia, 2012.
[19] M. André, Formal model for assigning human resources to teams in software projects,
     Information       and        Software     Technology,     vol       53,    (2011)       259–275.
     doi: 10.1016/j.infsof.2010.11.011
[20] M. Yilmaz, An examination of personality traits and how they impact on software development
     teams, Information and Software Technology, vol. 86, (2017) 101–122. doi:
     10.1016/j.infsof.2017.01.005
[21] Hsu, Shu-Chien, Understanding the complexity of project team member selection through agent-
     based modeling, International Journal of Project Management, vol.34, (2016) 82–93. doi:
     10.1016/j.ijproman.2015.10.001
[22] S. Bushuyev, R. Wagner, IPMA Delta and IPMA Organisational Competence Baseline (OCB):
     New approaches in the field of project management maturity, International Journal of Managing
     Projects in Business, vol. 7 (2), (2014) 302-310.
[23] T. Saati, K. Cairns, Analytical planning, Organization of systems. Radio and communication,
     Moscow, Russia, 1991.
[24] M. Odrekhivskyy, V. Pasichnyk, A. Rzheuskyi, V. Andrunyk, M. Nazaruk, O. Kunanets, D.
     Tabachyshyn, Problems of the intelligent virtual learning environment development. CEUR
     Workshop Proceedings 2386 (2019) 359–369.
[25] R. Kaminskyi, N. Kunanets, V. Pasichnyk, A. Rzheuskyi, A. Khudyi, Recovery gaps in
     experimental data. CEUR Workshop Proceedings 2136 (2018) 108–118.
[26] A. Rzheuskyi, H. Matsuik, N. Veretennikova, R. Vaskiv, Selective Dissemination of Information
     – Technology of Information Support of Scientific Research. Advances in Intelligent Systems
     and Computing 871 (2019) 235–245.
[27] V. Pasichnyk, V.Lytvyn, N.Kunanets, R. Vovnyanka, Y. Bolyubash, A. Rzheuskyi, Ontological
     approach in the formation of effective pipeline operation procedures, in: 13th International
     Scientific and Technical Conference on Computer Sciences and Information Technologies,
     CSIT, 2018, pp. 80–83.
[28] R. Kaminskyi, N. Kunanets, A. Rzheuskyi, A. Khudyi, Methods of statistical research for
     information managers, in: Proceedings of the 13th International Scientific and Technical
     Conference on Computer Sciences and Information Technologies, CSIT 2018, 2018, pp. 127–
     131.
[29] А. Kazarian, N. Kunanets, R. Holoshchuk, V. Pasichnik, A. Rzheuskyi, Information Support of
     the Virtual Research Community Activities Based on Cloud Computing, in: Proceedings of the
     13th International Scientific and Technical Conference on Computer Sciences and Information
     Technologies, CSIT 2018, 2018, pp. 199–202.
[30] A. Rzheuskiy, N. Veretennikova, N. Kunanets, V. Kut, The information support of virtual
     research teams by means of cloud managers. International Journal of Intelligent Systems and
     Applications 10(2) (2018) 37–46.
[31] V. Pasichnyk, D. Tabachyshyn, N. Kunanets, A. Rzheuskyi, Visualization of Expert Evaluations
     of the Smartness of Sociopolises with the Help of Radar Charts. Advances in Intelligent Systems
     and Computing 938 (2020) 126–141.
[32] V. Pasichnyk, N. Kunanets, N. Veretennikova, A. Rzheuskyi, M. Nazaruk, Simulation of the
     Social Communication System in Projects of Smart Cities, in: Proceedings of the 14th
     International Scientific and Technical Conference on Computer Sciences and Information
     Technologies, CSIT 2019, 2019, pp. 94–98.
[33] E. Vasilevskis, I. Dubyak, T. Basyuk, V. Pasichnyk, A. Rzheuskyi, Mobile application for
     preliminary diagnosis of diseases. CEUR Workshop Proceedings, 2255 (2018) 275–286.
[34] A. Rzheuskyi, N. Kunanets, V. Kut, Methodology of research the library information services:
     the case of USA university libraries. Advances in Intelligent Systems and Computing 689 (2018)
     450–460. doi:10.1007/978-3-319-70581-1_32.
[35] H. Lypak, V. Lytvyn, O. Lozynska, R. Vovnyanka, Y. Bolyubash, A. Rzheuskyi, D. Dosyn,
     Formation of Efficient Pipeline Operation Procedures Based on Ontological Approach. Advances
     in Intelligent Systems and Computing 871 (2019) 571–581.
[36] A. Shakhov, V. Piterska, O. Sherstiuk, O. Rossomakha, A. Rzheuskyi, Management of the
     technical system operation based on forecasting its “aging”. CEUR Workshop Proceedings 2565
     (2020) 130–141.
[37] M. Odrekhivskyy, N. Kunanets, V. Pasichnyk, A. Rzheuskyi, D. Tabachishin, Information-
     analytical support for the processes of formation of smart sociopolis of Truskavets. CEUR
     Workshop Proceedings 2393 (2019) 241–256.