        <article-title>Production planning in a construction company as an element of Gartner enterprise architecture</article-title>
      </title-group>
      <contrib-group>
        <contrib contrib-type="author">
          <string-name>S S Valeev</string-name>
          <xref ref-type="aff" rid="aff0">0</xref>
          <xref ref-type="aff" rid="aff1">1</xref>
        </contrib>
        <contrib contrib-type="author">
          <string-name>N V Kondratyeva</string-name>
          <xref ref-type="aff" rid="aff0">0</xref>
        </contrib>
        <contrib contrib-type="author">
          <string-name>R R Karimov</string-name>
          <xref ref-type="aff" rid="aff1">1</xref>
        </contrib>
        <contrib contrib-type="author">
          <string-name>M A Verkhoturov</string-name>
          <xref ref-type="aff" rid="aff1">1</xref>
        </contrib>
        <contrib contrib-type="author">
          <string-name>T V Islamgulov</string-name>
          <xref ref-type="aff" rid="aff1">1</xref>
        </contrib>
        <contrib contrib-type="author">
          <string-name>L I Shekhtman</string-name>
          <xref ref-type="aff" rid="aff1">1</xref>
        </contrib>
        <aff id="aff0">
          <label>0</label>
          <institution>Sochi State University</institution>
          ,
          <addr-line>Politekhnicheskaya Str. 7, Sochi, 354008</addr-line>
          ,
          <country country="RU">Russia</country>
        </aff>
        <aff id="aff1">
          <label>1</label>
          <institution>Ufa State Aviation Technical University</institution>
          ,
          <addr-line>K. Marx Str. 12, Ufa, 450008</addr-line>
          ,
          <country country="RU">Russia</country>
        </aff>
      </contrib-group>
      <abstract>
        <p>The problem of production planning as an element of Gartner enterprise architecture in a distributed organizational and technical system is considered on the example of a construction company of medium and large scale. Mathematical models for planning organizational and technical resources in a distributed system as elements of patterns are discussed. In the development of the information and application layers, field-proven solutions can be used as patterns. The approach to the organization of business processes of a construction company that allows solving the problem of optimal scheduling of construction works while simultaneously executing a number of projects by the company and, thus, increasing the management efficiency of a geographically distributed enterprise is considered. The enterprise architecture as a unified information environment for managers of a construction company, site managers, supply engineers, designers, and estimates is discussed.</p>
      </abstract>
    </article-meta>
  </front>
  <body>
    <sec id="sec-1">
      <title>1. Introduction</title>
      <p>Construction companies attribute to the class of distributed large-scale systems, characterized by a
multi-level management system and a geographically distributed structure. Since they simultaneously
implement business processes at several geographically remote sites, in order to solve their production
tasks, various subcontractors are involved in production and supplies.</p>
      <p>
        To improve the efficiency of the construction company, various approaches are used, based on a
phased transition from traditional data processing to a digital company within the framework of the
Industry 4.0 concepts [
        <xref ref-type="bibr" rid="ref1 ref2">1, 2</xref>
        ]. One such approach is the development of enterprise architecture.
Enterprise architecture includes basic elements [
        <xref ref-type="bibr" rid="ref3">3</xref>
        ], patterns [
        <xref ref-type="bibr" rid="ref4">4</xref>
        ], business process models [
        <xref ref-type="bibr" rid="ref5">5</xref>
        ] and
models of interaction with the external environment [
        <xref ref-type="bibr" rid="ref6">6</xref>
        ].
      </p>
      <p>
        Construction business is associated with the expenditure of significant amounts of labor, material
and financial resources on the facilities being built in parallel. At the planning stage of construction
production, it is necessary effectively distribute various types of resources between construction
facilities in order to increase the efficiency of the entire enterprise [
        <xref ref-type="bibr" rid="ref7 ref8">7, 8</xref>
        ]. Thus, in the face of market
competition and a difficult financial situation, the company needs operational planning methods [
        <xref ref-type="bibr" rid="ref9">9</xref>
        ].
      </p>
      <p>
        The task of planning and managing geographically distributed production divided into two levels –
the level of the local construction site and the level of the parent company [
        <xref ref-type="bibr" rid="ref10">10</xref>
        ].
      </p>
      <p>Considering that the process of designing a work plan based on a mathematical model for
optimizing time costs and optimal distribution of tasks, we will further consider these tasks as the
main elements of the design of the architecture of a construction company.</p>
      <p>
        The article discusses the formulation of the problem associated with the development of the
architecture of a construction company as a distributed production system. To improve the efficiency
of developing an information system, it is proposed to use an architectural approach in its
development. As a basic architecture, it is proposed to use an enterprise architecture based on the
Gartner architecture [
        <xref ref-type="bibr" rid="ref3">3</xref>
        ]. This enterprise architecture includes basic elements, patterns, business
process models and models of interaction with the external environment. The following discusses the
architectural features of developing an information system using this approach.
      </p>
      <p>The mathematical formulation of the problem of optimizing business processes as a basic pattern is
considered. This optimization model can serve as a basis for developing the architecture of a
construction company.</p>
      <p>The problem of developing a set of patterns for enterprise architects is considered on the example
of patterns of basic business processes and the schedule of work of a construction company. A
prototype of the architecture of a construction company based on the Gartner enterprise architecture is
proposed.</p>
    </sec>
    <sec id="sec-2">
      <title>2. Statement of the problem</title>
      <p>Cost reduction in construction is carried out not only by rational space-planning solutions of buildings,
the correct choice of building and finishing materials, lightening of construction, improvement of
construction methods, but also by effective management of all activities of a construction company,
prompt allocation of resources and optimization of the production plan [11, 12].</p>
      <p>Let us further consider the scheme of interaction between the parent enterprise and construction
projects during production planning, presented in figure 1. Here Mi is the system of organizational and
technical management of the i-th construction project, and then Ei is environment for the i-th
construction project. Elements AS (actuator system) are subsystems for the implementation of control
commands coming from a system Mi. Elements SS (sensors system) are subsystems for collecting
information about the state of business processes and resources. DES (distributed enterprise
information system) is a system for collecting, storing and transmitting data for a construction
company. EMS is an enterprise management system.</p>
      <p>The task is to integrate all these subsystems based on enterprise architecture (see figure 2) [13, 14].</p>
      <p>The functioning of a geographically distributed enterprise is associated with a number of different
problems. In particular, a large number of remote units leads to an increase in the complexity of
collecting information about their activities and complicates the procedures for processing it. Late
receipt of operational information on the state of business processes about construction projects is one
of the main factors that reduce the efficiency of management of a construction company, in particular,
planning and cost management processes of an enterprise.</p>
      <p>To analyze the initial data of a construction project, a significant number of specialists from a
construction company are involved, i.e. site managers, supply engineers, designers, cost estimating
engineers, etc. However, even with a detailed commercial proposal, a sufficiently high accuracy of
assessing the state of business processes is not ensured due to their complexity and impact of various
uncertainties.</p>
      <p>Usually, production planning carried out only for each local facility. This is due to objective
reasons related to the specifics of the construction business. Existing approach does not allow
assessing the state of the entire production system of the company, i.e. to optimally distribute its
resources across all facilities and make prompt decisions on planning and production management. As
a result, the term and cost of the project is determined either by expert or by regulatory methods based
on the calculation of the duration of projects’ tasks and works, which can cause significant deviations
from the actual production targets.</p>
      <p>For the customer of the construction contract, the durations and costs of work are key parameters
when choosing a contractor. Penalties for failure to meet contractual deadlines can be up to 30% of the
contract value.</p>
      <p>Preliminary planning of production processes in a distributed production system allows
coordinating and optimizing the redistribution of resources used between construction sites in the early
stages of production. This allows construction manager to develop a consolidated linear-scale schedule
(detailed plan of work) for the distribution of the company's own and borrowed resources, based on
the plan for resource costs at all construction sites, as well as optimally select the algorithms for
synchronizing data flows obtained at various stages of the life cycle of all construction sites.</p>
      <p>Improving the efficiency and reliability of assessing the required resources for a local construction
site and for the entire set of facilities of a construction enterprise as an organizational and technical
system is an urgent task.</p>
      <p>
        This problem is can be solved using network planning methods and BPM technology. It is
proposed to solve this problem based on the development of a prototype of the architecture of a
construction company within the framework of the Gartner methodology [
        <xref ref-type="bibr" rid="ref3">3</xref>
        ].
      </p>
      <p>Consider further the process of developing elements of enterprise architecture for the presented task.</p>
    </sec>
    <sec id="sec-3">
      <title>3. Mathematical models of construction company economic efficiency</title>
      <p>
        At the stage of developing an information system (see figure 2), basic blocks (models) are needed to
solve the problems of optimizing the resources of a construction company. These mathematical
models can be used by all participants in production processes and can be part of the enterprise
information system [
        <xref ref-type="bibr" rid="ref10">10</xref>
        ].
      </p>
      <p>The efficiency of an investment construction project can be estimated using the functions of
income D(t)  max and costs P(t)  min .</p>
      <p>tS tS
In this case, the economic efficiency of the project is defined as follows:</p>
      <p>The function of the company's income for a given period of time can be calculated using the
formula:</p>
      <p>E(t)  D(t)  P(t)  max .</p>
      <p>n
D(t)   D j (t),
j0
(1)
(2)
(3)
where j  (1, n) , n is a number of local construction objects (see figure.1); D j t  is income from j-th
local object.</p>
      <p>The cost function of a construction company for a given period of time t is represented as follows:
P(t)   Pj t, rM j (t), rT (t), rF (t), rH j (t) ,
n</p>
      <p>j j
j 1
where</p>
      <p>rM j (t) is the dependence of the costs of material resources of the system for the j-th
construction object on time;
rT j (t) is dependence of the costs of technical resources of the system for the j-th object;
rF (t) is the dependence of the costs of financial resources of the company for the j-th object;
j
rH j (t) is the dependence of the costs of human resources of the system for the j-th object.</p>
      <p>The model also takes into account time constraints tCRj  TCj , where TСj is construction time;
tCRj is the duration of the critical path of the j-th construction object.</p>
      <p>Total company resources constraints R should also be considered:
n
 rM j (t)  RM (t),
j1
n
 rT (t)  RT (t),
j1 j
n
 rF (t)  RF (t),
j1 j
n
 rH j (t)  RH (t).</p>
      <p>j1
1, if i - th worker can be assigned to j - th task;
aij  </p>
      <p>0, otherwise.</p>
      <p>i  1, m, j  1, n.</p>
      <p>Let the matrix of working time be given as W={wil} where wil is the number of free working time
for the i-th worker on the l-th day, i  1, m, l  1, d.</p>
      <p>The sought values are the elements of the assignment matrix X:






</p>
      <p>Thus, this statement of the problem can serve as a basis for the development of a pattern of the
main goals of a construction company (see figure 2).</p>
      <p>Let us further consider the mathematical problem of planning organizational resources for a
construction company to create a pattern for planning the resources of a company (see figure 2).</p>
      <p>When planning organizational resources, the problem arises of the best distribution of employees
(workers) for construction projects and for individual activities (tasks) within the framework of
business processes on the constructed objects, taking into account the requirements and restrictions for
a given object, for example, with the object's budget and the durations of the works.</p>
      <p>The initial data are the following:
 m is number of workers;
 n is number of tasks (activities);
 d is duration of the planned period of the task;
 W is total payroll;
 K  k1, k2 ,ki ,..., km is set of workers;
ki  k1i , k2i  is vector of characteristics of the i-th worker;
k1i is payment per hour for the i-th worker, k2i is assessment of the qualifications of the i-th
worker, i  1, m ;
R  r1, r2 ,rj,..., rn is set of tasks;
rj – vector of characteristics of the j-th task;
rj  r j , r2j , r3j , r1j is duration for j-th task;</p>
      <p>1
r2j is assessment of the qualifications required for j-th task;
r3j is the number of days from the beginning of the planned period to the deadline for the
completion of the j-th task, j  1, n .</p>
      <p>Let the elements of the matrix of feasible assignments A be described as follows:
(4)
(5)
m
 xij  1,
i1
xij  1</p>
      <p>Let us introduce a number of constraints. Only one worker can be assigned to each task:
j  1, n. Each task can only be assigned to a
worker admitted to this task:
aij  1, i  1, m,</p>
      <p>j  1, n. The qualifications of the appointed worker must be at least equal
to the qualifications required to perform the task: xij  1
k2i  r2j , i  1, m,
j  1, n. Limitation on
As an objective function, consider the total qualifications of a team of workers:</p>
      <p>1, if i - th worker is assigned to j - th task;
xij  </p>
      <p>0, otherwise.
 S 
where mSin l l _mwin il  r1j  is the number of days it will take for the i-th worker to complete the j-th

task. Limitation on the maximum workload of workers during the day is  i  1, m
n d
 xijr1j   wil .
j1 l1</p>
      <p>To avoid overloads, underloads in designing a work schedule and tasks without performers, the
available organizational are distributed between a set of simultaneously executed construction projects
in accordance with the mathematical model of the distribution of organizational resources (5) - (8).
The optimal distribution of material, financial and technical resources is calculated in accordance with
the mathematical model (1) - (4).</p>
      <p>The considered optimization patterns are implemented based on algorithmic patterns to form
enterprise architecture within the Gartner framework (see figure 2).</p>
    </sec>
    <sec id="sec-4">
      <title>4. Enterprise architecture patterns design</title>
      <p>During construction, the construction site manager monitors the utilization rate of a particular resource
in certain tasks, and uses additional resources if necessary.</p>
      <p>This task is solved based on specialized information systems. To implement the network planning
algorithm, the main business processes for the construction of a given object are determined, their
relationship and duration are determined, a network schedule is drawn up and the total duration of the
entire project is determined (see figure 3).
(6)
(7)
(8)</p>
      <p>To solve this problem, a set of models has been implemented using business processes and a visual
programming language.</p>
      <p>As a means of implementing the models, the BPMN language was chosen, which meets modern
requirements and includes a set of effective tools capable of implementing a wide range of tasks. An
important point is that a business analyst without the participation of a programmer can perform the
design of business processes.</p>
      <p>The creation of any business process begins by modelling an organizational structure, on the base
of which the executors of processes and sub-processes are determined. Next, a top-level main process
is created, in which lower-level sub-processes are included, which provides multi-level detailing.</p>
      <p>Based on the developed model of business processes and the corresponding mathematical model, it
is possible to find the necessary critical path for the implementation of the sequence of works on the
construction of a local construction site.</p>
      <p>Algorithms for solving the problem of finding the optimal route on the work execution graph are
selected from a set of algorithm patterns PA.</p>
      <p>Consider further an example of developing an optimal work execution plan, taking into account the
given constraints. The considered method of constructing a network plan for a construction site
includes four main stages: determining a list of works (see table 1), building a network, calculating
and building a time schedule.</p>
      <p>Based on the initial data (table 1), a preliminary simplified network schedule for the construction of
one of the facilities was developed (see figure 3).</p>
      <p>Herewith, critical processes were singled out, on which the total durations for completing
construction process depends (for example, the construction of a building frame), and non-critical
ones, on which the total durations depend not so rigidly (for example, laying internal
communications).</p>
      <p>Note that in case a construction company is carrying out similar projects, the schedule (see figure
4) can be used as a design pattern.</p>
      <p>This pattern, when filled with data, makes it possible to solve the problem of finding the optimal
solution based on the algorithms included in the set of algorithms for finding the optimal path on the
graph.</p>
      <p>The final cost estimate displays the volume and total cost of work, as well as the size of the wage
fund and the total number of standard person-hours.</p>
      <p>Based on the total number of labor costs, the total duration of the work was preliminarily calculated
is 48 days, the possible parallel execution of various types of work was also taken into account.</p>
      <p>Further, the duration of the critical path was determined on the base of constraints and the model
(see figure 4), which decreased to 39 days.</p>
      <p>Thus, we can conclude that the assessment of the timeframe for the completion of all works, based
on the proposed approach, turned out to be more accurate. A more accurate forecast of the final terms
allows enterprise manager to make a more attractive commercial proposal for the customer, which
improves competitive advantage of company.</p>
      <p>It also possible to prove that an unreasonable reduction in terms leads to the decline in quality of
construction works.</p>
      <p>In our case, one of the patterns for shaping the architecture of a construction company can be a
typical network schedule for the construction of an object.</p>
      <p>On the base of this schedule, it is possible to optimize business processes for each of the
construction objects, thereby solving the problem of synchronizing business processes and optimal use
of company resources (see figure 5).</p>
      <p>1919628
2410224</p>
      <p>O-2
I-1</p>
      <p>L-1
2119730</p>
      <p>P-2
16113129
2319832</p>
      <p>R-7</p>
      <p>K-2</p>
      <p>Based on the proposed approach to designing the architecture of an enterprise information system,
a prototype of a system was developed for a medium-sized construction company. Typical business
processes, a business process optimization model and schedule patterns taking into account the
specifics of business processes were used as patterns in the design of the system (see figure 6).</p>
    </sec>
    <sec id="sec-5">
      <title>5. Conclusions</title>
      <p>Modern construction companies can be attributed to the class of large-scale systems, characterized by
a multi-level management system. Usually, companies have a geographically distributed structure and
so simultaneously implement business processes at several geographically remote sites.</p>
      <p>In order to solve their production tasks, various subcontractors are involved in production and
supplies. To improve the efficiency of the construction company, various approaches are used, based
on a phased transition from traditional data processing to a digital company within the framework of
the Industry 4.0 concepts.</p>
      <p>One such approach is the development of Gartner enterprise architecture. Enterprise architecture
includes basic elements, patterns, business process models and models of interaction with the external
environment.</p>
      <p>The article discusses the formulation of the problem associated with the development of the
architecture of a construction company as a distributed production system.</p>
      <p>The architectural features of building an information system based on the architecture proposed by
Gartner are discussed.</p>
      <p>The mathematical formulation of the problem of optimizing business processes is considered. This
statement can serve as a basis for the development of the architecture of a construction company. The
problem of developing patterns of enterprise architects is considered on the example of a pattern for
constructing a schedule for the work of a construction company. A prototype of the architecture of a
construction company based on the architecture by Gartner is proposed.</p>
      <p>The problem of development of elements of enterprise architecture for a construction company is
considered. Mathematical models for optimizing company resources and a typical network schedule
for the distribution of work were selected as the main design patterns.</p>
      <p>In the development of the information and application layers, field-proven solutions can be used as
patterns.</p>
      <p>The considered approach to the organization of business processes of a construction company
allows solving the problem of optimal scheduling of construction works while simultaneously
executing a number of projects by the company and, thus, increasing the management efficiency of a
geographically distributed enterprise.</p>
      <p>At the same time, it is possible to work in a unified information environment for managers of a
construction company, site managers, supply engineers, designers, estimates, etc. It also provides a
sufficiently high accuracy in assessing production parameters at the stage of making proposal of
construction project, which allows solving the problem of assessing the state of the entire enterprise,
optimal allocation of resources among objects and making prompt decisions on planning and
production management.</p>
      <p>The proposed improvement of planning in construction processes based on business process
management technology and the developed mathematical models for planning organizational and
technical resources in a distributed construction company makes it possible to increase the efficiency
of planning construction processes.
[11] Baldwin A and Bordoli D 2014 A handbook for construction planning and scheduling (Oxford:</p>
      <p>John Wiley &amp; Sons)
[12] Levy S M 2010 Construction process planning and management: an owner’s guide to successful
projects (Amsterdam: Elsevier)
[13] Valeev S, Kondratyeva N and Verkhoturov M 2019 Intelligent Decision Support System of
Operation Sequencing of Technological Processes Planning Proc. of 2019 International
Russian Automation Conference (RusAutoCon) pp 1-6
[14] Tchernykh A, Bychkov I, Feoktistov A, Gorsky S, Sidorov I, Kostromin R, Edelev A,
Zorkaltsev V and Avetisyan A 2021 Mitigating Uncertainty in Developing Scientific
Applications in Integrated Environment Proc. of the Institute for System Programming of
the RAS 33 pp 151-172</p>
    </sec>
  </body>
  <back>
    <ref-list>
      <ref id="ref1">
        <mixed-citation>
          [1]
          <string-name>
            <surname>Wilkins</surname>
            <given-names>J 2017</given-names>
          </string-name>
          <string-name>
            <surname>How Industry</surname>
          </string-name>
          <article-title>4.0 impacts globalization</article-title>
          [Online] Available: https://www.manufacturingglobal.com/technology/how-industry-40
          <string-name>
            <surname>-</surname>
          </string-name>
          impacts-globalisation
          <source>[Accessed</source>
          <volume>06</volume>
          .
          <fpage>04</fpage>
          .
          <year>2021</year>
          ]
        </mixed-citation>
      </ref>
      <ref id="ref2">
        <mixed-citation>
          [2]
          <string-name>
            <surname>Davis</surname>
            <given-names>N 2016</given-names>
          </string-name>
          <article-title>What is the fourth industrial revolution?</article-title>
          [Online] Available: https://www.weforum.org/agenda/2016/01/what
          <article-title>-is-the-fourth-industrial-revolution [</article-title>
          <source>Accessed</source>
          <volume>06</volume>
          .
          <fpage>04</fpage>
          .
          <year>2021</year>
          ]
        </mixed-citation>
      </ref>
      <ref id="ref3">
        <mixed-citation>
          <article-title>[3] Enterprise architecture for digital transformation</article-title>
          [Online] Available: https://www.gartner.com/en/ [Accessed 10.
          <fpage>04</fpage>
          .
          <year>2021</year>
          ]
        </mixed-citation>
      </ref>
      <ref id="ref4">
        <mixed-citation>
          [4]
          <string-name>
            <surname>Bharadwaj</surname>
            <given-names>A</given-names>
          </string-name>
          ,
          <string-name>
            <surname>El Sawy</surname>
            <given-names>O</given-names>
          </string-name>
          ,
          <string-name>
            <surname>Pavlou</surname>
            <given-names>P</given-names>
          </string-name>
          and
          <string-name>
            <surname>Venkatraman</surname>
            <given-names>N 2013</given-names>
          </string-name>
          <article-title>Digital business strategy: Toward a next generation of insights MIS Q</article-title>
          37 pp
          <fpage>471</fpage>
          -
          <lpage>482</lpage>
        </mixed-citation>
      </ref>
      <ref id="ref5">
        <mixed-citation>
          [5]
          <string-name>
            <surname>Hitt L M and Brynjolfsson</surname>
            <given-names>E</given-names>
          </string-name>
          1996 Productivity,
          <article-title>business profitability, and consumer surplus: Three different measures of information technology value</article-title>
          <source>MIS Q 20</source>
          pp
          <fpage>121</fpage>
          -
          <lpage>142</lpage>
        </mixed-citation>
      </ref>
      <ref id="ref6">
        <mixed-citation>
          [6]
          <string-name>
            <surname>Ross J W</surname>
            , Weill
            <given-names>P</given-names>
          </string-name>
          and
          <string-name>
            <surname>Robertson D 2006 Enterprise</surname>
          </string-name>
          <article-title>Architecture as Strategy: Creating a Foundation for Business Execution (Brighton</article-title>
          , MA, USA: Harvard Business Press)
        </mixed-citation>
      </ref>
      <ref id="ref7">
        <mixed-citation>
          [7]
          <string-name>
            <surname>Shanks</surname>
            <given-names>G</given-names>
          </string-name>
          ,
          <string-name>
            <surname>Gloet</surname>
            <given-names>M</given-names>
          </string-name>
          ,
          <string-name>
            <surname>Someh</surname>
            <given-names>I A</given-names>
          </string-name>
          ,
          <string-name>
            <surname>Frampton</surname>
            <given-names>K</given-names>
          </string-name>
          and
          <string-name>
            <surname>Tamm</surname>
            <given-names>T 2018</given-names>
          </string-name>
          <article-title>Achieving benefits with enterprise architecture J</article-title>
          .
          <source>Strateg. Inf. Syst</source>
          .
          <volume>27</volume>
          pp
          <fpage>139</fpage>
          -
          <lpage>156</lpage>
        </mixed-citation>
      </ref>
      <ref id="ref8">
        <mixed-citation>
          [8]
          <string-name>
            <surname>Lee</surname>
            <given-names>S</given-names>
          </string-name>
          ,
          <string-name>
            <surname>Oh S W and Nam</surname>
            <given-names>K 2016</given-names>
          </string-name>
          <article-title>Transformational and transactional factors for the successful implementation of enterprise architecture in public sector Sustainability 8 p 456</article-title>
        </mixed-citation>
      </ref>
      <ref id="ref9">
        <mixed-citation>
          [9]
          <string-name>
            <surname>Hazen</surname>
            <given-names>B T</given-names>
          </string-name>
          ,
          <string-name>
            <surname>Bradley</surname>
            <given-names>R V</given-names>
          </string-name>
          ,
          <string-name>
            <surname>Bell</surname>
            <given-names>J E</given-names>
          </string-name>
          ,
          <string-name>
            <surname>In</surname>
            <given-names>J</given-names>
          </string-name>
          and
          <string-name>
            <surname>Byrd</surname>
            <given-names>T A</given-names>
          </string-name>
          <year>2017</year>
          <article-title>Enterprise architecture: A competence-based approach to achieving agility and firm performance Management</article-title>
          193 pp
          <fpage>566</fpage>
          -
          <lpage>577</lpage>
        </mixed-citation>
      </ref>
      <ref id="ref10">
        <mixed-citation>
          [10]
          <string-name>
            <surname>Bottlik</surname>
            <given-names>G P</given-names>
          </string-name>
          <year>2017</year>
          <article-title>An introduction to the mathematics of planning and scheduling</article-title>