        <article-title>A Digital Platform for the Risk Assessment of Operating the Production Facilities of an Enterprise Based on Fuzzy Sets of Zadeh and OFN*</article-title>
      </title-group>
      <contrib-group>
        <aff id="aff0">
          <label>0</label>
          <institution>Finance University under the Russian Federation Government</institution>
          ,
          <addr-line>Moscow</addr-line>
          ,
          <country country="RU">Russia</country>
        </aff>
        <aff id="aff1">
          <label>1</label>
          <institution>Russian State Agrarian University − Moscow Timiryazev Agricultural Academy</institution>
          ,
          <addr-line>Moscow</addr-line>
          ,
          <country country="RU">Russia</country>
        </aff>
      </contrib-group>
      <pub-date>
        <year>1967</year>
      </pub-date>
      <fpage>0000</fpage>
      <lpage>0002</lpage>
      <abstract>
        <p>In a modern economy, many aspects of the decision-making process require mathematical support. The inability to formalize the initial data for analytical tasks contributes to implementing unconventional approaches in working with incoming data on ongoing business processes. One group of such approaches is fuzzy sets, fuzzy logic, fuzzy arithmetic, which can operate with poorly structured data in conditions of incomplete information. Business management should have tools based on digital platforms to minimize losses. For these purposes, one should substantiate a risk assessment methodology for the general case. The risk assessment itself is a quantitative characteristic of the relationship of two values. This characteristic forms in the context of assessing the lost income from the operation of the machine and the costs of acquisition, maintenance, and repair. The authors propose to utilize a digital platform based on fuzzy sets of Zadeh and their applications for calculating risks under specified criteria and fuzzy arithmetic according to the Zadeh and OFN extension principles for the risk assessment. During the operation of production facilities, particularly the functioning of fixed assets, the issue of risk assessment associated with the service life of machines (operating costs, maintenance costs, increase in the amount of failure, increase in maintenance costs, and the remaining practical resource of vehicles) comes to the fore. In this context, risks</p>
      </abstract>
    </article-meta>
  </front>
  <body>
    <sec id="sec-1">
      <title>-</title>
      <p>associate with losses and missed opportunities. The authors propose a weighing
formula that corrects the value of failure depending on the onset of
consequences. It makes it possible to adjust risk assessments depending on the
severity of the socio-economic consequences of the negative event occurrence.
1</p>
    </sec>
    <sec id="sec-2">
      <title>Introduction</title>
      <p>The relationship of results and losses can be determined in absolute or relative units or
probability assessments. Absolute values are determined by the possible difference
between the planned and obtained results. Although this approach is straightforward, it
is less informative for decision-making by business management. The probabilistic
approach is the most informative, and it prevents one from considering the initial data.
The authors obtain a probabilistic description of the functioning of this element by
modeling the operation of an element of production capacity with discrete Markov
chains with continuous time.</p>
      <p>
        Based on the results of the carried out calculations, the authors obtain the
assessment that there is an excess of the probability of failure over the probability of
operation in the ninth year. Therefore, the probabilities of operation [0.156529,
0.329818, and 0.493974], and the probabilities of failure [0.204099, 0.284616, and
0.372416] are two fuzzy triangular numbers (sets). The authors continue further
discourse implementing the hardware and software complex [
        <xref ref-type="bibr" rid="ref3">3</xref>
        ].
      </p>
      <p>The research sequentially presents the numbers using the scripting language of the
http://fuzzycalc.xyz/arithmetic service:
• Fuzzy set probability of operation for nine years of operation
a=0.156529; b=0.329818; c=0.493974;
A=TN(a,b,c);
• Fuzzy set probability of failure (repair) for nine years of operation
i=0.204099; j=0.284616; k=0.372416;
B=TN(i,j,k).</p>
      <p>
        Fig. 1 and Fig. 2 illustrate the appearance of these fuzzy sets.
To assess the risks of operating the production facilities of the enterprise, the authors
compare these two fuzzy sets by performing an arithmetic subtraction operation for the
fuzzy arithmetic. If the result is positive, then the probability of operation is more
significant than the probability of failure. However, if the result is negative, then the
probability of failure is more significant than the probability of operation. If the
subtraction yields zero, then these probabilities are equivalent to one another.
Therefore, zero is an equivalence criterion that characterizes the transition from a
negative outcome to a positive one. Furthermore, the authors conduct a computational
experiment comparing fuzzy sets through subtraction. In other words, the authors
determine the excess of the probability of operation over the probability of failure. Fig.
3 demonstrates this aspect [
        <xref ref-type="bibr" rid="ref2">2</xref>
        ]. The authors implement the mentioned procedure using
the following calculation sequence:
The authors acquire a set (a triangular number) with the [-0.215888, 0.045201,
0.289875] parameters based on the subtraction results. As one can observe, this set
includes negative, positive, and zero values. The authors develop the “Assessing the
risk of operating the production facilities” methodology to overcome such uncertainty.
The authors continue further discourse implementing the http://fuzzycalc.xyz/risk
hardware and software complex.
3
      </p>
    </sec>
    <sec id="sec-3">
      <title>Results and Discussion</title>
      <p>The authors present the data of calculating the exceeding of the probability of
operation over the probability of failure [-0.215888, 0.045201, and 0.289875] as a
figure and denote the figures ABC and AEF (Fig. 4).</p>
      <p>The risk assessment is made concerning the relationship of the areas of the figures.
The position of the zero criterion determines the area of the AEF figure. If the zero
criterion lies on point A or is located to the left (i.e., point A is a positive number
deviating from zero), then the area of the AEF figure is zero. If the zero criterion is on
point C or is located to the right (i.e., point C is a negative number), then the area of
figure AEF is equal to the area of figure ABC. The amount of risk is determined by the
relationship of the areas of figures according to the following formula:
R = SAEF /SABC,
where:</p>
      <p>R is the magnitude of the risk of exceeding the probability of failure over the
probability of operation,</p>
      <p>S AEF is the area that characterizes the subset of the excess of the probability of
failure over the probability of operation,</p>
      <p>S ABC is the area that characterizes the set of exceeding the probability of
operation over the probability of failure.</p>
      <p>If the area of the AEF figure takes the zero value (when the probability of
operation is guaranteed to exceed the probability of failure), then for any area of the
ABC figure, the risk value takes the zero value (there is no operational risk).</p>
      <p>
        If the area of the AEF figure takes the value of the area of the ABC figure (when
the probability of operation is guaranteed to be less than the probability of failure),
then for any area of the ABC figure, the risk value takes the value 1 (the operational
risk is absolute) [
        <xref ref-type="bibr" rid="ref1">1</xref>
        ].
      </p>
      <p>Incidentally, the authors distribute the risk of exceeding the probability of the “In
operation” over the “Undergoing maintenance” probability sets in the interval from
zero to one.</p>
      <p>In the current example, the result of calculating the risk will have the following
form (Fig. 5).</p>
      <p>The authors calculate the risk value of exceeding the probability of the “In operation”
over the “Undergoing maintenance” probability sets on the interval of operation of
vehicles (automobiles) from 0 to 10 years. The authors observe the beginning of an
increase in the risk value from the eighth year of operation, which is caused by natural
wear processes and an increase in failure (Fig. 6).</p>
    </sec>
    <sec id="sec-4">
      <title>Conclusions</title>
      <p>The calculated linear risk assessment of exceeding the probability of failure over the
probability of operation is not acceptable in practice since, in various spheres of the
economy, the values of probability, operation, and failure may have different
significance for the decision-maker. Therefore, the risk of failure of a tractor, a car, or
an airplane carries various social and economic consequences. Therefore, the
requirements for the reliability of the non-stop operation of vehicles may vary. To
provide an assessment of the risks of the vehicle operation, the authors propose to
introduce a weighing formula of the following form into the methodology,
f(E,R) = E – k*R,
2
where
f is the function (mathematical rule);
E is the set of probabilities of a positive outcome (operation, technical readiness;
R is the set of probabilities of a negative outcome (failure, the occurrence of
technical impacts;
k is the coefficient of the undesirability of a negative outcome.</p>
      <p>According to the analysis results, the authors have determined that there is an
excess of the probability of failure over the probability of operation in the ninth year
of operation. The probability of failure fuzzy set (repairs for nine years of operation
i=0.204099; j=0.284616; k=0.372416, and the coefficient of the undesirability of a
negative outcome is represented by a singleton (a set consisting of one number) a=2;
b=2; c=2; a fuzzy set consisting of one value (Fig. 7).</p>
      <p>Fig. 8 presents a graphical representation of the performed calculation.
Fig 8. The result of calculating the risk of failure considering the coefficient of the
undesirability of a negative outcome. Source: Compiled by the authors.</p>
      <p>Fig. 8 demonstrates that an undesirable outcome is guaranteed, and production
facilities require replacement (purchase of new vehicles).</p>
      <p>The authors carry out similar calculations on the interval from 0 to 10 years of
operation. The result of calculating the risk assessment in the context of the weighing
formula of the decision-maker is presented in figures (Fig. 9).</p>
      <p>1
0,9
0,8
0,7
0,6
0,5
0,4
0,3
0,2
0,1
0</p>
      <p>In conclusion, one can carry out long-term planning of the operation of fixed assets in
conditions of multiple operation options and assess the risks of transient processes of
reliability and loss of operational qualities of machines, which determines the order
and plan of replacement of vehicles.</p>
    </sec>
  </body>
  <back>
    <ref-list>
      <ref id="ref1">
        <mixed-citation>
          1.
          <string-name>
            <surname>Sadykova</surname>
            <given-names>ZF</given-names>
          </string-name>
          et al (
          <year>2019</year>
          <article-title>) Assessing the effectiveness of a marketing strategy in conditions of uncertainty</article-title>
          . In:
          <article-title>International scientific conference dedicated to the 175th anniversary of K.A</article-title>
          .
          <string-name>
            <surname>Timiryazev</surname>
          </string-name>
          , Russian State Agrarian University - Moscow Timiryazev Agricultural Academy, Moscow, 3-
          <fpage>6</fpage>
          June 2019
        </mixed-citation>
      </ref>
      <ref id="ref2">
        <mixed-citation>
          2.
          <string-name>
            <surname>Sadykova</surname>
            <given-names>ZF</given-names>
          </string-name>
          et al (
          <year>2019</year>
          )
          <article-title>Financial management of an economic entity in conditions of uncertainty on the example of an operational lever</article-title>
          . In:
          <article-title>international scientific conference dedicated to the 175th anniversary of K.A</article-title>
          .
          <string-name>
            <surname>Timiryazev</surname>
          </string-name>
          , Russian State Agrarian University - Moscow Timiryazev Agricultural Academy, Moscow, 3-
          <fpage>6</fpage>
          June 2019
        </mixed-citation>
      </ref>
      <ref id="ref3">
        <mixed-citation>
          3.
          <string-name>
            <surname>Sadykova</surname>
            <given-names>ZF</given-names>
          </string-name>
          ,
          <string-name>
            <surname>Abaev</surname>
            <given-names>VA</given-names>
          </string-name>
          (
          <year>2019</year>
          )
          <article-title>Evaluation of an organization's investment strategy under uncertainty</article-title>
          .
          <source>Agricultural Risk Management</source>
          <volume>2</volume>
          (
          <issue>30</issue>
          ):
          <fpage>6</fpage>
          -
          <lpage>12</lpage>
        </mixed-citation>
      </ref>
    </ref-list>