<!DOCTYPE article PUBLIC "-//NLM//DTD JATS (Z39.96) Journal Archiving and Interchange DTD v1.0 20120330//EN" "JATS-archivearticle1.dtd">
<article xmlns:xlink="http://www.w3.org/1999/xlink">
  <front>
    <journal-meta />
    <article-meta>
      <title-group>
        <article-title>SMART Intelligence Models for Managing Innovation Projects</article-title>
      </title-group>
      <contrib-group>
        <contrib contrib-type="author">
          <string-name>Sergiy Bushuyev</string-name>
          <xref ref-type="aff" rid="aff0">0</xref>
        </contrib>
        <contrib contrib-type="author">
          <string-name>Natalia Bushuyeva</string-name>
        </contrib>
        <contrib contrib-type="author">
          <string-name>Victoria Bushuieva</string-name>
        </contrib>
        <contrib contrib-type="author">
          <string-name>Denis Bushuiev</string-name>
          <email>bushuievd@gmail.com</email>
        </contrib>
        <aff id="aff0">
          <label>0</label>
          <institution>Kyiv National University of Construction and Architecture</institution>
          ,
          <addr-line>Povitroflotsky Avenue, 31, 03680 Kyiv</addr-line>
          ,
          <country country="UA">Ukraine</country>
        </aff>
      </contrib-group>
      <abstract>
        <p>Existing SMART Intelligence Models for managing innovative projects and programs have been explored. The competency-based approach is considered the basis for building a SMART Intelligence Model for managing innovative projects and programs. Proposed five groups of Competencies SMART Intelligence Model for Managing Innovation Projects. The SMART intelligence model has five groups of interrelated competencies: emotional, social, cognitive, business and technical. Each group of competencies of the SMART Intelligence Model are defined. To assess the competence level of the project team, the Organization competencebased model IPMA Delta model was used. As an example of the application, the SMART Intelligence Model to the implementation of the double degree project of the Kyiv National University of Civil Engineering and Architecture and the Dortmund University of Applied Sciences within the framework of the implementation of European Union DAAD VIMACS and ERASMUS+ WORK4CE projects is presented.</p>
      </abstract>
      <kwd-group>
        <kwd>1 Innovation project</kwd>
        <kwd>Competencies</kwd>
        <kwd>SMART Intelligence model</kwd>
        <kwd>Emotional</kwd>
        <kwd>Social</kwd>
        <kwd>Cognitive</kwd>
        <kwd>Business</kwd>
        <kwd>Technical</kwd>
        <kwd>Managing projects</kwd>
      </kwd-group>
    </article-meta>
  </front>
  <body>
    <sec id="sec-1">
      <title>1. Introduction</title>
      <p>Intelligence today is generally understood as the ability to understand and adapt to the environment by
using inherited abilities and learned knowledge.</p>
      <p>
        The theory of multiple intelligences was developed in 1987 by Dr. Howard Gardner. This theory
suggests that the traditional notion of intelligence is far too limited. Dr. Gardner proposes eight different
bits of intelligence to account for a broader range of human potential. This intelligence are [
        <xref ref-type="bibr" rid="ref1">1</xref>
        ]:
2. Linguistic intelligence (“word smart”);
3. Logical-mathematical intelligence (“number/reasoning smart”);
4. Spatial intelligence (“picture smart”);
5. Bodily-Kinesthetic intelligence (“body smart”);
6. Musical intelligence (“music smart”);
7. Interpersonal intelligence (“people smart”);
8. Intrapersonal intelligence (“self-smart”);
9. Naturalist intelligence (“nature smart”).
      </p>
      <p>It was the beginning SMARTification of intelligence systems.</p>
      <p>
        The dynamic development of standards and methodologies in project management is associated with
the shortage life cycles of projects and project products. As the result, projects management practice
used hybrid approaches and methodologies, elements of entropy and genetic models of projects. Ideas
and concepts for creating projects based on analogues. The updating of knowledge and concepts of
project management in world practice confirms the significant interest in this field of activity [
        <xref ref-type="bibr" rid="ref2">2</xref>
        ].
      </p>
      <p>
        The rapid development of project management in world practice is associated with its impact on the
sustainable dynamic development of countries in the context of the formation of an electronic economy.
The conscious synergy of project management as a tool for the development and promotion of
SMARTification, E-business, E-commerce, E-economy, E-employment based on open Internet
technologies determines the main trends in the development of information technology, the
development of new methods and tools for project management [
        <xref ref-type="bibr" rid="ref3">3</xref>
        ].
      </p>
      <p>Under these conditions, the key trends in the development of project management are associated
with the following areas:
- Globalization of knowledge and project management technologies;
- Business practice;
- Information technologies;
- Social importance;
- Development of human resources involved in projects;
- General development of science and technology;
- Development of SMART markets and market mechanisms.</p>
      <p>
        As intelligence mechanisms, we are understood as modern concepts – SMART information
modeling, integrated project implementation and big data, with their methods, tools and modern
hardware and software [
        <xref ref-type="bibr" rid="ref4">4</xref>
        ]. Integrated use of intelligence mechanisms allows to obtain, process, store
and use of the knowledge generated in the project, as well as able to increase the effectiveness of the
project, achieve planned goals and increase the likelihood of its successful completion [
        <xref ref-type="bibr" rid="ref5">5</xref>
        ].
      </p>
    </sec>
    <sec id="sec-2">
      <title>2. Analysis of recent research and publication</title>
      <p>Cognitive models are used with two different objectives:
− a cognitive model aims to formally describe the cognitive processes underlying the observed
behavior in a specific task and explain specific experimental effects observed within this task;
− the parameters of a cognitive model estimated from the observed behavior in a task are used as
measures for differences across individuals or experimental conditions.</p>
      <p>
        One of the directions of cognitive analysis is explanatory cognitive models that provide an effective
tool for comparing prediction theories, models of the future, and experimental assessments of the
adequacy of knowledge. The complexity of cognitive analysis models and the lack of methods for
evaluating the results of knowledge accumulation makes it difficult to use them in research. The results
of explanatory cognitive models can provide a theoretical basis for deciding the pros or cons against a
particular model of cognitive analysis. Measures of quantitative analysis determine how project
managers or their operating conditions differ concerning a particular process of the cognitive model. In
the field of cognitive modeling, models define the cognitive process. Cognitive models of the second
direction are called models of cognitive evaluation. Any cognitive model can be both an explanatory
and an evaluative cognitive model, depending on the circumstances of its use. The cognitive models
that are used to explain the observed behavior of systems within specific projects differ from the
cognitive models that are used to quantify differences in their parameters [
        <xref ref-type="bibr" rid="ref6">6</xref>
        ].
      </p>
      <p>One of the biggest challenges in intelligence research is the identification of the cognitive processes
underlying cognitive competencies and the competencies of assessing the parameters of the knowledge
acquisition process.</p>
      <p>
        Modern theories of general intelligence suggest that intelligent behavior is the result of individual
differences in the various independent cognitive competencies of the project manager and that there is
a hierarchical structure of cognitive competencies with a common set of competencies that determine
individual differences in the cognitive abilities of project managers [
        <xref ref-type="bibr" rid="ref7">7</xref>
        ].
      </p>
      <p>According to the triarchic theory, intelligence has three groups of competencies: analytical, creative,
and practical.</p>
      <p>Analytical intelligence is called basic intelligence and refers to the intelligence that is applied to
analyze or evaluate problems and find solutions.</p>
      <p>Creative intelligence is defined as the ability to go beyond standard areas of knowledge to create
innovative ideas. This type of intelligence is defined by imagination, innovation and problem-solving.</p>
      <p>
        Practical intelligence is seen as the competencies that project managers use to solve the problems
they face in everyday life. In this case, the project manager finds the best match between the
requirements of the project and the requirements of the environment. Adaptation to the requirements of
the environment includes the use of knowledge gained from experience to purposefully change
following the state of the environment (adaptive competencies), change the environment by the goals
of the project (formative competencies) and search for a new environment for development
(competencies of selection of alternatives) [
        <xref ref-type="bibr" rid="ref8 ref9">8, 9</xref>
        ].
      </p>
      <p>Emotional Intelligence is the ability to keep under control stakeholders' emotions, discriminate
between different emotions, and use emotional information to guide thinking and behavior.</p>
      <p>Let's look at intelligence assessment. Intelligence assessment also reveals strong construct validity,
meaning that they are measuring intelligence rather than something else.</p>
      <p>There are issues with intelligence tests beyond looking at them in a vacuum. These tests were created
by western psychologists who created such tools to measure euro-centric values.</p>
      <p>Stereotype threat is a phenomenon in which people feel at risk of conforming to stereotypes about
their social group. Negative stereotypes can also create anxiety that results in lower scores.</p>
      <p>Stereotype threat is closely related to the concept of a self-fulfilling prophecy in which an
individual’s expectations about another person can result in the other person acting in ways that conform
to that very expectation.</p>
      <p>To convey an idea of the benefits of the application of cognitive modeling in intelligence research,
we will discuss three examples of cognitive models in the following sections. Let selected different
models describing cognitive processes of particular interest to intelligence research, such as decision
making, working memory and cognitive control. This is demonstrating how they may be used to
quantify project managers' differences in their respective cognitive processes. The three models
described below differ in their breadth of application and their former use as assessment or measurement
models.</p>
      <p>
        Projects are born in a certain environment and very often in the same agony as all living things. The
environment of the project "feeds" it with various ideas, approaches, tools, resources (including money)
and means of solving the problems of the project - it forms the environment of the project. As for a
person, clothing, housing, habitat and communication, etc. form an environment [
        <xref ref-type="bibr" rid="ref10 ref11 ref12 ref13">10,11, 12, 13</xref>
        ].
      </p>
      <p>The specifics of managing innovation projects and the problems of dynamic leadership lies in the
particular innovation of the tasks that project managers constantly have to solve, and the low level of
performance culture among project participants: customer, investor, financing organizations, project
managers, project performers, surrounding organization, control services (technical, financial, tax, etc.).</p>
      <p>In this case, project management is considered a universal language of communication between
project stakeholders. From the unambiguous and professionally correct understanding of the language
of project management, the result of the implementation of an innovation project largely depends on
the selected criteria (time, cost, quality, etc.).</p>
      <p>
        The main problems of managing innovation projects are formed around the following factors [
        <xref ref-type="bibr" rid="ref14 ref15">14,
15</xref>
        ]:
− customer requirements for the project and increasing their competence. At the same time, the
principle “appetite comes with eating” works;
− the innovation of the resulting products or projects. This innovation is considered an objective
property of the system, which requires the decentralization of management functions and the use of
hierarchy as a means of dealing with the innovation of management tasks. Typically, in such a
management scheme, a significant number of conflicts arise when decisions are made by managers of
the same level. Every manager tries to "pull the blanket over himself";
− relationship and mutual influence with the external environment of projects (economic, political,
environmental, social, cultural environment). Such connections quite often negatively affect the
progress of the project.
− degree of uncertainty and risk. In innovation projects, the degree of risk is always much higher, as
it is balanced by the effect of project implementation. Here the folk wisdom “you have to pay for
everything” works [
        <xref ref-type="bibr" rid="ref16">16</xref>
        ];
− organizational restructuring. Such restructuring is inevitable since the project management system
must reflect changes in the control object, which consist of changes in the structure of the
reorganization. This is an objective property of any innovation project, and the absence of changes in
an innovation project during its implementation is "not the rule, but the exception" [
        <xref ref-type="bibr" rid="ref17">17</xref>
        ];
− frequency of technology change. This property is determined by the significant duration of the
project, on the one hand, and the desire of the customer to obtain a result that corresponds to the latest
technological advances, on the other. The inevitability of replacing technical and technological
solutions makes it possible to meet the customer’s expectations of the type “I want this, but I don’t
know what” [
        <xref ref-type="bibr" rid="ref18">18</xref>
        ];
− planning and pricing errors. These errors are an essential attribute of any innovation project. In this
case, project managers are always under the "crossfire" of the designers, the customer and the
contractors. This triangle is the source of most of the problems that arise in the process of project
monitoring.
3. Competencies intelligent model for managing SMART innovation projects
In real practice project managers apply a conceptual model with five domains of competencies:
1. Emotional Intelligence (EI) competencies of Result Orientation, Initiative, Flexibility, and
Self-Confidence;
      </p>
      <p>2. Social Intelligence (SI) competencies of Empathy, Influence, Networking, and Distributed
Team Leadership. They also showed significantly more cognitive competencies in Systems Thinking
and Pattern Recognition;</p>
      <p>
        3. Cognitive Intelligence (CI) competencies being key to effectiveness in Acquisitions of
knowledge, Creativity and Innovation, Artificial Intelligence and Modeling in an organization [
        <xref ref-type="bibr" rid="ref19">19</xref>
        ];
4. Business intelligence (BI) competencies like Strategy, Culture and Values, Planning and
Control, Opportunity and Risk Management [
        <xref ref-type="bibr" rid="ref20">20</xref>
        ];
      </p>
      <p>
        5. Technical intelligence (TI) competencies: vision of the product and result, technical, technological
and organizational solutions in the implementation of the project, work in conditions of uncertainty and
innovation, clear definition of boundaries and work with the context [
        <xref ref-type="bibr" rid="ref21">21</xref>
        ].
      </p>
      <p>The SMART Intelligence model of Competencies for managing Innovation Projects is shown in
Fig. 1.</p>
      <sec id="sec-2-1">
        <title>Technical intellegence</title>
      </sec>
      <sec id="sec-2-2">
        <title>Buisness intelligence</title>
        <p>
          The approach to achieving a particular goal depends on the situation. The guiding intelligence
principles are the elements of the prospective competency as well as the technology solution used to
build the solution. This choice starts with what the best practice is already available and then what needs
to be built on top of that. This will be the technological and functional architecture [
          <xref ref-type="bibr" rid="ref22">22, 23</xref>
          ].
        </p>
        <p>Project managers face complexity and uncertainty, which means that every situation requires a
different approach. Therefore, the various Agile approaches are commonly referred to as
"Frameworks", they are the starting point from which the approach must gradually evolve. When you
start a project, you study the lessons learned, choose a certain structure, and realize that this choice is
an assumption that has not yet been proven to be correct.</p>
        <p>Work empirically when testing this assumption or hypothesis through an experiment. Such a
hypothesis must be formulated in such a way that it can be falsified. We often adjust in small steps and
sometimes you need to radically change the way of working. A clear, inspiring and supportive vision
for the product or result to be delivered gives meaning to the higher goals the organization wants to
achieve. It provides direction and sets boundaries. When there are many uncertainties and a changing
context, it is often impossible to specify goals and requirements for the result. Therefore, the command
continues to communicate with the user. The focus and boundaries of the product vision allow us to
constantly improve it with the help of sub-goals. We then work in a plan-do-check-act mode until we
achieve results [24].</p>
        <p>Consider the mechanisms of intellectual support for models based on their Smartification [25, 26].</p>
        <p>Emotional intelligence is supported by the SMARTification mechanism based on flexibility,
selfmanagement, emotional contagion, and result orientation competencies.</p>
        <p>SMARTification of the socio-intelligence mechanism is determined based on the active use of social
networks, distributed teams, and empathy.</p>
        <p>SMARTification of cognitive intelligence is based on knowledge acquisition, creativity and open
innovation, artificial intelligence and modeling in an organization.</p>
        <p>SMARTification Business intelligence mechanisms are based on competencies strategy, culture and
values, planning and control, opportunity and risk management.</p>
        <p>SMARTification of Technical intelligence mechanisms based on the competencies vision of the
product, output and outcome, technical, technological and organizational solutions in the project
implementation, action in conditions of uncertainty and open innovation, clear definition of scope and
project context.</p>
        <p>For the assessment of competence for the proposed model Key Intelligence Indicators have been
developed for each competency [27].</p>
        <p>In the case of the proposed intelligence competence model study according to the application of the
proposed conceptual model. It had been developed by an assessment Double degree Master's program
in preparation for Project Managers at Kyiv National University of Construction and Architecture. At
the end of this program group of 20 students had been assessed according to five domain conceptual
models of innovation competencies.</p>
        <p>
          The project team's competence was assessed using the IPMA OCB and IPMA ICB 4 models [
          <xref ref-type="bibr" rid="ref1 ref2">1,2</xref>
          ].
        </p>
        <sec id="sec-2-2-1">
          <title>Competencies by domain</title>
        </sec>
        <sec id="sec-2-2-2">
          <title>Acquisitions of knowledge Creativity and Innovation Artificial Intelligence Modeling by vision</title>
          <p>Cognitive Intelligence</p>
          <p>Social Intelligence
9
8
8
9</p>
          <p>Business intelligence</p>
          <p>Technical intelligence
The vision of the product and result, 8 7
Technical, technological and organizational solutions in
the implementation of the project, 7 7
Work in conditions of uncertainty and innovation, 8 7
Clear definition of boundaries and work with the context 7 7
As the result of analyses, there are two competencies, where the assessment level is low than
Benchmark.</p>
          <p>Culture and Values</p>
          <p>Strategy
Self-Confidence</p>
          <p>Opportunity and Risk</p>
          <p>Acquisitions of
knowledge
10</p>
          <p>Creativity and</p>
          <p>Innovation
Planning and Control</p>
          <p>Artificial Intelligence
8
6
4
2
0
Flexibility</p>
          <p>Networking
Initiative</p>
          <p>Team Leadership</p>
          <p>As the result of analyses, there is competence, where the assessment level is lower than Benchmark.
It is Team Leadership competence. To be successful project team need to improve this competence.</p>
          <p>The project manager decided on the initial step to organize 3 pieces of training for the project team.
The first training was devoted to the development of the initiative of the innovation project team. The
8
8
7
8
8
8
7
8
second concerned leadership. The third training improves Artificial Intelligence competence.
result, the assessment of the team's competence has changed significantly and is given in Table 2.</p>
          <p>Technical intelligence
The vision of the product and result,
Technical, technological and organizational solutions in
the implementation of the project,
Work in conditions of uncertainty and innovation,</p>
          <p>Clear definition of boundaries and work with the context</p>
          <p>The results of the evaluation of Innovation competencies compared to the benchmark are shown in
Figure 3.
7
8
8
7
7
8
8
9
7
7
7
8
8
7
7
8
8
7
7
8
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
8
6
4
2
0
Strategy
Self-Confidence</p>
          <p>Flexibility</p>
          <p>Initiative
Assessment level</p>
          <p>Benchmark</p>
          <p>Acquisitions of knowledge</p>
          <p>Clear definition of… 10 Creativity and Innovation
Work in conditions of…</p>
          <p>As the result of the training of the project team, the assessments of innovation competencies in
almost all cases exceeded the level of the benchmark. This indicates the readiness of the project team
for its successful implementation.</p>
        </sec>
      </sec>
    </sec>
    <sec id="sec-3">
      <title>4. Intelligence didactic and competencies model</title>
      <p>Three structural parts of the intelligence didactic model are:
− the teaching information includes module and type, topic, theme, corresponding module,
corresponding subjects, and health objectives;
− the contents refer to the structure of the teaching example which includes different steps and
tasks;
− the steps describe the main phases of the teaching example. Moreover, these steps are
divided into different tasks which correspond to the objectives of the teaching example;
− the warm-up and cool-down phases are only described when they are part of the main
subject;
− additional information includes the references and offers links and other information.</p>
      <p>Didactic concept based on the set of competencies. The structural elements of learning and outcomes
are teaching, understanding, generalization and use. The logic of the learning process, therefore, is to
move from the presentation of the material through explanation to understanding and generalization. It
is easy to see in this scheme most of the lessons today.</p>
      <p>Let's discuss the application of the didactic concept.</p>
      <p>Contemporary concepts applications are including:
− programming of the educational process;
− problem learning;
− developmental training;
− cognitive technology;
− cooperation pedagogy;
− cybernetic learning concept.</p>
      <p>
        Let's look at the set of competencies for the master's degree Education Program "Cognitive
technology" which was implemented at Kyiv National University of Construction and Architecture.
There are three groups of competencies. Assessment of the level of competencies for two groups done
by IPMA OCB model [
        <xref ref-type="bibr" rid="ref2">2</xref>
        ] in the group of 15 students in 2021.
      </p>
      <p>The first group of SMART competencies:
− degree of clarity: selection of information, its understanding and in-depth study;
− degree of association: the connection of new information with existing knowledge;
− degree of the system: formulation of concepts, conclusions, laws;
− degree of the method: understanding the theory, using it in new conditions, phenomena and
situations.</p>
      <p>Assessment of competencies by SMART Intelligence model for the first group of competencies is
shown in fig 4.</p>
      <p>Level of competencies</p>
      <p>Degree of the method:
understanding the theory,
using it in new conditions,
phenomena, situations.</p>
      <p>Degree of clarity:
selection of information,
its understanding and
indepth study;
10
8
6
4
2
0</p>
      <p>Degree of association: the</p>
      <p>connection of new
information with existing</p>
      <p>knowledge;
Degree of the system:
formulation of concepts,</p>
      <p>conclusions, laws;</p>
      <sec id="sec-3-1">
        <title>Second group SMART competencies:</title>
        <p>− ability to abstract thinking, analysis and synthesis;
− ability to communicate in a foreign language;
− ability to conduct research at the appropriate level;
− ability to learn and master modern knowledge.</p>
      </sec>
      <sec id="sec-3-2">
        <title>Third group SMART competencies:</title>
        <p>− ability to search, process and analyze information from various sources;
− ability to generate new ideas (creativity);
− ability to identify, pose and solve problems;
− ability to make informed decisions.</p>
        <p>Assessment of competencies by SMART Intelligence model for the third group of competencies is
shown in fig 5.</p>
        <p>Ability to make informed
decisions</p>
        <p>Ability to search, process
and analyze information
from various sources
10
8
6
4
2
0
Ability to identify, pose
and solve problems</p>
        <p>Ability to generate new
ideas (creativity)</p>
        <p>Program outcomes consist of the following educational results:
− to know and be able to apply in practice the methods of system analysis, methods of
mathematical and information modeling for the construction and study of models of objects and
processes of informatization;
− know the methods of forecasting the dynamics of processes of different nature, be able to
develop forecasting functions;
− know and be able to apply risk measures, assess them and use them in the analysis of
multifactorial risks of accidents and catastrophes;
− to know and be able to apply methods of evolutionary modeling and genetic methods of
optimization, methods of inductive modeling and mathematical apparatus of fuzzy logic, neural
networks, game theory and distributed artificial intelligence, etc.</p>
      </sec>
    </sec>
    <sec id="sec-4">
      <title>5. Conclusion</title>
      <p>The proposed SMART Intelligence Competencies model for managing Innovation Projects includes
five domains of competencies. These domains are the cognitive, emotional, social, business and
technical competencies. Each domain has a set of competencies.</p>
      <p>SMARTification process gives the possibility to develop Intelligence mechanisms for the SMART
model.</p>
      <p>To support of the success an innovation project, a benchmark level of competencies assessment is
used. It allows to identify the low level of some competencies and, at the stage of project initiation, plan
the necessary corrective actions to develop insufficient project competencies.</p>
      <p>The example of the program for the preparation of masters with double diplomas confirmed the
effectiveness of the proposed model.</p>
      <p>The given step by step process model allows to successfully carry out innovation projects.
The following issues should be highlighted as areas for future research:
− SMARTification of competence domain by intelligence mechanisms for managing
innovation projects;
− SMATR mechanism of managing the uncertainty in the value creation process of innovation
project;
−
creation of effective competence assessment models and tools for each domain of
competence.</p>
    </sec>
    <sec id="sec-5">
      <title>6. Acknowledgements</title>
      <p>The authors express their deep gratitude to the European Union ERASMUS + program for financial
and technical support of the WORK4CE project and the German Academy of Sciences for the provided
support for the VIMACS project</p>
    </sec>
    <sec id="sec-6">
      <title>7. References</title>
      <p>[23] Slivitsky А. Value migration. Маnn,Ivanov&amp; Ferber, (2006), 432 p.
[24] S. Bushuyev, D. Bushuiev, A. Zaprivoda, J. Babayev, Ç. Elmas, Emotional infection of
management infrastructure projects based on the agile transformation CEUR Workshop
Proceedings, (2020), #2565, pp. 1–12
[25] Agile Practice Guide: Paperback. USA, Project Management Institute, (2017), 210 p
[26] A Systems Approach to Planning, Scheduling, and Controlling (10th ed.). USA, New Jersey:</p>
      <p>Wiley, (2015), 1120 p.
[27] Ruhl, C. Intelligence: definition, theories and testing. Simply Psychology. (2020).
www.simplypsychology.org/intelligence.html</p>
    </sec>
  </body>
  <back>
    <ref-list>
      <ref id="ref1">
        <mixed-citation>
          [1]
          <string-name>
            <surname>Gardner</surname>
            ,
            <given-names>H.</given-names>
          </string-name>
          <article-title>The theory of multiple intelligence</article-title>
          .
          <source>Annals Of Dyslexia</source>
          , (
          <year>1987</year>
          ) v.
          <volume>37</volume>
          , pp.
          <fpage>19</fpage>
          -
          <lpage>35</lpage>
          .
        </mixed-citation>
      </ref>
      <ref id="ref2">
        <mixed-citation>
          [2]
          <string-name>
            <given-names>Individual</given-names>
            <surname>Competence</surname>
          </string-name>
          <article-title>Baseline for Project, Programme &amp; Portfolio Management, Version 4</article-title>
          . International Project Management Association. (
          <year>2015</year>
          ),
          <year>415p</year>
          .
        </mixed-citation>
      </ref>
      <ref id="ref3">
        <mixed-citation>
          [3]
          <string-name>
            <given-names>IPMA</given-names>
            <surname>Organisational Competence</surname>
          </string-name>
          <article-title>Baseline (IPMA OCB)</article-title>
          .
          <source>IPMA</source>
          , (
          <year>2013</year>
          ),
          <year>67p</year>
          .
        </mixed-citation>
      </ref>
      <ref id="ref4">
        <mixed-citation>
          <source>[4] The Cambridge Handbook of Intelligence</source>
          , Cambridge University Press, (
          <year>2011</year>
          ), pp.
          <fpage>58</fpage>
          -
          <lpage>82</lpage>
          DOI: https://doi.org/10.1017/CBO9780511977244.005
        </mixed-citation>
      </ref>
      <ref id="ref5">
        <mixed-citation>
          [5]
          <string-name>
            <given-names>Intelligence</given-names>
            <surname>Models</surname>
          </string-name>
          and
          <string-name>
            <surname>Best Practices. IALEIA</surname>
          </string-name>
          ,(
          <year>1999</year>
          ), 58 p.
        </mixed-citation>
      </ref>
      <ref id="ref6">
        <mixed-citation>
          [6]
          <string-name>
            <surname>Salovey</surname>
            ,
            <given-names>P.</given-names>
          </string-name>
          , &amp;
          <string-name>
            <surname>Mayer</surname>
            ,
            <given-names>J. D.</given-names>
          </string-name>
          <article-title>Emotional intelligence</article-title>
          . Imagination, Cognition and Personality, (
          <year>1990</year>
          ).
          <volume>9</volume>
          (
          <issue>3</issue>
          ),
          <fpage>185</fpage>
          -
          <lpage>211</lpage>
          .
        </mixed-citation>
      </ref>
      <ref id="ref7">
        <mixed-citation>
          [7]
          <string-name>
            <surname>Sternberg</surname>
            ,
            <given-names>R. J.</given-names>
          </string-name>
          <article-title>Contemporary theories of intelligence</article-title>
          . Handbook of psychology, (
          <year>2003</year>
          ). pp.
          <fpage>21</fpage>
          -
          <lpage>45</lpage>
          .
        </mixed-citation>
      </ref>
      <ref id="ref8">
        <mixed-citation>
          <article-title>[8] Guidebook of Program &amp; Project Management for Enterprise Innovation, Third Edition P2M, Project Management Association of Japan (PMAJ), (</article-title>
          <year>2017</year>
          ), 427 p.
        </mixed-citation>
      </ref>
      <ref id="ref9">
        <mixed-citation>
          <article-title>[9] A Guide to the Project Management of the Knowledge (PMBOK® Guide)</article-title>
          .
          <source>Seventh Edition</source>
          .
          <source>PMI</source>
          (
          <year>2021</year>
          ), 370 p.
        </mixed-citation>
      </ref>
      <ref id="ref10">
        <mixed-citation>
          <source>[10] ISO 21502. Guidance on project management. Project Committee ISO / PC 236</source>
          , (
          <year>2020</year>
          ),
          <year>52p</year>
          .
        </mixed-citation>
      </ref>
      <ref id="ref11">
        <mixed-citation>
          <source>[11] ISO 21503</source>
          .
          <article-title>Project, programme and portfolio management - Guidance on programme management</article-title>
          .
          <source>ISO / PC 236</source>
          , (
          <year>2017</year>
          ),
          <fpage>52p</fpage>
        </mixed-citation>
      </ref>
      <ref id="ref12">
        <mixed-citation>
          <source>[12] ISO 21504. Project, programme and portfolio management - Guidance on portfolio management ISO / PC 236</source>
          , (
          <year>2015</year>
          ),
          <fpage>24p</fpage>
        </mixed-citation>
      </ref>
      <ref id="ref13">
        <mixed-citation>
          <source>[13] ISO 21505. Project, programme and portfolio management - Guidance on governance ISO / PC 236</source>
          , (
          <year>2017</year>
          ),
          <fpage>11p</fpage>
        </mixed-citation>
      </ref>
      <ref id="ref14">
        <mixed-citation>
          [14]
          <string-name>
            <given-names>V.</given-names>
            <surname>Obradović</surname>
          </string-name>
          ,
          <string-name>
            <given-names>M.</given-names>
            <surname>Todorović</surname>
          </string-name>
          ,
          <string-name>
            <given-names>S.</given-names>
            <surname>Bushuyev</surname>
          </string-name>
          .
          <source>Sustainability and Agility in Project Management: Contradictory or Complementary? IEEE 13th International Scientific and Technical Conference on Computer Sciences and Information Technologies</source>
          ,
          <string-name>
            <surname>CSIT</surname>
          </string-name>
          <year>2018</year>
          , (
          <year>2018</year>
          )
        </mixed-citation>
      </ref>
      <ref id="ref15">
        <mixed-citation>
          [15]
          <string-name>
            <given-names>R. H.</given-names>
            <surname>Pherson</surname>
          </string-name>
          ,
          <string-name>
            <given-names>R. J.</given-names>
            <surname>Heuer</surname>
          </string-name>
          .
          <article-title>Structured Analytic Techniques for Intelligence Analysis</article-title>
          .
          <source>SAGE Publications Inc</source>
          , (
          <year>2020</year>
          ),
          <year>384p</year>
          .
        </mixed-citation>
      </ref>
      <ref id="ref16">
        <mixed-citation>
          [16]
          <string-name>
            <surname>Jae-Yoon</surname>
            ,
            <given-names>J.</given-names>
          </string-name>
          ,
          <string-name>
            <surname>Chang-Ho</surname>
            ,
            <given-names>C.</given-names>
          </string-name>
          ,
          <string-name>
            <surname>Jorge</surname>
          </string-name>
          .
          <article-title>An entropy-based uncertainty measure of process models</article-title>
          .
          <source>Information Processing Letters</source>
          <volume>111</volume>
          (
          <issue>3</issue>
          ), (
          <year>2011</year>
          ),
          <fpage>135</fpage>
          -
          <lpage>141</lpage>
          ,
        </mixed-citation>
      </ref>
      <ref id="ref17">
        <mixed-citation>
          [17]
          <string-name>
            <given-names>C.</given-names>
            <surname>Belack</surname>
          </string-name>
          ,
          <string-name>
            <given-names>D. Di</given-names>
            <surname>Filippo</surname>
          </string-name>
          ,
          <string-name>
            <surname>I.</surname>
          </string-name>
          <article-title>Di Filippo Cognitive Readiness in Project Teams. Reducing Project Innovationity and Increasing Success in Project Management</article-title>
          . New York, NY: Routledge/Productivity Press, (
          <year>2019</year>
          ), 252 p.
        </mixed-citation>
      </ref>
      <ref id="ref18">
        <mixed-citation>
          [18]
          <string-name>
            <given-names>N.</given-names>
            <surname>Drouin</surname>
          </string-name>
          ,
          <string-name>
            <given-names>R.</given-names>
            <surname>Müller</surname>
          </string-name>
          ,
          <string-name>
            <given-names>S.</given-names>
            <surname>Sankaran</surname>
          </string-name>
          ,
          <string-name>
            <given-names>A.-L.</given-names>
            <surname>Vaagaasar</surname>
          </string-name>
          .
          <article-title>Balancing leadership in projects: Role of the socio-cognitive space</article-title>
          .
          <source>Project Leadership and Society. № 2</source>
          . (
          <year>2021</year>
          ),
          <volume>12</volume>
          р.
        </mixed-citation>
      </ref>
      <ref id="ref19">
        <mixed-citation>
          [19]
          <string-name>
            <given-names>S.</given-names>
            <surname>Bushuyev</surname>
          </string-name>
          ,
          <string-name>
            <given-names>A.</given-names>
            <surname>Murzabekova</surname>
          </string-name>
          ,
          <string-name>
            <given-names>S.</given-names>
            <surname>Murzabekova</surname>
          </string-name>
          ,
          <string-name>
            <given-names>M.</given-names>
            <surname>Khusainova</surname>
          </string-name>
          .
          <source>Develop innovation competence of project managers based on entrepreneurship energy Proceedings of the 12th International Scientific and Technical Conference on Computer Sciences and Information Technologies</source>
          , (
          <year>2017</year>
          ).
        </mixed-citation>
      </ref>
      <ref id="ref20">
        <mixed-citation>
          <source>[20] The Availability of Information on the National Intelligence Mode. NCIS</source>
          , (
          <year>2000</year>
          ),
          <year>42p</year>
          .
        </mixed-citation>
      </ref>
      <ref id="ref21">
        <mixed-citation>
          [21]
          <article-title>Global alliance for project performance standards</article-title>
          . (
          <year>2009</year>
          ), http://www.globalpmstandards.org/
        </mixed-citation>
      </ref>
      <ref id="ref22">
        <mixed-citation>
          [22]
          <string-name>
            <surname>Forsberg</surname>
            ,
            <given-names>K.</given-names>
          </string-name>
          ,
          <string-name>
            <surname>Mooz</surname>
            ,
            <given-names>H.</given-names>
          </string-name>
          ,
          <string-name>
            <surname>Cotterman</surname>
            ,
            <given-names>H.</given-names>
          </string-name>
          <article-title>Visualizing Project Management, 3rd edition</article-title>
          , John Wiley and Sons, New York, NY, (
          <year>2005</year>
          ).
          <year>360p</year>
          .
        </mixed-citation>
      </ref>
    </ref-list>
  </back>
</article>