        <article-title>Management for IT/IS Projects</article-title>
      </title-group>
      <contrib-group>
        <contrib contrib-type="author">
          <string-name>Bakhrom Shamuratov</string-name>
          <xref ref-type="aff" rid="aff0">0</xref>
        </contrib>
        <contrib contrib-type="author">
          <string-name>Mohamed A. Hamada</string-name>
          <email>m.hamada@iitu.edu.kz</email>
          <xref ref-type="aff" rid="aff0">0</xref>
        </contrib>
        <aff id="aff0">
          <label>0</label>
          <institution>International Information Technology University</institution>
          ,
          <addr-line>Manas St. 34/1, Almaty, 050000</addr-line>
          ,
          <country country="KZ">Kazakhstan</country>
        </aff>
      </contrib-group>
      <abstract>
        <p>In this research the essential meaning of Risks and Risk Management models are investigated toanalyze the main risk management models of software projects by developing an analytical comparison of modern Risk Management models to recommend the best model, which is more suitable for nowadays challenges and obstacles in the field of software projects development andagile project management.</p>
      </abstract>
      <kwd-group>
        <kwd>Keywords1</kwd>
        <kwd>Risk</kwd>
        <kwd>Risk Management models</kwd>
        <kwd>software projects</kwd>
        <kwd>ISO 31000</kwd>
      </kwd-group>
    </article-meta>
  </front>
  <body>
    <sec id="sec-1">
      <title>1. Introduction</title>
      <p>•
•</p>
      <sec id="sec-1-1">
        <title>Identify risks at any stage of projects; predict, compare, and analyze risks.</title>
      </sec>
      <sec id="sec-1-2">
        <title>Create the needed project strategy to mitigate or eliminate identified risks.</title>
      </sec>
      <sec id="sec-1-3">
        <title>Implement previous developed strategy.</title>
        <p>Monitoring the behavior of applied Risk Management model.5.Monitor and control the project
deliverables.</p>
        <p>Risk Management consists of the following features:
formalizing the Risk Management system as a possibility;
the need of the company's management for forward-thinking, intuition, and situation foresight;
the ability to respond quickly and recognize ways to improve the functioning of the
organization, and minimize the possibility of an undesirable course of events.</p>
        <p>It is not news that complex Risk Management systems are widely used in advanced countries such
as the USA. Because owners of large organizations are already made sure that old Risk Management
methods do not correspond to the modern project requirements and not sure about the high success
rate of project completion [2].</p>
        <p>A clear division of authority and responsibility among all structure entities is implied by the
implementation of Risk Management. The appointment of personnel in charge of carrying out the
essential Risk Management procedures at all levels is one of top management's duties.</p>
        <p>The company's strategic aims and objectives should be supported by such decisions, and they should
not contravene the laws in effect. Additionally, it is crucial to properly distribute among the executors
Proceedings of the 7th International Conference on Digital Technologies in Education, Science and Industry (DTESI 2022), October 20–21,</p>
        <p>2022 Copyright for this paper by its authors.
the functions of risk identification and risk situation control.</p>
      </sec>
    </sec>
    <sec id="sec-2">
      <title>2. The aim and objectives of the research</title>
      <p>Aim: This research aims to demonstrate the importance of Risk Management in the organization,
compare the methods of Risk Management models and make a suggestion on the best risk management
model (identify the most effective method of Risk Management) for software projects.</p>
      <p>Tasks:
• To determine the existing methods of Risk Management;
• To analyze and compare determined methods of Risk Management;
• To identify which method of Risk Management is most effective for an organization.</p>
    </sec>
    <sec id="sec-3">
      <title>3. Research methods</title>
      <p>In this research, examples of Risk Management methods were considered using the example of
various types of scientific research on this topic, as well as by making a survey (interviewing employee
of Big 4 Companies that works in the Risk Management area). Methods of empirical research are used
as the main methods by using quantitative analysis.</p>
      <p>The process of Risk Management evaluation and the suggestion of the suitable model to construct
the Risk Management methodology was described according to the guidelines of PMBOK. It is also
worth noting that all the proposed models described in the article, according to the authors classification,
models have a primitive appearance, which still needs to be finalized. The authors also mentioned which
functions should be improved in this model, which played an important role in assessment process.</p>
      <p>The recommended risk management model for nowadays organizations was considering the
recommendations of the authors and the modern challenges and problems of Risk Management such as
system automation, minimum consumption and maximum efficiency.</p>
    </sec>
    <sec id="sec-4">
      <title>4. Related works (literature review)</title>
      <p>
        Alexsandro S.F., 2021 in his work represented a risk prediction model (software) called “Atropos”
for project management according to the project similarity by it in the context of history. The
proposedmodel consists of 6 main components (stages): (
        <xref ref-type="bibr" rid="ref2">1</xref>
        ) inserting data about the current project; (
        <xref ref-type="bibr" rid="ref3">2</xref>
        )
analyzing the likeness of the project with historical context; (
        <xref ref-type="bibr" rid="ref4">3</xref>
        ) storing the information about the
current project during the whole project management; (
        <xref ref-type="bibr" rid="ref5">4</xref>
        ) comparing each step of the current project
with captured projects from a historical database; (
        <xref ref-type="bibr" rid="ref1 ref6">5</xref>
        ) identification of possible recommendations based
on comparisonof the previous stage; (
        <xref ref-type="bibr" rid="ref7">6</xref>
        ) building risk management approach to the current project. In
a nutshell, the author represented an automated risk management model that builds an accurate risk
management planwith described details (risks, recommendations and etc.) [3].
      </p>
      <p>
        The study by Li G. 2021 represents the risk management model called “Monte Carlo”, which acts as
a decision-support system to predict possible risks and risks that may be caused by previous risks
(interdependencies network). This model is consisting of 3 main components: (
        <xref ref-type="bibr" rid="ref2">1</xref>
        ) development of risk
interdependencies network for possible risks identification; (
        <xref ref-type="bibr" rid="ref3">2</xref>
        ) development of “Monte Carlo”
simulation for assessment of risks; (
        <xref ref-type="bibr" rid="ref4">3</xref>
        ) further planning to risk mitigation plans. Also, the author
provedof importance oh his model by examining two cases of risk assessment in project management
[4].
      </p>
      <p>
        Syrine Ch., 2020 in his study represents an improved risk management model in Scrum methodology
to increase the success rate. This model is created by making a survey, taking the main parts from
PMBOK. The peculiarity of this model is that it contains all required phases from planning to risk
mitigation stages. This model is described in 6 stages: (
        <xref ref-type="bibr" rid="ref2">1</xref>
        ) risk management planning; (
        <xref ref-type="bibr" rid="ref3">2</xref>
        ) risk
assessment; (
        <xref ref-type="bibr" rid="ref4">3</xref>
        ) analysis performing; (
        <xref ref-type="bibr" rid="ref5">4</xref>
        ) risk response plan; (
        <xref ref-type="bibr" rid="ref1 ref6">5</xref>
        ) implementation previous stage; (
        <xref ref-type="bibr" rid="ref7">6</xref>
        )
riskmonitoring [5].
      </p>
      <p>The work of Béatrix Baraforta, 2019 presents the result of the development of a new Risk
Management assessment algorithm called “Integrated Risk Management process model for IT
Organizations (IRMIS)”. This algorithm differs from others in that in this model each process is divided
into more small business processes, which provides an opportunity for a more in-depth study of the risk.
It is also worth noting that this algorithm is developed based on the guidelines recommended by
international standard ISO 31000 in the context of multi-standards of ISO series [6].</p>
      <p>In the work of Varlamova D., 2020, was proposed implementation of an automated Risk
Management algorithm in the organization. The author suggests automating Risk Management with
software-based solutions.</p>
      <p>More precisely:
• building a process model of Risk Management with the help of Workflow task support systems;
• data streams will be in the data storage;
• the data will be processed and analyzed automatically using machine learning techniques with
the ability to build models and predictions;
• use of dashboards for reporting and visualization of operational, analytical, and statistical data;
• automated document management systems will ensure the integration of normative documents
from different management systems [7].
4.1.</p>
    </sec>
    <sec id="sec-5">
      <title>What is the risk and risk management?</title>
      <p>Formal articulation of the concept of risk is essential and allows organizations to refer to and apply
consistent definitions and develop a similar understanding of terminology. While a similar
understanding of risk is important, the word “risk” has many different meanings. Similarly, in everyday
discourse, "risk" can mean danger, likelihood, consequence, potential adverse factors or threats, and
sometimes opportunities [8].</p>
      <p>All of these factors, including probability, consequence, danger, etc., characterize risks. Risk is
often defined as "the influence of uncertainty on the achievement of objectives" in the context of the
ISO 31000 standard. As a result of this description, Risk Management cannot be a procedure that is
added on top of existing managerial decision-making systems. On the other hand, risk management is
an integral part of all operations and procedures.</p>
      <p>Additionally, according to ISO 31000, "goals might have diverse elements (financial, health, safety,
or environment) and can be applied at different levels (strategic, organization, project, product, and
process)". This variation from what is intended can be both beneficial and harmful.</p>
      <p>Furthermore, according to ISO 31000, risk is defined as "the mix of an event's consequences and its
associated likelihood" and is frequently characterized by a "connection between prospective events and
consequences, or a combination of both". As a result, the probability and sources of the risk's inception
are also risk components. Thus, risk can be described as a combination of the following elements shown
in Figure 1 [9].</p>
      <p>In other words, in order to identify risk, one must take into account an event that is probable to occur
owing to the presence of risk sources, as well as estimate its potential outcomes (the level of uncertainty
is defined by the likelihood of occurrence). These effects will have an impact on both individual and
corporate objectives.</p>
      <p>The source of risk is described in the standard as an element “which, by itself or in combination with
others, has the intrinsic potential to generate a risk”. The most elusive risk factor, probability, can be
simply defined as "the likelihood that something will occur." This "something" in the context of Risk
Management refers to a risk-related event.</p>
      <p>As we've already established, risk management is essential for achieving both individual and
corporate goals, but it's not the only one. This necessitates the careful application of the steps
mentionedin the sentences below.
4.2.</p>
    </sec>
    <sec id="sec-6">
      <title>What does good Risk Management mean?</title>
      <p>The following standards must be applied in order to evaluate the effectiveness of risk management:
• The prompt identification of risks;
• Risks are thoroughly examined, and the most significant ones are given increased importance;
• Balanced risk treatment is carried out;
• Risk treatment is carried out effectively;
• The resources required to implement contingency plans are available, and they have been
designed, tested, and are still feasible.</p>
      <p>Compliance with these criteria requires systematic Risk Management based on the following actions:
• Establishing a context or understanding of what we are “protecting” (our strategy or assets,
health, market performance, etc.) and who the stakeholders are;
• Identifying risks (what events may occur, why they may occur, how likely they are to occur,
and what impact they may have on us) and becoming familiar with as many of them as possible;
• Understanding the risks that are most significant to us helps us assess and evaluate them;
• Starting with the risks that are most significant to us, we can choose how to address them (we
can keep the risk, share it with another party, mitigate it, or prevent it by removing its source);
• Execution of the choice made in direct response to the Risk Management procedure;
• Creation of a crisis management strategy for risks that have been taken on or reduced. A strategy
for managing the risk should it materialize is the end result of this. Since Risk Management is a
mechanism for providing sufficient, but not absolute, security, this conceptual step of the process is
crucial.</p>
    </sec>
    <sec id="sec-7">
      <title>4.3. Main Functions of the Risk Management process</title>
    </sec>
    <sec id="sec-8">
      <title>4.3.1. Context establishing</title>
      <p>Information is both produced and consumed during the risk management process. The quality of the
raw material determines the quality of the final result, just like it does in any other process. The
following is a list of the most crucial inputs to the risk management process [10]:
• Goals. One essential component of the risk management approach is clearly defined objectives.
Remember that risk is defined as "the influence of uncertainty on goals." It will be highly challenging
to recognize, comprehend, and address the associated risks if the goals are not clearly defined. The
Center for Strategic and International Studies (CSIS) recommends "identifying and evaluating risk,
taking into account the strategy and mission of the organization" as the most effective strategy;
• Assets. Risk Management also requires knowledge of assets - the value of the organization,
what it is trying to protect, and potential sources of additional direct or opportunity costs. The key
assets of an organization are physical assets, technology, internal infrastructure, capital, finance, and
information systems. These assets can be ranked according to the degree of criticality and combined
into various categories;
• Information about stakeholders and their needs. According to ISO 31000, a stakeholder is "a
person or organization that has the potential to affect (or is already being impacted by, or may
become influenced by) a decision or activity." It is critical to understand stakeholders' demands in
order to predict their behavior, as their wants can be a source of various dangers for a business.</p>
    </sec>
    <sec id="sec-9">
      <title>4.3.2. Risk identification</title>
      <p>A thorough and current awareness of the hazards an organization faces is what risk identification is meant
to give it. A risk registry contains a list of all known dangers. It is created by making a list of all pertinent
risks' incidences, root causes, likelihoods, and effects [11].</p>
      <p>The risk register is constructed via a number of techniques. An essential method for identifying hazards
is past risk analysis, which can also serve as the foundation for internal classification. The organization
compiles databases of internal losses and obtains data from outside sources to better understand historical
hazards.</p>
      <p>As shown in Figure 2 below, some of the risks are internal. They originate from business processes and
are determined by the nature of the organization's activities. Often referred to as "operational risks", such
risks arise from poorly tuned business processes, human error, or system failure. They usually include
professional risks, personnel risks, and information and infrastructure risks.</p>
      <p>From a regulator's point of view, risks can be classified by the ability of the regulatory parties to
manage risks themselves (as opposed to the need to coordinate actions) and by their impact on other
parties (as opposed to risks affecting only one organization or regulatory area).</p>
      <p>Other risks originate in the external environment. They come from markets, partners, consumers,
regulatory actions and the natural environment. Business risk combines all events related to changes
inthe demand for products and services of the organization, changes in the price of these products, and
other relevant factors.</p>
      <p>Risk classification helps to comprehensively identify the risk. To develop a risk register, you can
analyze all existing types of risks to understand what each of them means to the organization.</p>
      <p>Risks can be identified through brainstorming using simple checklists where the discussion can be
based on risk classification. It is also possible to conduct a series of interviews during which risk
classifications can help identify the most suitable respondents and shape the design of the
questionnaires. Another useful risk identification tool is the Delphi method, which helps to reach a
compromise and conduct a preliminary safety analysis. The idea of the latter is to compile a list of
threats and risks by taking into account such characteristics as materials and equipment used or
produced in a given process or industry, operating conditions, and the relationship between the
components of the system.</p>
      <p>Another risk identification tool is a structured “what-if” analysis. It implies a systematic study carried
out in a group, using the standard phrase of the subjunctive "what if" in combination with indications
of the study of how a system, organization, or process will be affected by deviations from normal
business and behavior. The discussion is conducted by wording questions containing the phrase
"what- if": "what if ...", "what would happen if ..." or "whether happened to someone or something ...".
The purpose of the analysis is to stimulate the analysis team to explore potential scenarios, their
causes, consequences, and impacts on a large scale.</p>
    </sec>
    <sec id="sec-10">
      <title>4.3.3. Risk analysis and assessment</title>
      <p>The purpose of the risk analysis and assessment step of the risk management process is to prioritize
previously detected issues, ensuring that the most severe risks are handled first. Various threats are
contrasted to achieve this [12].</p>
      <p>Risk analysis is characterized as "the creation of an understanding of risk... by assessing the
implications and likelihood of their occurrence, as well as other risk parameters," according to ISO
31000. In order to decide if risk treatment is necessary, risk assessment compares the amount of risk
discovered throughout the analysis process to the risk criteria clarifying within the context under
discussion.</p>
      <p>Probability and repercussions, two components of the idea of risk, are used as performance
metrics. For a corporation, the effects of likelihood are frequently represented in terms of financial or
time losses, whereas for a regulator, the effects may include economic losses, environmental harm, or
worsening inpublic health. If decision-makers use these indicators, they can multiply the opportunity
by the repercussions to determine the potential cost of risk. You can decide which dangers are more or
less important by repeating this action with all of them.</p>
      <p>However, risks cannot always be quantified. In such cases, the construction of a matrix of
consequences and opportunities is the simplest and most often used tool for prioritizing risks. It allows
for a combination of qualitative and semi-qualitative impact ratings and opportunities to obtain an
objective and reasonable risk rating. According to ISO 31010, it is "often used as a screening tool when
multiple risks have been identified, for example, to identify risks that require further or more detailed
investigation”.</p>
      <p>Probability and repercussions, two components of the idea of risk, are used as performance
metrics. For a corporation, the effects of likelihood are frequently represented in terms of financial or
time losses,whereas for a regulator, the effects may include economic losses, environmental harm, or
worsening inpublic health. If decision-makers use these indicators, they can multiply the opportunity
by the repercussions to determine the potential cost of risk. You can decide which dangers are more or
less important by repeating this action with all of them. Those risks, whose costs are the biggest, will
be themost significant for the organization.</p>
      <p>Similarly, the full range of impacts can be broken down into “very low”, “low”, “medium”, “high”,
and “very high” impacts. This spectrum usually includes financial loss, professional safety, customer
safety, environmental damage, reputation, and other parameters.</p>
      <p>The impact of a single risk, for instance, may be "low" in terms of finances, "mid" in terms of
workplace safety, and "very high" in terms of reputation. The same risk event may have an impact on
each of these categories to differing degrees. It is simpler to assign a risk category in the overall rating
linked with the highest score awarded to any of the consequences when these criteria are organized into
a matrix.</p>
      <p>A significant advantage of this tool is that it does not allow users to calculate the cost of a risk that
cannot actually be calculated, such as loss of life or health. It also helps policy makers compare risks
across a wide range of areas and develop Risk Management at the government level.</p>
      <p>Once a risk rating has been developed in context of probability and influence, the organization needs
to assign each combination of probability and influence level of severity (for example, "high impact
and high probability of influence" - critical risk). This will create a matrix like the one shown in Figure
3. The organization can then use this matrix to prioritize all previously identified risks.</p>
    </sec>
    <sec id="sec-11">
      <title>4.3.4. Selection and implementation of risk treatment strategies</title>
      <p>Once the risks have been prioritized, the organization can decide how to respond to each risk, starting
with the most pressing. Key inputs at this phase include the organization's tolerance level for risk, often
known as risk appetite or risk acceptance requirements.</p>
      <p>Next, we will look at four main risk treatment strategies:
• Tolerating or accepting risk;
• Transfer or sharing of risk;
• Risk mitigation;
• Risk avoidance.</p>
      <p>Due to ISO 31000, selecting the best risk management approach depends on striking a balance
between the implementation's effort and expense and the rewards realized while also taking into account
statutory, regulatory, and other criteria including social responsibility and environmental protection.
In order to choose the best or most profitable alternative, cost-benefit analysis is frequently used to
choose a risk management plan. It compares the whole projected expenses to the total expected
benefits.</p>
      <p>When choosing a risk treatment strategy, it is important to take into account the risk's magnitude,
the value that will come from the risk-related activity (which can be stated through targeting), and the
cost of risk management.</p>
      <p>Tolerating or accepting a risk is the value that will result from the risk-related activity (which
canbe expressed through targeting), and the cost of risk management when selecting a risk treatment
method.</p>
      <p>1. Where "the stakes are high", i.e. the expected benefit from risk-taking is extremely high.
2. When the cost of treating risk is greater than the cost of possible damage if the risk event
occurs(example, it makes no sense to spend $100 on risk mitigation if it entails a loss of $50).
3. When something is beyond personal or organizational control and there is no other choice but
totake the risk.
4. When the decision maker is willing to take the risk (and all legal and regulatory
requirementshave been met).</p>
      <p>Taking the risk does not mean that the risk is forgotten. This means that whoever takes a risk knows
why they are doing it, that the risk is entered into the risk register, and that all risks taken are taken
intoaccount when developing contingency plans.</p>
      <p>Transferring risk means sharing risk with another party or parties. One of the possible strategies
in this case is outsourcing, when one company transfers to another part of the functions and the risks
associated with them. Another well-known risk transfer strategy is insurance.</p>
      <p>Sharing risk with another person or parties is referred to as risk transfer. Outsourcing, where one
organization passes some of the functions and risks associated with them to another, is one of the
conceivable methods in this situation. Insurance is a well-known method of risk transmission.</p>
      <p>The process of risk mitigation entails making an effort to reduce the effects and/or likelihood of a
risk event happening. This might be accomplished by removing risk factors, altering the probability of
an event occurring, or altering its effects.</p>
      <p>Risk avoidance means stopping or avoiding activities that may increase the likelihood of a risk
occurring. It also implies the waiver of all benefits associated with it, including some benefits that
cannot be foreseen. For example, banning certain manufacturing processes can hinder the
development of potentially beneficial technologies. Risk avoidance is generally preferred when the
expected benefit does not exceed the cost of risk mitigation and when the risk cannot be accepted.</p>
      <p>The ISO 31000 standard advises that when choosing risk treatment methods, an organization take
into account the values and vision of its stakeholders as well as the best channel for communication
with them. It is also advised to consider the possibility of additional hazards associated with the
implementation of new regulations. Even if it doesn't, the failure or ineffectiveness of risk management
strategies could still result in a severe risk.</p>
      <p>Once a risk's method of action has been established, a risk treatment plan that outlines the approaches
an organization will use to handle each risk included in the identified risks and specifies the order in
which each risk must be treated must be developed. According to the guideline, the risk treatment
approach should include the following:
• Reasons for choosing a particular processing method, including a description of the expected
benefits;
• List of persons responsible for the approval and implementation of the plan;
• Proposed actions (which may include the development of regulations);
• Necessary resources.</p>
      <p>The risk treatment plan is the first tangible result of the risk management process, and it serves as
the foundation for further decisions and the appropriate prevention of risks that may jeopardize the
attainment of organizational goals.</p>
    </sec>
    <sec id="sec-12">
      <title>5. Comparing and suggesting the most suitable model for the organization</title>
      <p>In this research, the first three Risk Management models, described in the paragraph above (literature
review), were compared to determine the most suitable Risk Management model for present
organizations.
5.1. “Atropos” Risk Management model, presented by Alexsandro S.F.</p>
      <p>In comparison with other suggested models, the “Atropos” model has a more complex structure.
Firstly, the structure of “Atropos” consists of the following six main components that allow to users
interact with this Risk Management model:
• Interface: due to these component users can access the project input and output. In other
words, this component allows to users’ up-to-date project details and get back project
recommendations;
• System view and API (Application Programming Interface): this is one of the main
components since they are used to integrate the application layer with other model components;
• Database: this component helps to store whole project information as well as information about
previous projects that are used for Risk Management recommendations;
• Configuration: to generate recommendations, the Risk Management model has to be
configured via these components to set project similarities;
(a)
(b)
(c)
Figure 4a: “Atropos” interface (a – project details, b – setting, c – risk recommendation)
• Risks and Recommendations generator: this component uses Bots for constant monitoring
of project events and comparing them with previous projects from the database. In case of event
matching - Bots generate risks with their recommendations.</p>
      <p>Secondly, one of the biggest advantages of “Atropos” Risk Management model over other models
is the user-friendly interface, showed in Figure 4a and Figure 4b, which is easy to use even for a
specialist who is not good at Risk Management.</p>
      <p>After establishing the concept of “Atropos” Risk Management (Figure 5), we can figure out the
main advantages and disadvantages of this model by its functionality:</p>
      <p>Advantages:
• User–friendly interface;
• Risks are detected by the model itself;
• Recommendations generated by the model itself;
• The minimum human involvement;
• Many steps described in Basic Risk Management are automated.</p>
      <p>Disadvantages:
• The database must be filled by users;
• Risks with recommendations must be filed into a database before projects started;
• The model can give incorrect recommendations in case of absence the of similarities in the
database.</p>
      <p>The main difference of the “Monte Carlo” model from others is that this model considers not only
identified risks but also covers risks that may entail identified risk [13].</p>
      <p>Like the previous “Atropos” Risk Management model, “Monte Carlo” model uses previous experiences
(projects histories) to predict risks more accurately and possibly their cause.</p>
      <p>“Monte Carlo” Risk Management model consists of three main stages with their components.</p>
      <p>The first stage is “Risk identification”. The input for this stage is information about previous similar
projects to identify current project risks and build interdependencies with other risks. As output, from this
stage, we will get possible project risks in relation to other risks, which can be realized in case the previous
risk is not mitigated. Knowing all possible risks – allows for building cause-effect relationships. In addition,
in this step, each risk’s spontaneous probability (SP) and transition probability (TP) are also calculated
(Figure 6). By the end of this stage, the author proposed to call this stage as “Development Risk
Interdependencies Network (RIN)”.</p>
      <p>The next stage is “Risk Assessment”. As input parameters here stand the project and experts’
opinions. In addition, at this stage, the “Monte Carlo” Risk Management model is built by modeling
behaviors of identified project’s risk occurrence. After this, for each identified and related risk calculated
the following parameters, which we get as output parameters: local and global influence of risk, total
risk loss, and total risk propagation loss.</p>
      <p>The final stage is “Risk Treatment”. In this stage project team, according to the identified and
evaluated risk, makes a plan for risk mitigation. After that, comes the evaluation of proposed plans for
risk treatment. And finally, the project manager or stockholders choose the most effective way to risk
treatment.</p>
      <p>Unlike the “Atropos” model, “Monte Carlo” Risk Management model refers to mathematical
calculation and the involvement of people more often, which is one of the significant disadvantages of
“Atropos” Risk Management model. And the main advantage is identifying possible project risks and
risks that may be caused by previous risks.</p>
    </sec>
    <sec id="sec-13">
      <title>5.3. Risk Management model in Scrum development process, proposed by</title>
    </sec>
    <sec id="sec-14">
      <title>Syrine Ch.</title>
      <p>The Risk Management model, proposed by Syrine Ch., was created on basis of PMBOK (Project
Management Body Of Knowledge) and by making a survey by 65 experts from different countries.
Unlike previously described models, it does not have any automated algorithms or mathematical
models. However, this model covers all requirements described in standard ISO 31000.</p>
      <p>The author divided this model into several stages, from risk planning to risk monitoring (Figure 7):
• Risk Planning;
• Risk Identification;
• Quantitative and Qualitative analyze;
• Risk Response;
• Risk Response Implementing;
•</p>
      <sec id="sec-14-1">
        <title>Risk Monitoring.</title>
        <p>In the first stage author highlighted “Risk Planning”. Like other models, the input for this stage is
detailed information about the current project status, and as output comes a general plan of risk
management.</p>
        <p>The second stage is the “Identification of risk”. In this stage author proposed involving all Scrum
team members. Risks are identified by team experience and experts’ ideas that are shared among the
team. In addition, the author highlighted the importance of this stage by detailed analysis during risk
identification. The output of this stage is the risk register with the following parameters:
• Description – the short description of identified risk;
• Date of risk birth – the date when risk is identified;
• Lakewood – the possibility of risk realizing;
• Impact – influence of risk;
• Category – the group for which risk belongings;
• Priority – identifying the priority among risks;
• Status – determine whether the risk is mitigated or still open.</p>
        <p>In addition, the author highlighted the importance of sharing information about registered risks to
make better collaboration between the team.</p>
        <p>The third stage is “Quantitative and Qualitative analyze”. This stage is responsible for risk
analyzinghow it can be influenced by the project. Unlike Risk Management models described before,
this model does not have an exact way to how calculate the impact. Mostly, it will depend on the
project, which iswhy this model is more suitable for small projects.</p>
        <p>The next stages are “Risk Response” and “Risk Response Implementing”. In this step, Scrum team
members choose the best strategies to mitigate and take an action under identified risks.</p>
        <p>The final stage is “Risk Monitoring”. This step is designed to control mitigated risks and used as a
plan for future projects.</p>
        <p>Obtaining the ultimate risk information is possible after the product has been delivered. The risk
register offers a view of all detected risk data, and future scrum projects can use this data to plan.</p>
      </sec>
    </sec>
    <sec id="sec-15">
      <title>6. Result of analytical comparison of Risk Management model</title>
      <p>Since we covered all the main concepts of the three above-described models such as “Atropos”,
“Monte Carlo” and model suggested by Syrine Ch., we can build a comparison table to identify the
most suitable Risk Management model for the organization. As the basis for comparison, we took the
main components from ISO 31000 and PMBOK described in the fifth paragraph and all main stages
from each Risk Management models (Table 1).</p>
      <p>After comparing of three models, we can easily say that each model meets all main requirements
described in ISO 31000 and PMBOK. Since these models have their specifications, all of them can be
integrated into the organization depending on the project size.</p>
      <p>However, XXI century is the century of digitalization, “Atropos” Risk Management model is more
suitable for many organizations, since, it has automated business processes and requires less human
involvement, which is most important.</p>
      <p>One of the biggest cons of “Atropos” Risk Management model is the implementation cost. Since,
this model requires of integration databases, APIs, Bots and etc., more organizations cannot effort to
implement this model.</p>
      <p>Thus, we can conclude, that organizations have to choose a Risk Management model according to
the project size. For example, “Atropos” is suitable for big organizations with large projects, while
“Monte Carlo” model is suitable for medium organizations, and the model proposed by Syrine Ch. is
suitable for small organizations respectively.</p>
    </sec>
    <sec id="sec-16">
      <title>7. Conclusion</title>
      <p>This research presented to understand the basics of Risk and Risk Management terms by reviewing
existing models. This work covered the basic meaning of Risk Management and how it is structured in
different models.</p>
      <p>To identify the most suitable Risk Management for organizations was compared the most widely
used models such as “Atropos”, “Monte Carlo” and the model suggested by Syrine Ch. The comparison
was according to the basic Risk Management rules (from ISO 31000 and PMBOK). We noted that all
authors of that models stick to the basic structure of Risk Management that is shown in Table 1. The
main difference between them is the way of integration in the organization.</p>
      <p>Making detailed comparisons between model components, allowed us to identify which models are
suitable for the organization. Rather, it was revealed that all models contain all the necessary
components described in the standard. Moreover, the selection of the model should depend on the type
of organization and on the type of project.</p>
      <p>In addition, it should be mentioned, that author highlighted that their model is a primitive type, and
they will improve their models by collecting more information from future projects.</p>
    </sec>
    <sec id="sec-17">
      <title>8. References</title>
    </sec>
  </body>
  <back>
    <ref-list>
      <ref id="ref1">
        <mixed-citation>
          5.2. “Monte Carlo”
          <article-title>Risk Management model, proposed by Li G.</article-title>
        </mixed-citation>
      </ref>
      <ref id="ref2">
        <mixed-citation>
          [1]
          <string-name>
            <given-names>K.</given-names>
            <surname>Buganová</surname>
          </string-name>
          ,
          <string-name>
            <given-names>J.</given-names>
            <surname>Šimíčková</surname>
          </string-name>
          ,
          <article-title>Risk management in traditional and agile project management</article-title>
          ,
          <source>Transportation Research Procedia</source>
          <volume>40</volume>
          (
          <year>2019</year>
          )
          <fpage>986</fpage>
          -
          <lpage>993</lpage>
          . URL: https://doi.org/10.1016/j.trpro.
          <year>2019</year>
          .
          <volume>07</volume>
          .138.
        </mixed-citation>
      </ref>
      <ref id="ref3">
        <mixed-citation>
          [2]
          <string-name>
            <given-names>A.</given-names>
            <surname>Luis</surname>
          </string-name>
          ,
          <article-title>Longevity of risks in software development projects: A comparative analysis with an academic environment</article-title>
          ,
          <source>Procedia Computer Science</source>
          <volume>181</volume>
          (
          <year>2021</year>
          )
          <fpage>827</fpage>
          -
          <lpage>834</lpage>
          . URL: https://doi.org/10.1016/j.procs.
          <year>2021</year>
          .
          <volume>01</volume>
          .236.
        </mixed-citation>
      </ref>
      <ref id="ref4">
        <mixed-citation>
          [3]
          <string-name>
            <given-names>S. F.</given-names>
            <surname>Alexandro</surname>
          </string-name>
          ,
          <article-title>A risk prediction model for software project management based on similarity analysis of context histories</article-title>
          ,
          <source>Information and Software Technology</source>
          (
          <year>2021</year>
          ). URL: https://doi.org/10.1016/j.infsof.
          <year>2020</year>
          .
          <volume>106497</volume>
          .
        </mixed-citation>
      </ref>
      <ref id="ref5">
        <mixed-citation>
          [4]
          <string-name>
            <given-names>L.</given-names>
            <surname>Guan</surname>
          </string-name>
          ,
          <string-name>
            <given-names>A.</given-names>
            <surname>Abbasi</surname>
          </string-name>
          ,
          <string-name>
            <given-names>M.J.</given-names>
            <surname>Ryan</surname>
          </string-name>
          ,
          <article-title>A simulation-based risk interdependency network model for project risk assessment, Decision Support Systems 148 (</article-title>
          <year>2021</year>
          )
          <article-title>113602</article-title>
          . URL: https://doi.org/10.1016/j.dss.
          <year>2021</year>
          .
          <volume>113602</volume>
          .
        </mixed-citation>
      </ref>
      <ref id="ref6">
        <mixed-citation>
          [5]
          <string-name>
            <surname>Ch. Syrine</surname>
          </string-name>
          ,
          <article-title>A framework for risk management in Scrum Development Process</article-title>
          ,
          <source>Procedia Computer Science</source>
          <volume>164</volume>
          (
          <year>2021</year>
          )
          <fpage>187</fpage>
          -
          <lpage>192</lpage>
          . URL: https://doi.org/10.1016/j.procs.
          <year>2019</year>
          .
          <volume>12</volume>
          .171.
        </mixed-citation>
      </ref>
      <ref id="ref7">
        <mixed-citation>
          [6]
          <string-name>
            <given-names>B.</given-names>
            <surname>Barafort</surname>
          </string-name>
          ,
          <string-name>
            <given-names>A. L.</given-names>
            <surname>Mesquida</surname>
          </string-name>
          ,
          <string-name>
            <given-names>A.</given-names>
            <surname>Mas</surname>
          </string-name>
          ,
          <article-title>Integrated risk management process assessment model for IT organizations based on ISO 31000 in an ISO multi-standards context</article-title>
          ,
          <source>Computer Standards &amp;Amp; Interfaces</source>
          <volume>60</volume>
          (
          <year>2018</year>
          )
          <fpage>57</fpage>
          -
          <lpage>66</lpage>
          . URL: https://doi.org/10.1016/j.csi.
          <year>2018</year>
          .
          <volume>04</volume>
          .010.
        </mixed-citation>
      </ref>
      <ref id="ref8">
        <mixed-citation>
          [7]
          <string-name>
            <given-names>D.</given-names>
            <surname>Varlamova</surname>
          </string-name>
          ,
          <string-name>
            <given-names>A.</given-names>
            <surname>Dolzhenkova</surname>
          </string-name>
          ,
          <string-name>
            <given-names>S.</given-names>
            <surname>Korochkina</surname>
          </string-name>
          ,
          <article-title>Automation in risk management” Economics and Environmental Management (</article-title>
          <year>2020</year>
          )
          <fpage>78</fpage>
          -
          <lpage>86</lpage>
          . URL: https://doi.org/10.17586/
          <fpage>2310</fpage>
          -1172-2020- 13-4-
          <fpage>78</fpage>
          -86.
        </mixed-citation>
      </ref>
      <ref id="ref9">
        <mixed-citation>
          [8]
          <string-name>
            <given-names>J.</given-names>
            <surname>Masso</surname>
          </string-name>
          ,
          <article-title>Risk management in the software life cycle: A systematic literature review</article-title>
          ,
          <source>Computer Standards &amp;Amp; Interfaces</source>
          <volume>71</volume>
          (
          <year>2020</year>
          )
          <article-title>103431</article-title>
          . URL: https://doi.org/10.1016/j.csi.
          <year>2020</year>
          .
          <volume>103431</volume>
          .
        </mixed-citation>
      </ref>
      <ref id="ref10">
        <mixed-citation>
          [9]
          <string-name>
            <given-names>B.</given-names>
            <surname>Barafort</surname>
          </string-name>
          ,
          <article-title>Integrated Risk Management Process Assessment Model for IT organizations based on ISO 31000 in an ISO multi-standards context</article-title>
          ,
          <source>Computer Standards &amp; Interfaces</source>
          <volume>60</volume>
          (
          <year>2018</year>
          )
          <fpage>57</fpage>
          -
          <lpage>66</lpage>
          . URL: https://doi.org/10.1016/j.csi.
          <year>2018</year>
          .
          <volume>04</volume>
          .010.
        </mixed-citation>
      </ref>
      <ref id="ref11">
        <mixed-citation>
          [10]
          <string-name>
            <given-names>J.</given-names>
            <surname>Arlinghaus</surname>
          </string-name>
          ,
          <article-title>Assessing and mitigating the risk of Digital Manufacturing: Development and implementation of a digital risk management method</article-title>
          ,
          <source>IFAC-PapersOnLine 54.1</source>
          (
          <year>2021</year>
          )
          <fpage>337</fpage>
          -
          <lpage>342</lpage>
          . URL: https://doi.org/10.1016/j.ifacol.
          <year>2021</year>
          .
          <volume>08</volume>
          .159.
        </mixed-citation>
      </ref>
      <ref id="ref12">
        <mixed-citation>
          [11]
          <string-name>
            <given-names>S.</given-names>
            <surname>Sankaranarayanan</surname>
          </string-name>
          ,
          <article-title>Prediction of risk percentage in software projects by Training Machine Learning Classifiers</article-title>
          .
          <source>Computers &amp;Amp, Electrical Engineering</source>
          <volume>94</volume>
          (
          <year>2021</year>
          )
          <article-title>107362</article-title>
          . URL: https://doi.org/10.1016/j.compeleceng.
          <year>2021</year>
          .
          <volume>107362</volume>
          .
        </mixed-citation>
      </ref>
      <ref id="ref13">
        <mixed-citation>
          [12]
          <string-name>
            <given-names>O.</given-names>
            <surname>Okudan</surname>
          </string-name>
          ,
          <article-title>A knowledge-based risk management tool for construction projects using case-based reasoning</article-title>
          ,
          <source>Expert Systems with Applications</source>
          <volume>173</volume>
          (
          <year>2021</year>
          )
          <article-title>114776</article-title>
          . URL: https://doi.org/10.1016/j.eswa.
          <year>2021</year>
          .
          <volume>114776</volume>
          .
        </mixed-citation>
      </ref>
      <ref id="ref14">
        <mixed-citation>
          [13]
          <string-name>
            <given-names>A.</given-names>
            <surname>Qazi</surname>
          </string-name>
          ,
          <article-title>Prioritizing risks in sustainable construction projects using a risk matrix-based Monte Carlo simulation approach</article-title>
          ,
          <source>Sustainable Cities and Society</source>
          <volume>65</volume>
          (
          <year>2021</year>
          )
          <article-title>102576</article-title>
          . URL: https://doi.org/10.1016/j.scs.
          <year>2020</year>
          .
          <volume>102576</volume>
          .