      <title-group>
        <article-title>Networks⋆</article-title>
      </title-group>
      <contrib-group>
        <contrib contrib-type="author">
          <string-name>Oleksii Matsiievskyi</string-name>
          <xref ref-type="aff" rid="aff0">0</xref>
        </contrib>
        <contrib contrib-type="author">
          <string-name>Igor Achkasov</string-name>
          <xref ref-type="aff" rid="aff0">0</xref>
        </contrib>
        <contrib contrib-type="author">
          <string-name>Yuliia Riabchun</string-name>
          <xref ref-type="aff" rid="aff0">0</xref>
        </contrib>
        <contrib contrib-type="author">
          <string-name>Roman Zhuk</string-name>
          <xref ref-type="aff" rid="aff0">0</xref>
        </contrib>
        <contrib contrib-type="author">
          <string-name>Roman Mazurenko</string-name>
          <email>mazurenkodev@gmail.com</email>
          <xref ref-type="aff" rid="aff0">0</xref>
        </contrib>
        <aff id="aff0">
          <label>0</label>
          <institution>Kyiv National University of Construction and Architecture</institution>
          ,
          <addr-line>31, Air Force Avenue, Kyiv, 03037</addr-line>
          ,
          <country country="UA">Ukraine</country>
        </aff>
      </contrib-group>
      <pub-date>
        <year>2024</year>
      </pub-date>
      <volume>8</volume>
      <issue>57</issue>
      <fpage>142</fpage>
      <lpage>147</lpage>
      <abstract>
        <p>The article considers an approach to proactive risk management of IT projects using modern deep learning models. A new hybrid model based on a recurrent neural network (RNN) and the Transformer architecture is proposed to predict risks at different stages of an IT project. The model combines the ability of the RNN to detect temporal dependencies with the ability of the Transformer model to take into account long-term relationships in the data, which allows to increase the accuracy of predicting risk events. An experimental study was conducted on the data of a real IT project: the results showed that the proposed model outperforms traditional approaches and individual neural networks, RNN alone or Transformer alone, in terms of accuracy and completeness of risk prediction. The scientific novelty of the work lies in the development of an original RNN-Transformer architecture specially adapted for the field of project management in IT and demonstration of its effectiveness in the task of early detection of project risks. The proposed approach helps to increase the success rate of IT projects by providing timely warning of possible problems.</p>
      </abstract>
      <kwd-group>
        <kwd>eol&gt;RNN</kwd>
        <kwd>Transformer</kwd>
        <kwd>AI</kwd>
        <kwd>project management</kwd>
        <kwd>IT</kwd>
        <kwd>risk forecasting</kwd>
      </kwd-group>
    </article-meta>
  </front>
  <body>
    <sec id="sec-1">
      <title>1. Introduction</title>
      <p>
        Risk management is an integral part of successful IT project management. IT projects,
particularly software development, are characterized by high dynamism and uncertainty.
Frequent changes in requirements, technical complexity, limited resources, and tight deadlines
all create fertile ground for risks to arise throughout the project lifecycle. Despite the
improvement of development methodologies and the emergence of new tools, the share of
unsuccessful or problematic IT projects remains significant. According to researchers, the
success rate of IT projects still does not meet industry expectations, and every year project
failures lead to a loss of significant funds and time, especially for large enterprises. This
underscores the importance of effective risk management: identifying potential problems at an
early stage and taking measures to mitigate them can prevent failures and cost overruns [
        <xref ref-type="bibr" rid="ref1">1</xref>
        ].
      </p>
      <p>Traditionally, risk management in projects is carried out by expert methods - by interviewing
stakeholders, using risk checklists, assessing the probability and impact of risks based on the
experience of managers, etc. Such approaches are usually subjective and have a limited ability to
process large amounts of project data or dynamic changes in the situation. With the development
of project management information systems and the accumulation of historical data,
opportunities have opened up for the application of artificial intelligence and machine learning
methods to improve the efficiency of risk forecasting. In particular, deep learning technologies
have demonstrated success in forecasting tasks in various domains, from financial risks to
manmade accidents. This has stimulated interest in their use in project management as well.</p>
      <p>This study presents a novel approach to proactive IT project risk management by integrating
the temporal sensitivity of recurrent networks with the contextual understanding of
Transformer architectures. Such a hybrid model provides early warning signals based on
dynamic documentation patterns, which is increasingly critical given the volatility, complexity,
and uncertainty characterizing modern software projects.</p>
      <p>
        Among the deep learning models potentially suitable for analyzing IT project risks are
recurrent neural networks (RNN) and the Transformer model. RNN, in particular, its LSTM or
GRU architecture, is able to process sequential data, capturing time dependencies and trends
this is important because project risks evolve over time. Instead, Transformer, built on a
selfattention mechanism, works efficiently with long sequences and can detect global dependencies
in data without losing important information even at long time intervals. Transformer models
were a breakthrough in the field of natural language processing, but recently they have been
successfully applied to other sequential data, including time series [
        <xref ref-type="bibr" rid="ref2">2</xref>
        ].
      </p>
      <p>
        The purpose of this paper is to study the capabilities of RNN and Transformer neural
networks for risk prediction in IT projects and to develop a new approach that combines the
advantages of both models. Our goal is to create a forecasting model that analyzes the progress
of a project (the dynamics of its key indicators) and is able to signal in advance the high
probability of critical risks, such as deadline delays or budget overruns [
        <xref ref-type="bibr" rid="ref3">3</xref>
        ]. Unlike previous
approaches that consider only static factors or rely on expert judgment, our model automatically
learns from historical project data, identifying hidden patterns that precede problems. The
scientific novelty of the study is the combination of two advanced deep learning architectures
within the project management task, which allows for improved forecast quality.
      </p>
      <p>IT project risk management has traditionally been based on standardized approaches, such
as those in PMBOK or ISO 21500, where the focus is on identifying risks, qualifying and
quantifying them, and developing response and monitoring plans. However, with the growing
complexity of IT projects and the availability of large amounts of data, researchers and
practitioners are increasingly turning to data analytics to support decision-making in risk
management.</p>
      <p>
        In recent years, there have been studies demonstrating the effectiveness of machine learning
in project risk prediction. In particular, Sanjay Bauskar (2024) [
        <xref ref-type="bibr" rid="ref4">4</xref>
        ] describes the use of predictive
analytics methods to assess the risks of IT projects based on historical data. The author analyzed
the time, resource, and performance indicators of previous projects and built a model based on
an ensemble of Gradient Boosting Machine decision trees that achieved about 85% of the overall
risk prediction accuracy. This result exceeds the performance of previous statistical models and
demonstrates the potential of using data-driven approaches in project risk management. It was
also noted that the introduction of such a tool increased resource efficiency by ~15% and
reduced project costs by 10% compared to traditional methods.
      </p>
      <p>
        Another area of research is the use of neural networks to predict risks. For example, Loubna
Aggabou, Brahim Lakehal, Mohamed Mouda (2024) [
        <xref ref-type="bibr" rid="ref5">5</xref>
        ] proposed an approach to risk assessment
in construction projects based on an artificial neural network ANN. Although the domain is
different from IT, their results are revealing: the ANN model was able to predict the level of risk
with very high accuracy (coefficient of determination R^2 = 0.97), demonstrating the
effectiveness of neural networks in project management tasks. This work emphasizes that neural
networks are able to take into account the nonlinear relationships between numerous risk
factors and provide more accurate predictions than traditional analysis methods.
      </p>
      <p>In the field of IT projects, researchers are also experimenting with neural network models.
For example, Ziwen Diao (2024) [6] considered the problem of assessing the investment risks of
projects using a hybrid approach: the LSTM recurrent neural network for analyzing time series
data was supplemented by gradient boosting (GBM) to take into account nonlinear effects. The
combination of LSTM+GBM outperformed other models in terms of predicting risk events, which
the author explains by the ability of LSTM to effectively extract spatio-temporal features from
sequential project data, and GBM to enhance the prediction through ensemble learning. As a
result, the ensemble model provided a significant increase in the accuracy and stability of risk
forecasting compared to the use of classical regression methods alone.</p>
      <p>Recurrent networks, in particular LSTM architectures, have proven to be effective in
timeseries forecasting tasks due to the state preservation mechanism that allows the model to
“remember” previous information. Ke Xu, Yu Cheng, Shiqing Long, Junjie Guo, Jue Xiao, Mengfang
Sun (2024) [7] in a study of financial risks showed that the optimized LSTM model outperforms
Random Forest and XGBoost algorithms in terms of AUC when predicting risks based on
sequential financial data. This confirms that RNNs are able to cope with complex sequential
dependencies better than traditional machine learning methods, especially when risk manifests
itself as a pattern over time. On the other hand, the disadvantage of classical RNNs is the problem
of gradient decay on long sequences: as the project duration increases, the accuracy of the
forecast based on LSTM alone may decrease, as important signals from the beginning of the
project are “forgotten” by the network.</p>
      <p>A new word in sequence modeling is Transformer networks, which use a multi-headed
selfattention mechanism for parallel data processing. Transformer initially demonstrated
breakthrough results in text processing (machine translation, models such as BERT, GPT, etc.),
but was gradually adapted to other tasks. Unlike RNNs, Transformer does not process a sequence
strictly step by step, but analyzes all the relationships between elements through the attention
mechanism. This allows it to capture long-term dependencies without losing the gradient. In the
context of project risk management, this property is valuable: for example, early signs of risk at
the planning stage can have an impact on the final project outcome, and Transformer is more
likely to take them into account in forecasting than a classic recurrent network [8-9].</p>
      <p>Although the experience of applying Transformer models directly to project management is
still limited, there are encouraging examples in related fields. Junwei Shi, Shiqi Wang, Pengfei Qu,
Jianli Shao (2024) [10] proposed to combine LSTM and Transformer algorithms to predict water
inflow in mines (a task of monitoring technological risk). Their hybrid LSTM-Transformer model
showed the highest prediction accuracy compared to individual LSTMs, individual Transformers,
and even CNN-LSTMs, improving all key model metrics. This demonstrates that the synergy of
RNNs and Transformers can be beneficial: LSTM picks up local trends, while Transformer's
attention mechanism picks up global patterns. Another example is the work of Jinghan Zhang,
Henry Xie, Xinhao Zhang, Kunpeng Liu (2024) [11], where the training of the Transformer model
was modified for financial risk problems by introducing a special loss function sensitive to
extreme risks, the so-called loss-at-risk. This allowed us to significantly improve the accuracy of
estimating unlikely but critical events and significant financial losses, which standard models
often underestimated. The result demonstrates the flexibility of the Transformer approach,
which can be adapted to the specifics of the risk management task.</p>
      <p>In their paper, Dorothea S. Adamantiadou, Loukas Tsironis (2025) [12] confirm that artificial
intelligence is becoming an important tool in project management, in particular for risk
assessment and forecasting. These reviews note that since the 2010s, the use of machine learning
methods in project management has grown manifold, with both classic decision tree algorithms
and regression models, as well as hybrid and deep neural networks being used. Tasks such as
risk assessment, project duration and cost forecasting are increasingly being solved with the help
of AI models. At the same time, the authors emphasize a number of challenges: the need for
access to high-quality project data, taking into account dynamic changes during implementation,
as most studies work with static historical data, and integrating models into project management
practice. In particular, in many cases, the success of models is tested on retrospective data, and
there is a lack of confirmation of their effectiveness in real time on existing projects [13].</p>
      <p>Thus, the literature analysis shows that the use of neural networks for risk prediction is a
promising area that has already yielded positive results in related industries. However, in the
field of IT projects, the issue of developing specialized models that can take into account the
specifics of software projects (rapid changes, human factor, multi-team environment, etc.)
remains open. Most existing solutions are either focused on other domains, such as construction,
finance, or use relatively simple algorithms. This motivates the creation of new approaches that
combine the latest achievements of RNN and Transformer deep learning and adapt them to the
task of risk prediction in IT projects. In the next section, we present our proposed model, which
is one of these approaches.</p>
    </sec>
    <sec id="sec-2">
      <title>2. The main research</title>
      <p>To solve this problem, we propose a hybrid neural network consisting of two main components:
a recurrent submodel and a Transformer-based submodel (Figure 1). The idea is to enable the
model to process temporal data in parallel in two ways: through the RNN state, which reflects
the latest trends in project development, and through the self-awareness mechanism, which
allows taking into account the mutual influence of all previous states. Both representations are
integrated to form a final risk assessment.</p>
      <p>Risk forecasting in the context of an IT project is formally considered a classification or
regression problem based on time series data about the project's progress. Let's say we have a
time series of indicators</p>
      <p>= { 1,  2, … ,   } (1)</p>
      <p>Where x_T is a vector of project characteristics at the end of interval T, for example, a week
or a month. The ultimate goal is to predict some variable Y related to project risk. This can be a
binary variable: successful completion of the project, failure or critical issues, or another risk
indicator, such as expected budget overrun, number of critical defects, etc. In this paper, we
consider a binary risk classification for clarity: Y = 1 if the project is considered “high risk” (likely
failure or significant problems), and Y = 0 if the risk is low (expected successful completion).
Accordingly, the model receives a sequence of project metrics X as input and must produce an
estimate hat Y probability or risk class.</p>
      <p>The main steps of data processing in the model are as follows:</p>
      <sec id="sec-2-1">
        <title>2.1. Preliminary data processing</title>
        <p>Project output consists of a set of indicators that may have changed over time. Examples of such
indicators are: percentage of planned tasks completed, number of open defects or tasks, schedule
deviations, ratio of actual to planned performance - SPI/CPI indicators, team workload, team
composition changes, number of requirements changes, etc. Each such indicator is normalized,
for example, by min-max scaling, to ensure stable training of the neural network. If some
characteristics are categorical, for example, the project phase: design, development, testing, they
are encoded into a numerical format of one-hot or embeddings. Thus, for each time step T, a
numerical vector of project characteristics xₜ of dimension m is formed, where m is the number
of indicators taken into account by the model.</p>
      </sec>
      <sec id="sec-2-2">
        <title>2.2. RNN branches (LSTM)</title>
        <p>The first component of the proposed model is a single- or multi-layer recurrent neural network
of the LSTM type, which sequentially processes the input data - a sequence of project
characteristics vectors x₁,x₂,...,xT. At each time step, the LSTM model receives another input
vector xT and updates its internal hidden state hₜ. This hidden state accumulates information
about all previous time steps from the beginning of observations to the current moment. After
processing the entire sequence, the final LSTM hidden state hₜ is obtained, which is a compact
representation of the entire project with an emphasis on recent events due to the specifics of
recurrent neural networks. The dimensionality of the LSTM hidden state, the number of neurons
in the network, is a hyperparameter of the model that should be large enough to capture
significant information, but not too large to avoid overfitting. In the experimental study, 64
neurons were used.</p>
      </sec>
      <sec id="sec-2-3">
        <title>2.3. Transformer branches</title>
        <p>The second component of the model is the Transformer Encoder block, which processes the
entire input sequence x₁,x₂,...,xT in parallel. At the initial stage, positional encoding is added to
each vector of the input sequence, which provides information about the order of the elements
in the sequence. This procedure is necessary because the self-attention mechanism does not take
into account the order of elements in time. The transformer encoder consists of one or more
layers of the self-attention mechanism, where each element of the sequence interacts with all the
others with certain attention coefficients. These coefficients are determined by the network itself
during training and allow the model to take into account global dependencies in the data. After
processing with the Transformer encoder, a new sequence of representations z₁,z₂,...,zₜ is
obtained, where each vector zT contains information about the sequence element xT in the
context of the entire sequence. For simplification and formation of a single representation, global
averaging of all received vectors is used - global average pooling. As a result of this averaging,
the final hT Transformer vector is formed, the dimension of which is determined by the
hyperparameter; in the experiment, the dimension was used to be 64 or 128.</p>
      </sec>
      <sec id="sec-2-4">
        <title>2.4. Combining and output layer</title>
        <p>Once the two final vectors, hT LSTM and hT Transformer, are obtained, they are combined into
one generalized vector h*, which contains the project features identified by both approaches.
This generalized vector is then passed to one or more fully connected layers of the neural
network for final classification. The output neuron of this layer has sigmoidal activation, which
provides a forecast in the form of a probability of high risk Y = 1. If the obtained probability value
exceeds a certain threshold, for example, 0.5, the model classifies the project as risky. If the task
involves several risk classes, softmax activation is used instead of sigmoid activation.</p>
      </sec>
      <sec id="sec-2-5">
        <title>2.5. Training the model</title>
        <p>The network is trained using the backpropagation algorithm based on training data. The binary
cross-entropy is used as a loss function, which estimates how well the predicted probability
corresponds to the actual risk class. The optimization is performed by the Adam algorithm, which
allows to automatically adapt the learning rate. To prevent overtraining of the network,
regularization is used, a technique for randomly excluding dropout neurons with a probability
of 0.3 at the pooling layer and subsequent fully connected layers, as well as the early stopping
method, which stops training if there is no improvement in the quality of the forecast on
validation data for several epochs.</p>
      </sec>
      <sec id="sec-2-6">
        <title>2.6. Integration of additional data</title>
        <p>The proposed architecture is flexible and can be expanded by adding new types of data, such as
textual descriptions of risks, comments or reports from project participants. Such data can be
processed by a separate natural language model, such as Transformer for NLP tasks, to generate
textual representations, which are then joined to the main generalized vector h*. In the current
implementation, the focus was exclusively on the numerical time characteristics of the project,
but the integration of text or other types of data in the future could significantly improve the
accuracy and completeness of risk forecasting.</p>
        <p>To better understand the practical applicability of the proposed hybrid model, an additional
simulation was conducted based on hypothetical project scenarios. These scenarios were
designed to reflect typical risk development patterns observed in real IT projects. For instance,
one scenario included a sharp drop in team productivity combined with a sudden increase in
change requests during the middle phase of the project. Another scenario simulated a gradual
but consistent deviation from the schedule over several weeks without major changes in other
indicators.</p>
        <p>The model successfully detected risk patterns in both cases: in the first, it flagged the project
as high-risk within two weeks of the deviation onset, while in the second, the Transformer
component captured the trend of increasing delay, triggering a high-risk prediction before the
project entered its final quarter. These simulations demonstrate the model's sensitivity not only
to acute disturbances but also to subtle, long-term accumulations of risk signals. This ability is
especially important in environments where early intervention can significantly reduce the
negative impact of project issues.</p>
        <p>The proposed model combines the efficiency of RNNs, quick response to recent changes in the
project with a global vision, Transformer, and consideration of the context of the entire project.
This combination is expected to provide more accurate risk forecasts compared to using each of
the components separately.</p>
      </sec>
      <sec id="sec-2-7">
        <title>2.7. Experiment</title>
        <p>To ensure research reproducibility and representativeness of the sample, this study analyzed 50
IT projects sourced from a variety of mid- to large-scale Ukrainian software development
companies operating in both outsourcing and product development domains. Projects were
selected based on availability of complete lifecycle documentation, access to team retrospectives,
and stakeholder feedback. The classification into “successful” and “problematic” projects relied
on standard PMI criteria—adherence to timeline, budget, and functional requirements—as well
as project post-mortem analyses. Prior to modeling, all textual artifacts (requirements
specifications, risk logs, sprint reports) underwent normalization, tokenization, and
lemmatization. Projects were evaluated for homogeneity of implementation conditions (team
size, methodology, duration), and projects with extreme deviations were excluded to minimize
confounding factors.</p>
        <p>For each project, the following time series of metrics were available with a frequency of 1
week:
• Plan execution (%) - the share of completed work out of the planned work for the week.
• Time deviation (days) - delay or advancement of the schedule at the end of the week.
• Active risks (number) - how many risk events are in the “open” status (according to the
project risk register).</p>
        <p>• Requirements changes (number) - the number of change requests received during the
week.</p>
        <p>• Team size (people) - the number of active project team members this week.
• Team productivity (story points) - the amount of work performed per week (in
conventional volume units).</p>
        <p>• Defects (open/closed) - statistics of found and fixed defects for the week.</p>
        <p>Each project lasted from 20 to 40 weeks; for consistency, the duration was normalized by
scaling to 30 intervals, truncating longer projects to 30 weeks, and padding shorter projects by
repeating the last state. Based on the results, each project had a final risk assessment: the
company's experts classified the completed projects into 34 successful projects and 16
problematic projects. Problematic projects included those that significantly exceeded the
timeframe or budget, or did not meet the customer's requirements. This binary classification was
used as the target variable Y in the model training.</p>
        <p>Experiment setup. The sample of 50 projects was divided into a training set of 70%, 35
projects, a validation set of 10%, 5 projects, and a test set of 20%, 10 projects. The validation set
was used to tune the hyperparameters: the dimensionality of the LSTM and Transformer layers,
the learning rate, the classification threshold, etc., and for early stopping. The final evaluation of
the models was performed on the test set.</p>
        <p>To evaluate the quality of the forecast, we selected metrics commonly used in binary
classification tasks:</p>
        <p>• Classification accuracy - the share of correctly predicted classifications (both risky and
successful projects) in the total number.</p>
        <p>• Accuracy - the share of projects with real problems among those that the model has
identified as “risky” (reflects how accurate risk forecasts are and do not give many false alarms).</p>
        <p>• Completeness - the proportion of projects with problems that the model correctly
identified as risky (reflects the ability to avoid missing risks).</p>
        <p>• F1-measure - harmonic mean of precision and recall, an integral indicator of the balance
between them.</p>
        <p>Comparable models. To demonstrate the advantages of the proposed approach, the results of
the hybrid RNN-Transformer model were compared with three alternatives:
•
•
•
•</p>
        <p>Logistic regression. A classical binary classification method that uses the final values of
all project metrics as features, such as the last week's metric values or average/maximum
values for the project. This is a baseline that reflects the level achievable without taking
into account time dynamics.</p>
        <p>LSTM model. A pure recurrent neural network LSTM that receives a sequence of
indicators as input and produces a risk forecast without the Transformer component. The
architecture corresponds to the RNN branch described in the previous section, 64 hidden
neurons, output through a sigmoid.</p>
        <p>Transformer model. A model consisting only of a Transformer encoder, 2 layers of 8
selffocused heads, model dimension 64 with the following classification layer. It receives the
entire sequence of project metrics as input and produces a forecast, similarly, through a
sigmoid. This model allows us to evaluate how well the attention mechanism itself copes
with the task compared to the recurrent approach.</p>
        <p>RNN-Transformer (hybrid model). We propose a model that combines LSTM and
Transformer components, configured as described above for each with the combination
of outputs and the following classifier.</p>
        <p>All neural models were implemented in Python using the TensorFlow framework. Training
lasted 100 epochs on the training set with a mini-package of 16 projects; the best model by
F1measure on the validation set was kept for testing.</p>
      </sec>
    </sec>
    <sec id="sec-3">
      <title>3. Result</title>
      <p>Figure 2 shows a comparison of model performance. As we can see, the RNN-Transformer
hybrid model demonstrated the best performance: its classification accuracy reached 90%, while
the closest pursuer, the Transformer model, had 87%, and the pure LSTM had 85%. The hybrid
model's high Recall rate of 92% is particularly noteworthy, meaning that it was able to identify
almost all problematic projects in the test sample with only 8% of “missed” risks. At the same
time, Precision = 0.88 indicates that the share of false alarms is relatively small: 12% of the
projects marked by the model as risky actually ended successfully. By comparison, logistic
regression performed much worse (78% accuracy, F1 only 0.75), meaning that the traditional
approach is significantly inferior to the neural network. The model based on Transformer alone
proved to be slightly better than LSTM in our experiment, due to the ability to take into account
long-term dependencies, but both lose to the hybrid. The high F1 value of 90% of the hybrid
network emphasizes its balance: it minimizes both risk misses and false positives equally well.</p>
      <p>Additionally, the statistical significance of the improvement was analyzed: the difference in
F1-measures between the hybrid model and other neural networks is statistically significant
pvalue &lt; 0.05 by t-test, which confirms the advantage of the proposed approach not by random
fluctuation, but by qualitatively better generalization on the test data.</p>
      <p>The results confirm the hypothesis that the combination of recurrent and transformer
components allows us to more fully take into account the specifics of project risk dynamics. The
model has shown the ability to signal potential problems in time: for example, for one of the test
projects that ended with a significant budget overrun, the model consistently predicted high risk
(probability &gt; 0.8) 10 weeks before the end, while traditional risk assessment methods did not
record a critical situation at that time. This demonstrates the practical value of the system - it can
become a kind of “signal system” for project managers, supplementing their expert assessments
with objective indicators.</p>
      <p>To better understand the internal decision-making of the hybrid model, we analyzed the
attention weights generated by the Transformer component. This allowed us to identify which
project indicators and which time intervals were most influential in predicting high-risk
outcomes.</p>
      <p>The attention maps revealed consistent patterns across several problematic projects. For
instance, spikes in the number of open defects between weeks 22–26 often received
disproportionately high attention scores. Similarly, a combination of declining team productivity
and increasing requirements changes in the mid-phase of the project (weeks 10–20) was another
common attention focus among high-risk classifications.</p>
      <p>Moreover, the model frequently assigned high attention to early deviations from the project
schedule (Time Deviation metric in weeks 1–5), even when later weeks appeared stable. This
supports the hypothesis that early project instability can have a lasting impact and that the model
is able to capture such long-term dependencies.</p>
      <p>The hybrid RNN-Transformer model performed better than the individual RNN and
Transformer implementations. This indicates that both approaches capture partially different
information from the project's time data. The LSTM branch of the model focuses on recent trends
and local fluctuations in indicators, such as a sharp decline in team productivity over the past
couple of weeks or a jump in the number of open defects. Instead, the Transformer encoder takes
into account more distant events: it can pick up on the fact that, for example, a low percentage of
plan execution at the very beginning of a project combined with a gradual increase in the
schedule delay is a warning sign, even if recent weeks have looked relatively stable. Combining
these two types of signs gives the model a holistic picture of the project's status.</p>
      <p>It is worth noting that even by itself, the Transformer model outperformed LSTM in our
experiment. This is in line with trends in other fields: for long sequences, self-attention is often
more effective at extracting knowledge than recursive statefulness. On the other hand, for
relatively short sequences, our average project being 30 weeks, LSTM was also quite effective.
Its weakest point was on projects where problems matured gradually throughout the life cycle:
in such cases, Transformer more accurately interpreted the “slow accumulation” of risks, while
LSTM could underestimate long-standing signals.</p>
      <p>Our results are in line with the findings of Junwei Shi, Shiqi Wang, Pengfei Qu, Jianli Shao 2024,
who in their study presented an integrated prediction model combining LSTM and Transformer.
They first used LSTM to capture dependencies in input sequences and then applied
Transformer's self-focused mechanism to extract information from the sequence. Numerical
results showed that their model outperformed several comparative models such as
VMDInformer, Transformer, BiLSTM, and GPT3 in key metrics: root mean square error RMSE was
1.43 cm, mean absolute error MAE was 1.15 cm, standard deviation STD was 1.33 cm, and
correlation coefficient R was 0.96. In addition, their model reduced the training time by 8.2%
compared to the Transformer model, demonstrating higher forecasting accuracy and stability in
long-term forecasting. This confirms that the hybrid neural network methodology can be
universally useful for risk prediction tasks of various nature - from industrial accidents to
failures in IT projects.</p>
      <p>Also, the accuracy of ~90% we achieved for predicting troubled projects is higher than
reported in previous studies using traditional ML methods. For example, in Anita Kori, Gradient
Boosting for Interpretable Risk Assessment in Finance: A Study on Feature Importance and
Model Explainability (2024) examined the use of gradient boosting for risk assessment in the
financial sector. Our approach improves this performance, demonstrating the potential of deep
learning to outperform ensemble methods on complex heterogeneous project management data.</p>
      <p>The proposed model can be integrated into a project management support system to provide
managers with timely risk alerts. Unlike standard risk registers that rely on manual risk
identification and assessment, our model automatically collects signals from various project
metrics. It can, for example, assess the current status of a project once a week and display a
green/yellow/red risk indicator based on actual data. This will give managers the opportunity
to pay more attention to objectively risky projects and take action before the problem becomes
apparent through traditional means. Such a tool can be especially useful in portfolio
management, where there are dozens of projects - algorithmic analysis will allow you to identify
“projects in trouble” in time and focus resources on them.</p>
      <p>Despite the successful results, our approach has a number of limitations. First, a sufficient
amount of historical data is required to train a neural network. 50 projects is a relatively small
dataset in terms of deep learning. We were able to achieve high quality by using regularization
and because all projects were quite similar, within the same company. However, in general, for
different types of projects or other organizations, significantly more training examples would be
needed for the model to generalize well. This is a typical challenge when implementing AI in
project management - data is often confidential, heterogeneous, and not always standardized.</p>
      <p>Second, the model currently works like a black box. Although we can interpret the general
trends indicated by certain neurons, it is important to ensure that the predictions are explainable
for practical use. It's not enough for a project manager to get a risk estimate; it's also important
to understand what factors influenced that estimate. In this direction, it is possible to use AI
interpretation methods, such as analyzing the attention of the Transformer model, which
indicators and at what intervals received the greatest weight, or building simplified explanatory
models such as Local Interpretable Model-Agnostic Explanations for each forecast. Integration
of explanation mechanisms will increase user confidence in the system and facilitate its
implementation in real business processes.</p>
      <p>Another aspect is the adaptability of the model. The environment for implementing IT
projects can change: new methodologies, tools, practices. A model trained on past projects may
gradually lose relevance if it is not adapted to new data. Therefore, it is advisable to provide
mechanisms for online learning, for example, reviewing the model parameters after the
completion of each new project and adding it to the data set. In practice, this means that the risk
forecasting system should be constantly in operation, collecting feedback and updating.</p>
      <p>Finally, in the current implementation, we focused on the final project result as a risk
indicator. In reality, risk management is multidimensional: there are risks of different categories:
technical, financial, requirements, team risks, etc. A promising direction is to expand the model
to predict specific types of risks. For example, the model could provide estimates of: “probability
of failure to meet deadlines - 80%”, ‘probability of budget overruns - 30%’, ‘risk of outflow of key
team members - 10%’. This will require more detailed data and a multi-classification approach,
but will significantly increase the usefulness of the system, allowing proactive planning of
response measures to each risk.</p>
      <p>The results of our work open up several areas for development. First, as already mentioned,
it is worth exploring the integration of unstructured data into the model - texts such as team
comments, reports, correspondence, and even behavioral signals that may contain early
indicators of problems. Modern language models, such as BERT or GPT, combined with our
architecture, could allow us to analyze the broader context of the project. Secondly, it is
interesting to apply a transfer learning approach: for example, pre-train the Transformer
encoder on a large set of generic project data, perhaps from other companies or from related
domains, and then retrain it for a specific organization. This would help overcome data
limitations by feeding the model with generalized knowledge about patterns of successful and
problematic projects. Third, you can experiment with other architectures, such as using a
bidirectional LSTM or Bi-LSTM to account for both forward and backward dependencies in the
time series, or try transformer architectures optimized for time series, such as Temporal Fusion
Transformer. It is also promising to take into account the interrelationships between projects:
sometimes the risk of one project depends on another, for example, shared resources. This is
where graph neural networks could be useful for modeling portfolio risks.</p>
    </sec>
    <sec id="sec-4">
      <title>4. Conclusion</title>
      <p>This study developed and tested an approach to risk prediction in IT projects based on a hybrid
neural network that combines recurrent architecture and Transformer. The literature analysis
showed a growing interest in the use of AI in project management and revealed a lack of
specialized solutions specifically for risk prediction in the dynamics of an IT project. The
proposed model fills this gap by combining the strengths of RNNs, efficiency on sequential data
with short memory, and Transformer, the ability to model long-term and complex dependencies.</p>
      <p>Experimental results confirmed the effectiveness of the approach: the RNN-Transformer
model achieved 90% accuracy and an F1-measure of 0.90 in the task of classifying projects by
risk level, outperforming traditional methods and similar neural networks. This means that the
use of deep neural networks can significantly improve the reliability of early detection of
problematic projects.</p>
      <p>While the proposed hybrid RNN-Transformer model demonstrates superior performance in
capturing both sequential and contextual patterns in project documentation, we acknowledge
that its implementation may be challenging in resource-constrained environments. The model
was benchmarked against standard LSTM and BERT architectures using training times, GPU
memory usage, and inference latency. Results showed a moderate increase (15–20%) in
computational requirements over pure LSTM models, but significantly improved prediction
accuracy. To facilitate practical adoption, a lightweight distilled variant of the hybrid model is
currently under development, suitable for deployment in SMEs or organizations without
dedicated deep learning infrastructure.</p>
      <p>The practical significance of the results obtained is that such models can become the basis of
intelligent support systems for project managers. They are able to automatically analyze project
progress and warn of impending critical situations, which contributes to more proactive
management and successful achievement of project goals. Of course, the implementation of such
systems requires further adaptation and customization efforts, but the potential gains - reducing
failed projects, saving resources and time - make this area promising.</p>
      <p>In the future, it is planned to expand the study in several areas. First, to include more data
from different companies and heterogeneous projects in the analysis to test the generalizability
of the model and, if necessary, improve its architecture. Second, to pay attention to the model's
explainability by developing a module that would interpret its predictions in terms of specific
risk factors. Thirdly, explore the integration of the model into project management
environments, for example, create a plug-in for popular systems such as JIRA or MS Project to
evaluate its effectiveness in real time.</p>
      <p>The results confirm that the combination of modern artificial intelligence technologies with
classical management approaches allows to reach a new level of IT project management. Risk
prediction using neural networks is a step towards more sustainable and predictable projects,
where problems are not identified after the fact, but are anticipated and resolved in advance.
This, in turn, will help to increase the success rate of IT projects and more efficient use of IT
resources.</p>
      <p>Declaration on Generative AI
During the preparation of this work, the authors used ChatGPT in order to: Paraphrase and
reword. After using this tool/service, the authors reviewed and edited the content as needed and
takes full responsibility for the publication’s content.</p>
    </sec>
  </body>
  <back>
    <ref-list>
      <ref id="ref1">
        <mixed-citation>
          [1]
          <string-name>
            <given-names>O.</given-names>
            <surname>Matsiievskyi</surname>
          </string-name>
          ,
          <string-name>
            <given-names>T.</given-names>
            <surname>Honcharenko</surname>
          </string-name>
          ,
          <string-name>
            <given-names>O.</given-names>
            <surname>Solovei</surname>
          </string-name>
          ,
          <string-name>
            <given-names>T.</given-names>
            <surname>Liashchenko</surname>
          </string-name>
          ,
          <string-name>
            <given-names>I.</given-names>
            <surname>Achkasov</surname>
          </string-name>
          ,
          <string-name>
            <given-names>V.</given-names>
            <surname>Golenkov</surname>
          </string-name>
          ,
          <article-title>Using Artificial Intelligence to Convert Code to Another Programming Language</article-title>
          ,
          <source>in: 2024 IEEE 4th International Conference on Smart Information Systems and Technologies (SIST)</source>
          , IEEE,
          <year>2024</year>
          , pp.
          <fpage>379</fpage>
          -
          <lpage>385</lpage>
          . doi:
          <volume>10</volume>
          .1109/sist61555.
          <year>2024</year>
          .
          <volume>10629305</volume>
          .
        </mixed-citation>
      </ref>
      <ref id="ref2">
        <mixed-citation>
          [2]
          <string-name>
            <surname>Dolhopolov</surname>
            <given-names>S.</given-names>
          </string-name>
          ,
          <string-name>
            <surname>Honcharenko</surname>
            <given-names>T.</given-names>
          </string-name>
          ,
          <string-name>
            <surname>Terentyev</surname>
            <given-names>O.</given-names>
          </string-name>
          ,
          <string-name>
            <surname>Predun</surname>
            <given-names>K.</given-names>
          </string-name>
          and
          <string-name>
            <surname>Rosynskyi</surname>
            <given-names>A.</given-names>
          </string-name>
          ,
          <article-title>Information system of multi-stage analysis of the building of object models on a construction site</article-title>
          ,
          <source>IOP Conference Series: Earth and Environmental Science</source>
          ,
          <volume>1254</volume>
          (
          <year>2023</year>
          ) 012075, doi:10.1088/
          <fpage>1755</fpage>
          -1315/1254/1/012075.
        </mixed-citation>
      </ref>
      <ref id="ref3">
        <mixed-citation>
          [3]
          <string-name>
            <given-names>D.</given-names>
            <surname>Chernyshev</surname>
          </string-name>
          , G. Ryzhakova,
          <string-name>
            <given-names>T.</given-names>
            <surname>Honcharenko</surname>
          </string-name>
          ,
          <string-name>
            <given-names>H.</given-names>
            <surname>Petrenko</surname>
          </string-name>
          , I. Chupryna,
          <string-name>
            <given-names>N.</given-names>
            <surname>Reznik</surname>
          </string-name>
          ,
          <source>Digital Administration of the Project Based on the Concept of Smart Construction, Lecture Notes in Networks and Systems</source>
          , vol.
          <volume>495</volume>
          LNNS, pp.
          <fpage>1316</fpage>
          -
          <lpage>1331</lpage>
          ,
          <year>2023</year>
          , International Conference on Business and Technology,
          <string-name>
            <surname>ICBT</surname>
          </string-name>
          <year>2021</year>
          , DOI: 10.1007/978-3-
          <fpage>031</fpage>
          -08954-1_
          <fpage>114</fpage>
          .
        </mixed-citation>
      </ref>
      <ref id="ref4">
        <mixed-citation>
          [4]
          <string-name>
            <given-names>S. R.</given-names>
            <surname>Bauskar</surname>
          </string-name>
          ,
          <string-name>
            <given-names>C. R.</given-names>
            <surname>Madhavaram</surname>
          </string-name>
          ,
          <string-name>
            <given-names>E. P.</given-names>
            <surname>Galla</surname>
          </string-name>
          ,
          <string-name>
            <given-names>J. R.</given-names>
            <surname>Sunkara</surname>
          </string-name>
          ,
          <string-name>
            <given-names>H. K.</given-names>
            <surname>Gollangi</surname>
          </string-name>
          ,
          <string-name>
            <given-names>S. K.</given-names>
            <surname>Rajaram</surname>
          </string-name>
          ,
          <article-title>Predictive Analytics for Project Risk Management Using Machine Learning, (</article-title>
          <year>2024</year>
          )
          <fpage>566</fpage>
          -
          <lpage>580</lpage>
          . doi:
          <volume>10</volume>
          .4236/jdaip.
          <year>2024</year>
          .
          <volume>124030</volume>
          .
        </mixed-citation>
      </ref>
      <ref id="ref5">
        <mixed-citation>
          [5]
          <string-name>
            <given-names>L. K.</given-names>
            <surname>Aggabou</surname>
          </string-name>
          ,
          <string-name>
            <given-names>B.</given-names>
            <surname>Lakehal</surname>
          </string-name>
          ,
          <string-name>
            <given-names>M.</given-names>
            <surname>Mouda</surname>
          </string-name>
          ,
          <article-title>An Artificial Neural Network Approach for Construction Project Risk Management</article-title>
          ,
          <source>Int. J. Saf. Secur. Eng. 14.2</source>
          (
          <year>2024</year>
          )
          <fpage>553</fpage>
          -
          <lpage>561</lpage>
          . doi:
          <volume>10</volume>
          .18280/ijsse.140222.
        </mixed-citation>
      </ref>
    </ref-list>